Thanks, Andrea. This morning, I'll provide key updates on our operations and projects, discuss our production outlook, and share some highlights from our reserves and resources update and exploration results. Before that, it's important to know we continue to manage the evolving challenges presented by COVID. And while our operations continue to track well against our longer term plans, we experienced some disruptions beginning late last year and into early part of this year related to the Omicron variant. Well, the severity of the cases has been very low, we saw increased absenteeism, which impacted productivity at certain sites. As Paul mentioned, this has been reflected in our 2022 production guidance, which I will discuss shortly. With respect to our plans and projects going forward, while we do our best to mitigate the effects of COVID inflation, we are not immune to these global challenges, and therefore the timing results of outlook is subject to change. Looking back on 2021, I'd like to start with an update of Tasiast. The restart of the mill went as planned and we expect to produce more than 600,000 ounces per annum over the next several years. During the fourth quarter, we produced 50,000 ounces of expected while replenishing inventory on carbon. And towards the end of the quarter, the mill achieved pre-fire throughput rates of 80,000 tonnes per day. And as Paul as mentioned, we've had a few days with 21,000 tonnes already. The mining rate improved in the fourth quarter, however, Omicron-related absenteeism has somewhat hindered progress in sustaining these rates. These issues are now subsiding and we expect to largely catch up on mining during 2022. Moving on to the 24k project, the first phase of spent 21,000 tonnes pounds per day is now 98% complete, and we expect the project to finish under budget despite challenging conditions presented during the pandemic. We expect to reach 21,000 tonnes per day on a sustained basis by the end of the first quarter as planned. The second phase of the project is also advancing well with procurement of all major equipment complete and on track to reach 24,000 tonnes per day by mid-2023. Regarding our production outlook, I like to provide some additional context on some of the changes. We previously guided to production range with a midpoint of 2.7 million ounces in 2022 and have adjusted that to 2.65 million ounces plus/minus 5%. This 50,000 ounce change can be explained roughly in equal parts, by the impact of Omicron and lower expected production from the vantage pad at Bald Mountain. As Paul mentioned, growth profile for 2020 was weighted towards the back half of the year as La Ciopa and Tasiast will be ramping up. In addition, Paracatu's production is expected to increase in the second half of the year as grades improve. First quarter raise at Paracatu are expected to be the low severe as we plan on processing lower grade stockpile material, while mining activities focused on stripping. For 2023, we previously guided a production midpoint of 2.9 million ounces and have adjusted this to 2.8 million. There are a number of puts and takes across the portfolio, but this adjustment can be largely explained by three factors. First, we've re-sequenced the mine plan at La Coipa and Chirano to accommodate mine life extension. Second, last year, we made value add decisions at La Coipa and Bald Mountain that resulted in a deferral of production. At La Coipa we extended the mine life with the addition of Puren. The plan is to blend Puren ore with Phase 7 ore for optimal performance in the mill, which is expected to lower the feed grade in 2023, leading to a deferral of approximately 40,000 ounces. However, this phase of Puren is expected to add approximately 200,000 ounces to life of mine production and extend La Coipa's mine life from 2024 to 2026. At Bald Mountain, we approved extensions at a few of the north area pits, which resulted in resequencing of mine time, leading to a deferral of 30,000 ounces in 2023, but adding 60,000 ounces of total production. Lastly, as noted last year, the well mitigation efforts around Mountain deferred the high production years due to additional stringent requirements. While the impact of this deferral was within our plus/minus 5% range around the time of the guidance, taken with these other developers and update to our midpoint was warranted. Looking at the 2024, we expect our existing operations to support another strong year with production of 2.6 million ounces. Notably, this excludes Manh Choh, which we continue to advance and could ultimately contribute modestly to 2024 production. Moving now to our reserves and resources, we are pleased to have reported a net addition of 2.7 million ounces proven and probable reserves, compared with 2020, taking total reserves up to approximately 33 million ounces, while increasing our reserve grade by 4%. The biggest contributors to the increase was Udinsk, where we successfully converted 3 million ounces from resources to reserves with the completion of our PFS during the fourth quarter. Additionally, Round Mountain added approximately 800,000 ounces net of depletion, mostly due to Phase S. Elsewhere in the portfolio, we were able to offset depletion of Fort Knox with a contribution of approximately 200,000 ounces from the Gil Satellite project and added over 300,000 ounces of Lobo-Marte for the completion of the feasibility study. Measured and Indicated resources declined from approximately 32 million ounces at the end of 2020 to 29 million ounces at the end of 2021. And this decrease is mainly due to reserve conversions, partially offset by increases at Chirano, La Coipa and Lobo-Marte. Next, I want to provide a brief update on the ongoing optimization work at Round Mountain. Starting with Phase S, we have been very encouraged by the work and as I just mentioned, have converted this Phase to reserves and are now working on how to sequence into the mine plan. With respect to Phase W, the ongoing geotechnical work has introduced the potential need for shallower slopes over more extensive areas than previously identified, which may affect Round Mountains annual level of production posted 2024. At Phase X, we've had very encouraging drill results. In fact, four of our vessels last year across the company were at Phase X, which confirmed continuity of several structural domains. As a result of these new developments, the optimization study is now evaluating additional alternatives, which include a modified open pit sequence of Phase W and S and the potential for underground mining proportions of Phase W, leading into Phase X. An early stage scenario for underground mining proportions of Phase W could potentially benefit the economics of Phase X, and could also reduce capital intensity, as well as our greenhouse gas emissions compared to an open pit scenario with a shallower wide angle. These new considerations will require additional time to work through and we now expect the optimization studies to be completed in the second half rather than the first. Turning out to exploration, I will discuss some highlights from last year on areas of focus for this year. During the past year, we completed over 230,000 metres of drilling and continue to focus within the footprint of existing infrastructure. In Russia, we encountered several high-grade targets in a Kupol synergy zone, which is the 130 kilometre radius around Kupol. At [indiscernible] the results from drilling have delineated high-grade veins with attractive widths in the Arykvaam mineralized structure. The zone of mineralization has been defined across a strike length of approximately 1.4 kilometres with significant further potential at depth and along strike. At Round Mountain, as I mentioned, we encountered an encouraging results of Phase W and confirm continuation of mineralization beyond the current resource pitch show. We plan to construct an expiration drift this year to continue evaluating the potential. At Gold Hill a new high-grade vein located over 300 metres from the current resources discovered. We plan to continue to test this new vein and potential for extension that Gold Hill later in the year. Lastly, at Curlew, the drilling focus on areas around the historic K2 mine sight, which is located approximately 35 kilometres from the Kettle River mill. During the last year, the development of the new underground risks are completed, leading to the exposure for new veins which will allow us to continue underground drilling. Before turning the call back to Paul, I'd like to provide an update on our La Coipa Restart Project and discuss the recent mine life extension. I'm pleased to report the project is expected finish on time and on budget, with modest production expected in the first quarter. Commissioning of the plant is well underway and we've started building a crushed ore stockpile. We expect to ramp up production over the first half this year to reach full production levels by mid-year. The addition of the first phase of Puren combined with a successful mine plan optimization Phase 7 has increased life in mine production by 45% to approximately 1 million ounces. We continue to look for additional opportunities to extend mine life and have begun preliminary discussions with Codelco, our joint venture partner, about another phase of Puren. With a number of satellite pits on the property, we remain very encouraged that we can continue to extend life at La Coipa into the late 2020s. And with that, I'll turn the call back to Paul.