Paul Tomory
Analyst · JPMorgan
Thank you, Andrea. Today, rather than a detailed review of each operation, I want to discuss a few key highlights and will be happy to take questions. At Tasiast, as Paul mentioned, the mill is up and running. The neutron screen and other key items arrived on site as scheduled and were installed last month. The mill is periodically achieving pre-fire throughput rates as planned. And we are in the process of ramping up and expect to achieve these levels on a sustained basis with the goal of achieving full production rates, throughput rates in December. While the mid -- while the mill is being [fed we’re] (ph) ahead of schedule, we've elected to use lower grade ore during the ramp up period, so the initial production will be modest. Furthermore, during this initial period where we're replenishing inventory on carbon following its depletion in the weeks after the fire. All told we expect to produce approximately 15,000 ounces during the fourth quarter and most importantly, exit the year with throughput rates of around 18,000 tons per day. We are on track initially with the projector to hit 21,000 tons per day by the end of the first quarter. I'm also pleased to say that the middle repair costs of approximately $20 million dollars were considerably lower than our initial estimates. Mining activities has continued through the quarter and as Paul mentioned, by the end of the year, we expect to have built high grade stockpiles. Mining rates during the quarter are lower than initially anticipated, as a result of challenges in drilling and blasting. However, these issues are being addressed and we remain on track to achieve strong production Tasiast next year, in line with our technical report and our studies. The 24k project is also progressing as planned with completion expected in mid '23. Moving to Round Mountain, the optimization study, which includes Phase S, is on schedule and we expect it to be completed in the first half of next year. The Geotech work is advancing well and will provide the data needed to make conclusive decisions throughout the ultimate slow bangle, as well -- as any needed to step out some berms. And to-date the study is not presenting any significant surprises. In the quarter, we also completed the relocation of the waste pile from the top of the pit to further stabilize the wall. Moving to the results of the Udinsk PFS, this study confirms the projects expected stronger turns. The conclusion of the PFS and combination of more than 55,000 meters of infill and Geotech drilling has allowed us to convert approximately 3 million ounces from resources to reserves. Most of the study outcomes are in line with the assumption of the time of the acquisition with some improvements in recovery and production. Capex however, has increased by approximately a $150 million., broken down roughly it follows in thirds. First third, approximately from an inflation. Another third is from value-added decisions that have improved the NPV become with an added capital cost, for example, a finer crush for better recovery. And finally, a third from scope changes including earthworks in camp facilities, which were costlier than initially anticipated. As Paul mentioned, we also completed the FS on Lobo-Marte. The study confirmed the project's key parameters, pit optimization work, and infill drilling completed over the past few years resulted in increased global markets reserves by approximately 300,000 ounces. And to its resources by 600 thousand as compared to the PFS. The estimate for initial capital increased by approximately 8 % compared to previous study but mostly due to the reclassification of certain plant elements from sustaining to initial. As such, the NPV, is in the line. We completed the study with key environmental and community considerations as part of the project design, and continue to advance the EIA submission. Lobo-Marte will now enter a lengthy permitting phase, which we expect will take 3 years. Construction decision will not be made until after that with construction beginning no earlier than 2025. Mining at Lobo-Marte, will not begin until permitting has concluded and we've completed mining at La Coipa as the 2 sites currently plan to use the same water source. We continue to see further potential to extend La Coipa by bringing satellite deposits into the mine plan and we've made significant progress on them. Therefore, we may ultimately push out Lobo-Marte to accommodate more production at La Coipa, which would allow us to further leverage our capital investments in Chile and to extend our overall production profile in that country. And with that, I will turn it back to Paul.