Thank you, Richard. Now moving on to Slide 8. Segovia process plant expansion has progressed as scheduled. And as previously disclosed, Phase 1 of the Segovia expansion is complete, the new extended receiving area for our CMP is fully commissioned and handed over to operations and working well. The new facility began processing materials in October 2024. Phase 2, which involves installation of ball mill in the formal contractor receiving area is underway with commissioning expected in quarter 2 this year as scheduled. Following the ramp-up period, we expect to reach production rate of about 300 tonnes per day by the end of '25, enabling Segovia to produce 210,000 and 250,000 ounces of gold in 2025 and in the range of 300,000 ounces of gold from 2026 onwards as per our guidance released earlier in January. The total cost of Segova's processing plant expansion project is still installation at $15 million. And at the end of the year last year, we had spent $8.5 million. If we could move on to Slide 9, please. I'd like to provide an update on the construction progress at the Marmato Lower Mine. As you can see from the photographs on this slide, the construction of Lower Mine continues to advance with, firstly, the access roads to the Lower Marmato process facility and the accommodation camp now 100% completed. Secondly, the decline development underway with 200 meters completed by the end of February 2025 and the processing plant foundation earthwork 12% ahead of schedule as of the end of February 2025. At the beginning of this year, we initiated an engineering assessments to evaluate whether we could expand the plant - the current CIP plant currently under construction. As a result of the studies, we have decided to expand the CIP processing facilities at the Lower Mine from 4,000 tonnes per day to an expanded 5,000 tonnes per day, whilst also expanding our CMP business model, increasing the feed and average grade of the existing Upper Mine flotation plant, thereby further increasing the gold production. With the completion of these expansions, we expect Marmato to be able to produce in the range of 200,000 ounces of gold per year, which compares to the previous life of mine average of only 162,000 ounces per year. If you could move to Slide 10, please. As you can see from the drawing on this slide, the key enhancements required to take the throughput from 4,000 tonnes per day to 5,000 tonnes per day are straightforward as the upgraded 5,000 tonnes per day design will use major components from the current 4,000 tonnes per day design, while also integrating some high-capacity components, installing the secondary crushing unit, adding an extra leach tank to support the increased throughput and accelerating certain project components into the initial capital phase. We expect this ramp-up to begin at H2 2026. Moving on to Slide 11. As of February 2025, we have spent $75 million on construction. The estimated cost to complete the revised construction, taking the throughput from 4,000 to 5,000 tonnes per day is $290 million, bringing the total upfront cost to $365 million, $85 million over the previous construction plan. The 25% bigger plant requires bringing forward the tailings facility construction and the backfill plant into the upfront capital, and this is estimated at $50 million. We have also opted to build a $20 million power - grid power line instead of relying on a third-party power purchase agreement. The process plant enhancement that I mentioned earlier, namely integrating some high-capacity components, a secondary crushing circuit and adding an extra leach tank to support the increased throughput are expected to cost around about $10 million. Importantly, the net construction cost to Aris is $208 million, considering the remaining stream funding of $82 million. In our view, this is a very attractive investment proposition, being able to meaningfully increase production of a long-life asset with minimal, limited incremental capital, against the backdrop of record high gold prices. Looking ahead with the new Marmato and the expansion of Segovia, Aris is targeting an annual production rate of more than 500,000 ounces of gold. With that, I'd like to hand over the call to Oliver.