Stuart McDonald
Analyst · TD Cowen. Your question please
Great. Thank you, Brian, and welcome everyone to our first quarter conference call. As usual, I'll start with a business overview of our key activities and operational results in the quarter and then turn the call over to Bryce for a more detailed review of the financial performance. So, starting with Florence, our Florence Copper project, we just issued a project update last week confirming everything is moving forward on time and on budget. Good progress continues to be made with construction activity at the site, and we remain on schedule to produce first copper before the end of this year. In the well field, as of this week, we only have two wells left to drill. So, we have 88 out of 90 production wells completed, and all 18 of the point of compliance wells are also done. We've ramped down to just one drill remaining on-site, and that one will be finishing up in the next few weeks. This is a great accomplishment, as obviously, the well field is a critical aspect of the overall project. In the SX/EW plant area, we also have a lot of activity and progress, and all critical path items are moving forward on schedule. The installation of the electrowinning crane was completed in Q1, which allowed for the final wall and roof panels to be installed, completing the building structure. Current areas of focus include installation of electrical and piping equipment, completing, completion of the substation facility, and ongoing work on the pipe corridor to connect the plant to the well field. In the coming months, as key systems are completed, progressive commissioning and testing will occur at the same time, as the final construction activities. And in the fall, we expect to commence well field operations at initial injection, which sets us up for first copper cathode production before the end of the year. We continue to advance initiatives for operational readiness. Our recruiting is going well. By next week, we'll have over 100 employees on-site. We're also close to finalizing our first asset supply contract for the initial ejection and pre-leaching period later this year. It's been 10 years, since we acquired the Florence project, and we're now less than 9 months from producing first cathodes. It's been a long process to get where we are today, but I think the outcome is going to be well worth the wait for all our shareholders and other stakeholders. Florence is one of the few copper projects in the world currently under construction, and it will be a major new supplier of refined copper capital for the U.S. market. The potential for U.S. import tariffs on copper is further evidence of the unique value that we have in this asset. The COMEX copper price yesterday was about 14% higher than the LME price, and the project has the potential to benefit from this premium in the future. Now, onto Gibraltar, where we produced 20,000,000 pounds of copper in the first quarter with a C1 cost of $2.26 per pound. Copper sales of CAD22 million at a realized price of $4.24 per pound generated adjusted EBITDA of CAD34 million and cash flows from operations of CAD56 million. Mill throughput ran above design capacity at an average rate just under 88,000 tons per day. Head grade of 0.19% was in line with our expectations as a significant portion of the mill feed was from lower grade stockpiles as planned. However, copper recoveries dropped to 68%, as the impact of oxidized ore was more significant than anticipated. So, our overall production in the quarter was about 10% lower than we expected. Our original plan had higher grade ore coming from the deeper benches of the connector pit beginning in the second quarter, after the initial waste stripping was completed. Unfortunately, challenging mining conditions at the top of the current connector pit pushback has impacted truck and shovel productivities, so we will not get to the higher grades now until the third quarter. Second quarter production is expected to be similar to the first quarter, and then we will see a step change of production in the second half with average grades above Gibraltar's reserve average, and these good grades should continue, into 2026. As a result of all this, we expect 2025 production to be approximately CAD10 million lower than our previous guidance of CAD120 million to CAD130 million. The refurbishment of Gibraltar's SX/EW plant and restart plants have made good progress, and we expect first cathode production later in the second quarter. The plan is to produce about 3,000,000 or 4,000,000 pounds of cathode this year. It will be a seasonal operation, but a lot of copper oxide ore has been stacked, and we expect the leach pads to run for many years into the future. Last but not least, a brief update on our Yellowhead copper project, which we believe represents an important long-term growth option for the company, continuing to work closely with BC government and the Simp First Nation on project permitting initiatives. The Yellowhead mine would be a major producer with 180,000,000 pounds of copper production annually over a 25-year mine life. I would make it the second largest copper mine in Canada. We're planning to publish a new technical report this summer, which will incorporate updated metal pricing, costing, and then also the new Canadian tax credits are available for copper mine development and have the potential to positively impact the economics as well. So, with that, I'll pass the call over to Bryce.