Thanks, Pete. So we're on Slide 8. For the operations, all of the mines are working on continuous improvement programs that are focused on productivity improvements, consumable usage reduction and also procurement savings. Specifically looking at Mesquite during Q1, the focus was on stripping and the Brownie and the Vista East pits, and that will provide us or for the remainder of 2023. Due to the emphasis on stripping and Q1, we did have a relatively low number of new ounces that went onto the pad during that period. And yet, ounces were as planned for the quarter in part due to contributions that we got from re-leaching and side slope leaching of the pad in previously leached areas. We are continuing our expiration and permitting efforts looking for mine life extensions at Mesquite. At Castle Mountain, we were placing both run of mine and crushed and conglomerated or on the heat bleach pads. We had an increase in the overall tenant being placed over the prior quarter and we continue working on increasing the overall crusher throughput with the intent to put all of it through the crusher conglomeration system. We are advancing our permitting and met test work in support of Phase 2, and I'll mention some more of that later on. At Los Filos, we're currently mining in the Los Filos and the Guadalupe open pits as well as the Los Filos underground mine. We've had improved productivity with more tons being placed in the quarter and with higher grades coming from both open pits and underground mines. However, recovery was impacted for some of the ore coming from Guadalupe open pit. Some of the ore has a high copper grade, specifically copper oxides, and they are cyanide consumers, and they delay our overall gold recovery. So, we've now been separating that ore. We're using a higher cyanide dosage and we anticipate an extended leach cycle for the recovery of the gold from that or so. That's going to mean that the ounces from that ore will be dragged out over subsequent quarters. Also of note, we did suspend the Bermejal underground during the quarter and that was due to the prolonged development period and investment period and the lower productivity that we were getting out of the mine. We will develop the revised mine plan to be able to match the timing for restart so that that higher grade ore will be fed into the CIL plant. Turning to Slide 9. At Arizona, we had good mine production as we moved through the peak of the rainy season. Our contractor brought in additional trucks during the quarter. We also mobilized the second contractor so that we can catch up on the material movement as the rainy season begins to abate. The process plant maintained a higher throughput than planned, and we produce slightly higher than plan for the quarter overall. At Fazenda, the mine performed well with open pit mining, contributing higher grades and more tons than planned, which helped to offset lower production from the underground mine while we catch up on development headings and bring on additional scopes in the underground. Both through put and plant recoveries at Fazenda were above plan and the mine was ahead overall announces being produced, and I note our expiration work at Fazenda continues to provide good resource and reserve replacement as per each year we focus on doing that to extend the life of Fazenda, and expiration has also been following up on the Greenstone belt between Fazenda and Santa Luz. At RDM, we restarted the process plant in January 19 after a permitting delay, and we're doing owner mining with our own equipment, supplemented with a rental equipment fleet, and mining is ahead of prior quarters for both the ore waste movement. We're processing this combination of in situ ore plus supplemented by low grade dump material. Recoveries are almost 90%, which is a couple percent above plan, and the mine intends to catch up on full year production as projected for the year. The final TSF raise is in progress. In our current TSF, we're optimizing the volume that we have available by cyclone in the tailings, and we've entered into the permitting process for a filtered tailing storage facility at RDM. Moving on to Santa Luz, we had lower recoveries in January, but over 65% was being achieved in February and March as we kept the war blend steady and modifications were being completed on the detox system, which is critical to maintaining recoveries at Santa Luz. Recoveries are now over 68% in April, and we continued to work on process plant improvements for, with a plan for recoveries to be over 70% for the second half of the year. I do note the resin leach plant is achieving higher recoveries overall than what would've been possible with carbon leach processing. Moving on to Slide 10 and onto the development side, Greenstone, this will be one of the largest gold mines in Canada with $5.5 million ounces of reserves. Annual production for the first five years will be 400,000 ounces a year, 14-year life and first production coming in the first half of 2024. I just want to take a moment to acknowledge the focus on safety at all of our mines, but especially as a construction project at Greenstone. They've passed 3 million hours just after the quarter end with no lost time injuries so good that they keep the focus on safety. Moving on to Slide 11 and looking at the construction information. The project is on budget and on track. Overall, the project is 73% complete at the end of Q1. You can see the various other items for a construction procurement, concrete, structural steel. Capital spend is 65% complete and we have around 260 million remaining as our share of the spend on the project. Project progress is really good during the winter months as Greg stole some of my thunder and talked about how well things have been going. All of the buildings were enclosed and being heated by the end of the quarter. Ball mill installation -- excuse me, ball mill installation has commenced as per the schedule and as you can see in the photos, a lot of the buildings now provide us the ability to move inside. We have major installations underway, mechanical, electrical, piping being a focus. All major equipment is on site with the exception of the HPGR, which is on route to the site at the moment. And on the operations side, we started mining in Q3 last year with four trucks and one shovel. We moved to 24x7 operations in Q4, and by the end of Q1, we'd moved 6 million tons of material. We now have seven trucks on site and two shovels. And I note that we will be doing an analyst visit in September this year. So moving on to our other expansion projects. They include Castle Mountain Phase 2. We'll see an increase to over 45,000 tons a day going on to the leach pads and production of around 218,000 ounces a year for a 14 year life. As Greg noted, we submitted our permit application in March of 2022. We've had our notices of completeness from the permitting agencies, and we'll continue to work through the process and should see environmental assessment work happening during 2023. For Piaba underground at the Aurizona mine, we're working on the feasibility study that involves mining from both the underground at the same time as the open pits. The feasibility study should be wrapped up -- will be wrapped up by mid-year. We have permits for three portal locations. We will upon completion of the feasibility study, look at timing for an expiration ramp that would give us underground drill stations and the ability to mine on the ore and will be looking to assess geotechnical and hydrogeological parameters, and also it will ultimately serve as a production decline. At Fazenda, as noted, we are looking at construction of the CIO plant. We'll be making a decision on the construction once we're through the higher CapEx period for Greenstone, and we're also looking for doing work on our operational efficiencies and having continued stability with the local communities. With that, I'll hand it back to Greg.