Paul Tomory
Analyst · JPMorgan. Your line is open
Thank you, Andrea. I will provide a brief update on the impacts from COVID, followed by an update on our operations, projects and exploration programs. As Paul mentioned, COVID restrictions are generally lifting around the world. And most of our operations are slowly returning to normal, with some exceptions. Thanks to our employees, operating communities and host governments and our operations have performed very well throughout this pandemic. I will begin by providing an update on the Tasiast mill repairs. Most importantly, over the last few days, the mill has been turned and we are now confident that the gearless motor drive, the trunnion bearings and mill shell are in good shape. To note, we have included a link to a video of the mill restart test in our press release. Based on this, we are confident that the mill will restart in the fourth quarter. A new trommel screen has been ordered and the anticipated delivery date supports the planned mill restart timeline. Following the installation of the trommel screen, we expect to be able to resume operations at full capacity, essentially right away without a significant ramp up period. We remain confident in our ability to meet 2022 production targets as a high grade stockpile that we will build will be available at startup. The 21k project is now 90% complete. Commissioning activities of the power plant have begun and we expect it to be operational in the late part of Q4 and we expect to reach 21,000 tons per day in the first quarter of 2022. Additionally, we are exploring ways to potentially shorten the time needed to reach 24,000 tons per day by taking advantage of mill downtime to advance on the project tie-in sooner. Moving to Brazil, Paracatu had a good first half overall. The mine produced 151,000 ounces, an increase of 24,000 over Q1 due primarily to the timing of ounces processed through the mill. Higher cash costs compared with Q1 are attributed principally to an isolated incident of unplanned maintenance, inflationary pressures, particularly on consumables, labor and diesel and higher power costs due to drought and the government’s response restricting hydropower generation, which has resulted in increased exposure to more expensive spot power purchases. On this issue, it’s worth noting that while drought conditions are prevalent in affecting power generation, it is not impacting water balance at Paracatu. In Russia, Kupol delivered another good quarter. Results were largely in line with Q1 as the transition to a narrower vein mining continues to progress as planned. We saw lower grades compared to previous quarter in Q2 of last year due to planned mine sequencing at Kupol combined with lower grade stockpiles from Dvoinoye. We expect grades to stay around these levels for the remainder of the year. Turning to Nevada, at Round Mountain, implementation of the revised mine plan is proceeding well and Q2 production was in line with our expectations. The relocation of the waste pile at the top of the pit continued during the quarter and should be completed next month. Fortunately, this historic waste pile proved to be mineralized, covering the costs of the re-handling. Mitigation efforts have stabilized the wall and significant progress has been made on further dewatering. The overall optimization study, including opportunities for the Phase S pushback is progressing well and on schedule to be completed early next year. Production was lower quarter-over-quarter as a result of our focus on mitigating the wall instability, while costs were largely in line. Turning to our other operations, Fort Knox performed well during the second quarter as production increased compared to Q1 due to an increase in ounces repaired from the new Barnes Creek heap leach. Cash costs remained high due to higher operating waste mine, but decreased year-over-year due to more ounces produced in the new heap leach. Bald Mountain’s production was lower compared to the previous quarter due to the timing of ounces recovered from the heap as we mined through some carbonaceous material in the Vantage pit at the beginning of the quarter. We expect stronger production in the second half. Higher cash costs compared to previous quarter were due to lower production and higher fuel costs. Chirano has also delivered a good performance so far this year. Production was slightly lower than Q1 mainly due to lower grades from the underground mine, but is largely in line year-over-year. And the mine continues to generate positive free cash flow. Moving on to our projects, as Paul mentioned, the Manh Choh scoping study was completed this quarter on schedule. The results confirm the project is low risk, low cost, high grade high return addition to our Fort Knox mine. Many of the key metrics in the study remain comparable to our view at the time of the acquisition, including grades, recoveries, life of mine production of approximately 1 million ounces, with first production expected in 2024. Capital cost estimates, however, have increased by approximately $50 million to approximately $150 million on a 100% basis. The increase is largely due to strategic decisions that are expected to de-risk the project and improve operational efficiencies, including reducing the use of contractors. In addition, a better understanding of the project site conditions, particularly topography and environment, contributed to this increased capital. The project is moving to an FS and we expect to report those results by the end of 2022. Our other projects are advancing well. Development work on the Gil satellite pits, located approximately 13 kilometers east of Fort Knox, is proceeding as planned and is on track for first production later this year. La Coipa remains on budget and on track for first production in mid ‘22 with fleet refurbishments now complete. Pre-stripping, plant refurbishment and mine road construction are also progressing very well. The Lobo-Marte FS is on schedule for completion in Q4 of this year, while permitting and community relations continue to advance. Udinsk PFS is still expected to be completed by year end in support of a reserve update. Infrastructure work at site has commenced, including the establishment of camp facilities. First production at Udinsk is still anticipated in 2025. With respect to exploration across the company, we continue to focus on promising targets around current operations in areas, where existing infrastructure can be leveraged, with the goal of extending mine life and adding to our mineral reserve and resource estimates. At Kupol, the exploration program targeting mine life extension is proceeding as planned. Targets at the south end of the Kupol vein were tested, intersecting narrow, but high grade veins. Importantly, exploration of Cancer established at Kayenmyvaam and Kavralyanskaya within the Kupol Synergy Zone, yielding high grade results in both areas. At Chirano, promising results during the first half of the year were encountered as we continue to target multiyear mine life extensions and additions to its mineral resource estimates at year end. Underground resource upgrade and definition drilling at Suraw and Tano located additional high grade pods and underground drilling was carried out at Suraw, Akoti South and Tano and surface drilling at the Mamnao West ore bodies. Development of an expiration drift to provide optimized drilling positions to target the over high grade plunging shoot is ongoing and is expected to be completed in the third quarter. The results of the first hold exceeded expectations with mineralized with greater than previously interpreted. Drilling at Akoti South has extended known mineralization to the immediate south of the reserve area, while at Tano, two mineralized west grades have been identified. At Udinsk, exploration activity is focused on infill drilling and completing the PFS geotechnical work. Additionally, on the larger Chulbatkan property, exploration drilling has commenced 2 to 5 kilometers to the northeast of the Udinsk resource pit, along the principal Chulbatkan float where mineralization has been encountered. At Round Mountain, exploration activities at Phase X focus on infill drilling and extending the known mineralization. We also work to improve the geologic model and assess mine planning options with the goal of delineating high grade material for potential underground mining and results continue to be encouraging. Lastly, at Curlew, exploration activities continue to target incremental high margin answers proximal to the K2 and K5 deposits by constructing a series of exploration drifts to explore the highly prospective area. Rehabilitation and development is ahead of schedule, with underground drilling to commence in the third quarter and continue well into next year. To wrap up on operations and projects, our priorities continue to be the health and safety of our employees, our social license to operate and the wellbeing of our communities and stakeholders, delivering strong consistent operating results and delivering our projects on time and on budget. And with that, I will turn the call back to Paul.