Thanks, Pete. So as mentioned earlier, we had a very good first half of the year, and we are looking at pushing hard to deliver strong production in the second half. We've noted before that about 55% of production this year is in the second half of the year. have Mesquite. The Brownie pit provided a majority of new ore, about 90% of the ore going to the leach pad and re-leaching on portions of the pad also contributed significantly to the Q2 gold production. Mining costs at Mesquite benefited from a drop in diesel prices. And just, for example, the current price is about 30% lower than it was in Q2 last year. Process costs were reduced through a reduction of cyanide and lime usage. We don't see that staying the same in the second half because we plan on stacking more in the second half. So the overall cost will go up on cyanide mine. At Castle Mountain throughput has increased 40% since the start of the year in the crusher and the crusher run time is up by about 30%. We continue with modifications to the crusher setup and we're planning for those additional modifications to be implemented in Q3. At Los Filos, productivity improvements were seen in both open pit and underground. Open pit has about 15% higher productivity, along with loading improvements and an increase in effective operating hours. For underground is about 23% increase in the ore tonnes being mined. So although we -- but although we have more tonnes going to the leach pad, we did have some challenges on the leach pad that we've been addressing. These include some higher copper ore coming from the Guadalupe open pit. I do note that this is only a portion of the ore, and it represents about 12% of the tonnes being stacked for the remainder of the year. We also had issues with solution management related to some broken pipes in one area of the pad. Those have since been repaired and the pregnant solution in that area where the breakage occurred needs to be drained. That impacts about 8,000 ounces that is slow in coming out of the pad. It will come out. It's just going to be slower to get coming out than originally anticipated. And we also had one portion of the leach pad, which had to be turned again and leached again after a carbonate precipitation occurred, which was hindered recovery. That impacts about 4,000 ounces. Again, those ounces will come out in the second half of the year. At Aurizona, -- in addition to the current mining contractor, we also mobilized a second contractor with articulated dump trucks. They'll be in for most of the rest of 2023. They came in during the rainy season. The rainy season is over now. We're putting a big push on the mining and to establish a larger stockpile in advance of the next rainy season. At Fazenda, we're currently mining mostly from open pits while the underground also catches up on development, and we'll work on bringing additional stopes into production. Drilling continues on the reserve replacement program at Fazenda. It's been successful every year, and we continue doing that to get successful in replacing reserves every year. At RDM, we had good performance from the owner-operated fleet. That fleet is a combination of our own trucks plus 15, 60-ton rental trucks -- the increase in mining of higher grade ore has brought the production up significantly in the quarter. And the mill feed is -- I'll note that mill feed is also being augmented with low-grade stockpile if there is any availability in the mill. At Santa luz, the team continues to gradually bring recovery up, and the plant had an average overall recovery of 67% in the quarter. We are targeting 70% or better for the remainder of the year, and the team continues to work on process and throughput improvements. So moving on to Greenstone. I get the pleasure of being able to speak about a really good story on construction progress, and the team has done a great job. We put out the Greenstone update news release on Tuesday and provided a complete summary of the project status. Essentially, the project is on budget and on schedule for H1 2024 production. Moving on to the next page, looking at progress. Overall progress at Greenstone is 85% complete, which is comprised of construction at 83% complete, engineering is 100% complete and procurement 87% complete. Capital spend at June 30 is $937 million, which is 76% complete of the budget on a 100% basis. And we have approximately $170 million remaining as Equinox Gold's share to fund through to project completion. Facilities handed over to operations so far are the permanent effluent water treatment plant, truck shop, warehouse, sewage treatment plant, potable water treatment plant, the pit and plant site fuel stations, reagent storage building and site mix emulsion or explosive plan. The Ministry of Transport Petrol Yards been turned over to the ministry and the dismantling of the [ Oppatrol ] yard is now complete. Highway 11 realignment is also complete and has now been transferred to the ministry and was open to the public a few days ago. And the natural gas pipeline to site has been commissioned and is now operational. Plant site is 75% complete. The TSF is 80% complete. Operations are now at 240 employees. We'll get to around 360 employees by year-end. We look forward to hosting an analyst and investor visit in early September. And now moving on to our other expansion projects. At Castle Mountain, the -- we continue in permitting. We've responded to queries from BLM, and we anticipate permitting being complete in 2025. In the meantime, it continues with engineering work and with [indiscernible] to support the Phase II of Castle Mountain. At Aurizona, as Greg mentioned, we've been advancing the engineering studies, and these incorporate additional drilling and the recent work looked at the underground mining at a higher production rate given the large scale of the underground resource. And we see benefits in continuing to advance our studies on operating with both open pit and underground to concurrently fill the plant. So we are looking -- we are planning on developing an exploration decline in H1 2024, which would provide us an opportunity to develop down to one of the ore zones, mine in the ore zone and enable collection of geotechnical and hydrogeological information on ore and Wallrock. The plan is to have a fully dimensioned decline that would serve as a production access and would also enable a rapid start to underground production when we've completed our additional studies. And then at Filos, we continue to assess the opportunity to invest in CIL, but we do remain focused on having the right climate in Mexico and within the region before committing to the major investment. And while we also have competing opportunities for capital investment on other projects. So with that, I'm going to hand it back to Greg.