Richard Thomas
Analyst · Canaccord Genuity
Thank you, Oliver. I'd like to start with Segovia, where the processing plant expansion remains on track to increase capacity from 2,000 tonnes a day to 3,000 tonnes per day. Installation of a second ball mill will be completed in May with the commissioning expected in June this year. The new ball mill will increase the throughput capacity and hence, gold production. Following a ramp-up period, we are targeting a production rate of 3,000 tonnes per day. Once we are able to fill the mill at 3,000 tonnes per day, we are expecting an annual gold production in the range of 300,000 ounces per year. As 2025 is a transition year, our gold production guidance to produce between 210,000 and 250,000 ounces and quarter 1 production of 47,549 ounces is a strong start and in line with our internal plans. Going across to Marmato, the construction of the Lower Mine is gaining momentum. In March, we announced a design change, which will increase the processing capacity to 5,000 tonnes per day. During the quarter and in April, the decline development progressed steadily with 323 meters completed of the full 1,700. Earthworks for the main substation platform is complete and the earthworks for the process plant platform continues in progress. In parallel, the site has seen an ongoing delivery and staging of key equipment and materials, including filters, cyclones, some pumps, some mining equipment, supporting the ramp-up construction momentum across several of the project areas. Once completed, Upper and Lower Mine Marmato combined will have the potential to produce over 200,000 ounces of gold per year. As of March 2025, we updated the estimated cost to complete the construction of the Lower Marmato Mine to $290 million, considering the 25% expansion to 5,000 tonnes per day of throughput capacity. And we have a further $82 million in remaining funding to be received from the Wheaton Precious Metals under the precious metal streaming agreement. The net construction capital balance of $208 million is thus fully funded as outlined by Neil and Oliver by way of cash on hand and ongoing cash flow generation from Segovia. I'd like to take this opportunity to encourage you to visit our website to view the latest developments in the Lower Mine construction. A link to the most recent video is available at the bottom of the slide or you can visit us directly at aris-mining.com. Let's move across to Slide 7, and we are pleased to highlight progress on our 2 major technical studies currently underway at Soto Norte and Toroparu in Guyana, starting with Soto Norte project located in the Santander Department of Colombia, where Aris holds a 51% joint venture interest and serves as the project operator. We continue to advance environmental and technical studies and expect to complete a new pre-feasibility study in the third quarter of this year. This is a revised smaller scale underground development plan incorporates several optimizations, including improvements to the processing design, tailings storage, mining methods, ore transport, water usage, all of which contributes to reducing the project's environmental impact. We look forward to providing a comprehensive update once the PFS is complete. If we go over to Toroparu, 100% owned open pit gold copper project located in Guyana, we've commissioned a new preliminary economic assessment to assess updated development options. Completion of the study is also expected in the third quarter of this year. Since updating the mineral resource estimate for Toroparu in March 2023, Aris Mining has also completed important infrastructure optimization studies. With that, I'd like to pass this back to Neil.