Thanks, Andrea. I'll be walking you through some of the key highlights of our global portfolio, touching on both operating performance and project updates. I'll start with Tasiast, which as Paul noted, continue to benefit from the excellent performance of the phase 1 expansion and the data on this slide really shows it all. Throughput averaged over 15,000 tons per day in the quarter and also through April. Outside of a planned shut down for site realign and inspection. The culmination of excellent mill throughput, improving grade, better recoveries resulted in a second consecutive quarter of record production. We're also making progress on the cost side, as cost of sales per ounce decreased by 20% compared to the fourth quarter, largely as a result of lower contractor expenses and maintenance supplies. And we are ramping up our continuous improvement initiatives at the site targeting areas such as operational improvements in mining, milling and maintenance, our overall approach to maintenance strategy and a review of all existing contracts. Through these efforts, we're targeting meaningful operational costs improvements. As Paul mentioned, the strong performance of phase 1 is leading us to rethink positively what the most capital efficient next step for Tasiast will be. One of the possible outcomes we're exploring is an incremental step above 20,000 tons per day, through debottlenecking continuous improvement, which we expect to result in significant capital savings versus the 30K plan. One of the main drivers for our thinking is that the grinding circuit has been able to consistently maintain a very fine grind with acceptable energy consumption. This final grind has allowed us to maintain very high recovery levels with shorter leach times. This option has a potential to achieve attractive cost metrics with substantially lower capital expenditures and enhanced economic returns. And we're targeting the second half of this year to complete our evaluation of this alternative. Moving on to Paracatu, which started the year off strongly and achieved record production and a 15% reduction in cost of sales per ounce, compared to Q4. The factors driving the cost and performance improvements that we've been realizing for Paracatu for the past few quarters include, first, the results of the asset optimization work we initiated last year, which has significantly improved our ability to predict grade recovery, ore hardness and throughput, and has made it possible for us to react to changing ore characteristics in real time, resulting in greater efficiency in the mill and also improved recovery. Second, our continuous improvement efforts have resulted in increased mine and mill efficiencies and lower operating costs. And thirdly, we made enhancements to mine infrastructure, including the rainfall mitigation initiatives as well as investments in renewable energy, which are helping to reduce power costs. Overall, we're very pleased with Paracatu’s performance and expect 2019 to be a strong year for the operation. Turning out to our mines in Nevada, the Round Mountain performed in line with our expectations during the quarter, although the production was lower quarter over quarter. This was largely related to mining harder ore and fewer heap leach ounces produced. In the first quarter, Round Mountain’s cost of sales per ounce were 12% lower compared to the fourth quarter, largely as a result of a decrease in operating waste mine, as mining activities were principally focused on capital stripping in support of the Phase W project where we are making excellent progress. We've encountered Phase W ore ahead of schedule and started stacking it on the completed heap leach bed. And as Paul mentioned, we've advanced commissioning of the process circuit in the end of March ahead of schedule. Initial solution is being applied to the heap leach in advance of full completion of the vertical CIC plant, which is now 80% complete. The Vantage project of Bald Mountain is also well advanced with the heap leach pad approximately 90% complete. We're stacking ore on the pad and applying solution ahead of full completion of the vertical CIC plant, which is approximately 70% complete. This site experienced unusually severe winter weather during the quarter, which challenged both Bald’s operational performance, as well as the scheduling costs on the Vantage project. The final cost of the project is now expected to be approximately $130 million, which also resulted from higher than anticipated construction contract rates and issues in the supply of the fabricated components. Commissioning of the processor could begin as planned at the end the first quarter, and we expect activities to ramp up through the balance of the year. Moving on to Fort Knox in Alaska, we indicated in our guidance that we anticipated production will be lower in Q1 and Fort Knox’s results were in line with that expectations. Key factors impacting Fort Knox are the impacts of the wall failure, which have been more challenging than originally anticipated. And Fort Knox has received a historic amount of precipitation over the past two years, particularly in the second half of last year. This has created further challenges with respect to geotechnical instability and our ability to manage groundwater levels beside. And finally, as we stack up the flanks of the value of the existing Walter Creek heap leach, recovery timing has been impacted. The results of these combined factors is that we now anticipate that certain ounces will come into the mine plant later than originally expected. We're building the new Barnes Creek heap leach pad as part of the Gilmore project, which will help mitigate some of these issues as we will be stalking closer to the liner starting in the late part of 2020. We continue to assess the impact of these challenges and are working to mitigate them as we can with a focus on optimizing our strategies for cash flow. One strategy we are implementing is running the mill at reduced rates in order to preserve the remaining tailings capacity for the best grade and material. The Gilmore project is not expected to be impacted by these factors, and is proceeding on budget and on schedule with startup of stripping planned for the third quarter. In terms of 2019 performance, we expect to see production increase from Q1 levels over the balance of the year. Turning now to our Chile projects, we completed the Lobo-Marte scoping study in the first quarter as planned. The study contemplates the heap leach operation using SART technology with operations starting at the end of La Coipa’s mine life. SART is a proven technology that we have previously used at Maricunga with positive results. It's still early days where the study contemplates a mine life of over 10 years, with total production of 4.1 million ounces at an average grade of 1.2 grams per ton. Our scoping level capital estimate is $750 million plus or minus 20% and we anticipate a three year construction timeline for the project once permitted and approved. On the back of these encouraging results, we are advancing Lobo-Marte to PFS and permitting efforts are now underway. Recall that we are considering Lobo-Marte in conjunction with the La Coipa restart project and a feasibility study for La Coipa is progressing well and we are on track to complete it in the third quarter. To wrap up on our operations and projects, our priorities continue to be maintaining our excellent safety record, delivering strong consistent operating results, managing our costs and delivering our projects on time and on budget. And with that, I'll turn it back to Paul.