Doug Reddy
Analyst · RBC. Please go ahead
Thanks, Pete. We're on Slide 7 in the presentation. At Mesquite, during Q3, the mine switched from waste stripping to ore movement and stacked 7.6 million tonnes on the leach pad. The strip ratio reduced from 2.0 in Q2 to 0.6 in Q3. Those stack down has begun to come under leach during the quarter. So, now we're waiting for them to start coming off the pad in Q4. Early in the quarter, they're actually in the end of Q2 and into start of Q3, there were issues with precipitation of a magnesium silicate and also low pH levels were caused by - releaching of some older areas of the pad. Both of those were addressed and resolved. During the quarter, the site has also been working on our plan to mine the Ginger deposit, which is a new zone that's next to the Brownie pit. So, we look forward to seeing how Ginger can come into our mine plan going forward. At Castle Mountain, crushing and agglomeration throughput continues to improve. We were at 67% of the ore being crushed before its being stacked. We continue to make up the difference with the run of mine ore, which does have a lower or slower percolation rate and a lower overall recovery. We are working on additional modifications to the crusher that will - we'll end up with improving ore throughput. Scaling on the drip lines on the leach pads, did occur at Castle Mountain in the quarter, and those have been addressed and resolved. At Los Filos, our productivity improvement program in the open pits and the underground mines has been underway from Q1 onwards. That program has seen a strong increase in the total tonnes being moved year-on-year and a reduction in dilution from the underground and at the same time, delivering more ounces overall to the pads. 80% of the ore is coming from Los Filos, Bermejal and Guadalupe open pits and the underground ore is from the Los Filos underground only. On the leach pad, we had delays in gold recovery, as noted in Q1 and Q2, but we're starting to see those ounces draw down in Q3. One of the areas was previously reported problem with broken leach pad piping, that was fixed, and we believe all of those ounces have now come off the pad in that area. We also had some areas with carbonate precipitation in an area where the pH had gotten very high and that was in preparation for the rainy season, where there was a drawdown of the overall solution on the pad. The area with the carbonate precipitation has now been turned and is being released. So that's been addressed. And then the higher grade ore with copper content continues to be separated, that receives a higher cyanide dosage and the long leach cycle time and for clarity, this impacts less than 14% of the recoverable ounces that have been stacked year-to-date. More recently, the mine sustained no damage, as a result of the hurricane that devastated the coastal region around Acapulco. Our employees at Los Filos have initiated a voluntary donations campaign that's in an effort, to support the affected families in Acapulco and other impacted areas and Equinox Gold will be supporting this effort. On the next page, in Brazil, all of our mines have had tailing storage facility construction either recently completed, or currently underway. So as Pete noted, this is the time of the year where we do the big push in all of our tailings facilities. And that's reflected in our sustaining capital expenditures for each of these mines. At Aurizona, Q3 production was higher than the prior quarter as they mine more tonnes and had access to higher grades. We continue mining with a second contractor on the site, that's to help move more waste and help build up an ore stock or stockpile for the coming rainy season. Currently, we're over 400,000 tonnes on the stockpile. We've largely caught up on waste movement with almost 8 million tonnes being moved in the quarter. Fazenda was mining from a combination of open pit and underground sources. Underground mining was up on both tonnes and grade in the quarter and the feed grades going into the plant, plus the plant throughput was above plan. So a very good quarter for Fazenda. Drilling was over 16,000 meters in the quarter. This is in the underground. That brings our underground drilling to over 39,000 meters year-to-date, that's focused on reserve replacement. That's been a successful program for the last half dozen years, and it's looking to be the same for this year as well. Exploration overall in the Fazenda, Santa Luz, Greenstone Belt continues on several promising targets. At RDM, the mine achieved its highest quarterly gold production since Q4 of 2020, primarily due to sending higher grade in situ ore to the plant. You'll recall that much of the previous year, we were supplementing feed to the plant with low-grade stockpiles. So we've been able to focus more on the in-situ or the RDM team has been doing a great job in mining with owner-operated equipment, and that's a combination of our trucks plus additional rented trucks. RDM is also in the permitting process for a filtered tailings storage facility that was submitted at the start of the year. So, we're looking for that to come through, sometime at the end of the year or into the New Year, but it doesn't have an impact. We have sufficient space to carry on in any case. Santa Luz continues to work on changes to overall recoveries. They were running at 67% in the quarter. We've been running just size 70% in October. So it's the small changes that make a difference at Santa Luz. I'll note that in the quarter, the total organic carbon content of the plant feed was running higher than planned. While we did have recoveries well into the mid-70s, when the lower total organic carbon levels are being fed in. Our work continues on increasing overall recovery, increasing the throughput and being able to feed ore with higher total organic carbon into the plant. And one of the initiatives that we're currently working through engineering work, and we've done a lot of test work on it already, is the impact of desliming of carbon from the ore that's currently being fed. So, we see that this will result in an overall enhanced to recovery. And essentially, it's removing the highest carbon portion of the ore and the remaining mass therefore, ends up with the improved overall recovery. Moving on to Greenstone on Page 9. Full-scale construction of Greenstone was announced in October of 2021, and two years later, the project remains on budget and on track for H1 of 2024 production. We are fortunate to have a very experienced and focused diligent team at the site. And this is a great photo showing the progress in the last two years. In the foreground is the ore storage dome. On the left-hand side is the primary and secondary crushing building feeding into the HPGR building that's near the center of the photograph. Behind the HPGR is the truck shop and warehouse building. And on the right-hand side is the mill building process plant building with the thickener in the foreground of the building and the leach tanks to one side. In between the thickener and the ore storage dome is the on-site power plant. The project had one LTI in the quarter and has had over 5 million hours worked so far. Move on to Page 10. Progress at the site as of September 30. The overall project is 93% complete with construction at 92% complete. Procurement is 90% complete, and then mechanical piping and electrical, those are the big focus. The big focus at site, as we reduce the personnel on site in the fourth quarter. This is how - the construction team will start to ramp down as our ops team has been building up, and we're in towards pre-commissioning and commissioning. The capital spend is 89% complete. On Page 11. Process plant is 91% complete. Both ball mills are mechanically complete, conveyors installed belt installation underway crusher, reclaim and HPGR substantially complete and the hydro testing and leach tanks has been underway. Our pre-commissioning activities are underway in several areas. Our process - the power plant is already complete and has been through commissioning. It's fully operational. The pipeline is commissioned and operational, and we've been switching over to powering portions of the plant during Q3. Full transition happens in Q4. The tailings facility is 94% complete. The South portion is complete to the final elevation, 340 elevation and buttress work continues. It will be - it is on schedule for completion and ready for use in Q4. There's a list of additional infrastructure over to the right, and I'm not going to read that through. Suffice to say that the key areas that remain are the tailings storage facility and the process plant. We've already done the realignment of the Highway 11. That was opened for traffic in '20 in August of this year and we've relocated the Ministry of Transportation Petroleum. So going to Page 12, looking at key milestones. As noted, the highways open, Process plant is 90% complete, and we've moved into pre-commissioning. So, our operational readiness and commissioning teams are in place and very active on site. In Q4, the big focus is the mechanical piping and electrical installation. And then, we move into wet commissioning on the process plant. The TSF, as noted, will be ready for use and preproduction mining ramps up. We'll have 800,000 tonnes on the stockpile. Currently, it's over 400,000 tonnes on the stockpile. The mining fleet will be augmented in Q4 going with and - six additional trucks bringing our fleet to 14. And then, we'll continue adding trucks, to the point where we're at 22 trucks by Q3 of next year. So H1, 2024, we'll see hot commissioning first gold for mining at 145,000 tonnes a day and the buildup of the lower stockpile. Looking at our other expansion projects, Castle Mountain is in permitting. The application was submitted in March of 2022. In the meantime, we continue with our optimization work. We're doing additional met test work and we continue with front-end engineering. The Aurizona expansion will see concurrent mining of Piaba underground, along with Piaba open pit and other nearby open pits, such as Tatajuba and Genipapo. The engineering work continues on supporting infrastructure, for example, additional power that's required for vent fans and supporting the underground. And the underground portal development will happen in 2024, the ramp and drill stations and the ramp provides drill stations and we will be doing test mining and it provides the basis for future production. At Los Filos, the CIL plant would add life and improve overall recovery. We're looking for the conditions that are conducive to investing in the construction and the extension of the mine life. So in the quarter, we have met with communities. We started the dialogue and that needs to involve all parties. We'll need everyone to be involved so that we can - all stakeholders to be involved so that we can put Filos on the path towards being able to invest in the CIL, additional stripping and ultimately extending the life. With that, I'm going to hand it back to Greg.