Doug Reddy
Analyst · RBC. Please go ahead
Thanks, Keith. We are now on Slide 10 of the presentation. At the Mesquite mine, gold production was within guidance at 88,000 ounces and below all in sustaining guidance at $1251 per ounce for the year. The mine stacked a large tonnage of ore in both Q3 and Q4 and it took a while to bring all of that ore under leach. This gold inventory was being drawn down in Q4 and it will continue into 2024 with most of the gold production in the first half of the year coming from the ore that's already stacked. Tripping of the Ginger pit is now the main focus for mining. The majority of the ore from that pit will be coming online in 2025. Ginger was a new discovery in 2023 and it's quickly been incorporated into the overall mine plan. At Mesquite the company continues working on developing additional resources and permitting to extend the life of the mine. At Castle Mountain, gold production was below guidance at 21,000 ounces and was within all-in sustaining cost guidance at $1899 per ounce for the year. Phase 1 is a small operation and that involves mining and processing of low-grade mineralized dump material. This material needs to be removed from the old open pits in anticipation of mining higher grade in situ ore during the Phase 2 expansion. Crushing agglomeration modifications were completed in 2023 and the contractor also increased their throughput by about 46%. But we still didn't get to the level of crushed material being fed through the crush and agglomeration system that we wanted. So we'll continue to work on this and also on cost reductions in 2024. At Los Filos, gold production was below guidance at 159,000 ounces and over the all-in sustaining cost guidance at $1890 per ounce for the year. In 2023, a productivity improvement program in both the open pit and underground mines was implemented and that yielded an increase in overall ore production. However, in spite of the additional ounces that were above the mine plant, being mined and stacked, Leach pad issues resulted in slower and lower recoveries and there was an increase in the inventory of ounces accumulated on the pad. The issues were resolved during the second half of the year and the drawdown of the ounces continued through Q4 and continues into Q1 this year. During 2024, we'll be mining from the Los Filos, Bermejal and Guadalupe open pits and also from the Los Filos underground. All of the ore goes on to the existing heapage pad and we're continuing optimization efforts to improve efficiencies and reduce costs. Longer term we'd like to expand the mine and to build the carbon and leach plant so we can process higher grade ore and that would be a 10,000 ton per day plant that we'd like to build. But we're not going to be able to make that investment unless we've been able to negotiate new agreements with our community partners so that we can ensure long term economic viability and stability for the mine. We started the dialogue in the Q4 of last year, and we're certainly hopeful that we'll be able to find a long-term solution so that we can invest on the mine, but as you will in the MD&A we have stated that we were not able to find a long-term solution, we may need to suspend the mine at least until new agreements are in place so that we can enter into a new phase of life for Los Filos. On to the next page, in Brazil, the Aurizona mine gold production was within guidance at 121,000 ounces and within on sustaining guidance at $1440 per ounce for the year. In 2023, we had a record year for the total tonnes being moved by the mine -- in the mine. We also completed the new tailing storage facility which is now in use that's in Vene 2 and we've begun decommissioning of the Vene 1 tailing storage facility. This year we're going to be mining from the Piaba pit, the Piaba East pit and also from the new Tatajuba open pit which is on the same trend into the west of Piaba. We will be finishing the installation of a pebble crusher that's to maintain throughput at 8,000 tonnes a day. Fresh rock will be about 67% of plant feed in 2024. We have the permits that we need to start the development of the portal and ramp to access the Piaba underground and we will start that work in the second half of the year. That's going to let us get underground to do some bulk sampling and underground drilling and the portal will be sized ultimately to be usable as a production decline for underground operations. At the Fazenda mine, we had another good year achieving guidance with 66,000 ounces produced, but coming in slightly above the all-in sustaining cost guidance at $1448 per ounce. Plant feed for 2024 will be 35% from open pit and 65% from underground. And I do note that the team is evaluating the opportunity for a larger open pit over the center portion of the main mineralized trend. So hopefully we'll talk about that more later on this year. Drilling programs continue to place reserves in the underground year on year and that's been a consistent annual program that we've had the effort to annually replace what we mine underground. And a TSF raise is in progress at Fazenda and will be completed in Q2. At RDM, gold production was within guidance at 53,000 ounces and below the all-in sustaining guidance at $1612 per ounce for the year. In 2023 we continued mining with a rental and owner fleet that's being operated by an owner’s team. We're doing this year we were continuing on with the stripping campaign that will allow us to get into a section of higher-grade ore at the bottom of the pit. When we expect full access to be, at the start of 2025. We're also doing some input dumping that should help us to reduce some costs and we're planning to implement dry stack tailings in the second half of the year. At Santa Luz, gold production was below guidance at 57,000 ounces and within the all-in sustaining cost guidance at $1834 per ounce for the year. The mine had a good first half of the year, but began to have problems with pollution and electro winning in the Q4 that impacted our resin activity and the recoveries. These issues were being addressed as we came into the end of the year and into the new year. In 2024, we will be making some plant modifications and those will be to increase mill throughput and improve recoveries. One of them is a desliming circuit that will be to reduce the total organic content and improve overall gold recovery by about 6%. We will be installing a new trunnion that's to increase mill throughput that should be about more than 10% increase in the throughput. And we are optimistic that these improvements overall will help stabilize the recoveries in throughput. We have the objective of achieving recoveries over 73% or higher for the second half of the year. We're also doing a TSF at Santa Luz that should be completed by the start of Q2. Okay, move on to Greenstone. So obviously a cornerstone asset for Equinox. It's got a great production profile, high average grade for an open pit, 1.27 grams and we'll be averaging 400,000 ounces a year on a 100% basis. So that gives us about 240,000 ounces coming to Equinox Gold given our 60% interest in the project. Plant throughput at 27,000 tonnes per day, I mean that's where we'll be ramping up to. And during that time we'll be evaluating what will be needed to be able to take it up to 30,000 tonnes a day which is the permitted rate for the mill. With a 14-year life, it's a good initial mine life, but we do also see opportunities to add from areas that are immediately adjacent to the current pit design plus from an underground opportunity and also other deposits on the property. So we look forward to being able to augment the mine plan over the coming years. I just visited site and just in transit back to the corporate office. It's an exciting time and I will commend the construction team after 25 months of construction. They have kept to the overall schedule of H1 being -- H1 2024 being the Gold Port. It's a really good sight to see. And when you look at the crushing circuit or storage dome, they've been in hot commissioning essentially they're ready to go. There's ore sitting in the or storage dome ready to be used. ball mills, HPGR, leach tanks and thickeners they're all in wet commissioning. And the tailings facility is permitted and ready for use. The mining flight fleet is 14 trucks, three shovels, current mining rates above 90,000 tonnes a day. And it will be ramped up to 180,000 tonnes per day as we bring on additional trucks and bring them into service. Stockpile for start up, currently it's just over 1.5 million tonnes. I know there's another 0.25 million tonnes broken in the pit. So they're doing a good job of putting everything in place ready for hot commissioning and ramp up. And we received all the permits required for the commissioning activities and overall things are going well. We're really looking forward to being able to announce first gold pour in the next few months and then advancing through ramp up in commercial production and onwards. So, with that, I'll hand it back to Greg.