Tom Fanning
Analyst · Credit Suisse. Please proceed
Good afternoon and thank you all for joining us. As you can see from the materials that we released this morning, we reported strong adjusted results for the full year that exceeded our original guidance expectations and we are in line with the updated year end estimate we disclosed on the third quarter call. By all accounts, 2019 was an outstanding year for our company. We performed well across a broad range of metrics. We reached all 2019 major milestones at Vogtle Units 3 and 4. Operational performance at our state-regulated utilities was superb with record generation and transmission performance. We concluded several key regulatory proceedings, including constructive base rate cases for Nicor Gas, Georgia Power, and Atlanta Gas Light. We took steps to further strengthen our balance sheet. We continued to economically de-carbonize our generating fleet, decreasing our coal generating capacity by 2,000 megawatts and we expanded our portfolio of renewable energy sources, which is now over 12% of our generation mix. Our company is ranked in the top quartile nationally for customer satisfaction and we were named Best Company to Work For in our industry and 14th overall in the United States. So, overall, terrific performance. Let’s turn now to an update on Plant Vogtle Units 3 and 4. In April of 2019, we laid out an aggressive site work plan as a tool to achieve margin to meet the November 2021 and 2022 regulatory approved in-service dates. Executing this strategy resulted in substantial progress at the site and we reached all major milestones in 2019. The aggressive site work plan established last April set a goal of approaching 90% completion of Unit 3 direct construction by year end. Today, Unit 3 direct construction is 85% complete. As we have discussed in the past, Southern Nuclear evaluates projected cost and schedule forecasts on a regular basis. As part of this process, we completed a scheduled refinement for Units 3 and 4 earlier this month, which in summary produced three major conclusions. First, we confirmed our ability to our expected ability to achieve the November ‘21 and November 2022 in-service dates. Second, we supported the site’s strategy to continue to utilize an aggressive site work plan with no change to the May 2021 target in-service date for Unit 3 and a 2-month advancement of the target in-service date for Unit 4 to March 2022. And third, we confirmed no change in the projected overall capital cost forecast. Now, I will walk you through the details. Let’s begin with some additional background on the schedule refinement. Over the past year, we continued to gain a greater understanding of the site capabilities for construction and testing, specifically for construction. In 2019, the site achieved sustained periods of 140,000 to 145,000 earned hours per week, but built a backlog to the April 2019 aggressive site work plan. The schedule refinement process took into account our 2019 performance and also our progress on work packages, testing and turnover. The resulting refined aggressive site work plan for 2020 relies on sustaining our current construction production levels and requires a reasonable increase in electrical commodity installation. On the refined aggressive site work plan, we have extended by about 6 weeks, 2 of our near-term milestones for Unit 3, starting cold hydro testing and hot functional testing. By extending these milestones, refining testing sequences between hot functional testing and fuel load and planning to complete non-critical electrical work later in the schedule, we now have more time to complete construction and work down the current backlog of construction hours. With these changes, the aggressive site work plan continues to target a Unit 3 fuel load by the end of this year supporting a May 2021 in-service date. The aggressive site work plan reflects a continuation of our strategy to drive construction productivity, complete testing activities and ultimately meet the regulatory approved in-service dates. Next, to complement the aggressive site work plan for Unit 3, we have established a November benchmark that forecasts construction production levels and future milestone dates necessary to support the regulatory approved in-service date of November 2021. This benchmark provides a clear comparison to the refined aggressive site work plan. On the November benchmark, fuel load could occur as late as the summer of 2021 in support of a November 2021 in-service date. The November benchmark also support our expectation that the aggressive site work plan is an appropriate strategy and provides sufficient flexibility to achieve the November 2021 regulatory approved in-service date. The result of the schedule refinement in the November benchmark is illustrated on the key milestones chart for Unit 3. The blue line represents the aggressive site work plan and the orange represents the November benchmark with the milestone start date shown in the circles and the direct construction percent complete detailed on the lines near the top. As you can see on the green bars, recently, we have been averaging about 2% completion per month for direct construction for Unit 3. If we maintain construction completion of approximately 2% of direct construction from each month from now until hot functional testing, we would expect to be close to the blue line or the aggressive site work plan. To achieve the November benchmark, we estimate this metric would need to be approximately 1.3% each month. Now, let’s focus on estimated costs. In conjunction with the refined schedule in the fourth quarter, Georgia Power allocated an additional $110 million of its project contingency. Primary drivers for this allocation include a continuation of current cost and schedule productivity trends, which have been lower than planned. Through the fourth quarter of 2019, Georgia Power has allocated a total of $140 million. So, approximately 60% of our initial total cost contingency remains. Looking at it another way, the scheduled cost margin and the remaining cost contingency combined represent approximately 20% of the remaining estimated cost to complete. Recall the estimated cost of the time between the aggressive site work plan and the regulatory approved November in-service dates or there our scheduled margin is embedded in Georgia Power’s base capital forecast. As we have said, we expect to utilize the entirety of these funds as we progress towards completion of the project. In summary, as I mentioned earlier, there is no change to the total estimated cost to complete the project. Finally, from a regulatory perspective, Georgia Power continues its Vogtle construction monitoring, or VCM, process with the Georgia Public Service Commission. VCM 2021, recall it, 12 months, was unanimously approved by the PSC on Tuesday. Georgia Power filed VCM ‘22 accounting for 6 months yesterday. In summary, we continue to expect that we will meet the November regulatory approved in-service dates and there is no change to our estimated cost to complete. It is important to recognize the substantial progress made on Vogtle Units 3 and 4 both in 2019. And really since the Southern Nuclear team assumed leadership at the site nearly 3 years ago, it is equally important to recognize that there is much work ahead, particularly in 2020. Our primary objective remains achievement of the regulatory approved November 2021 and 2022 in-service dates for Vogtle Units 3 and 4 and we look forward to communicating progress on our major milestones in the month ahead. Drew, I will turn it over to you now for an update on the financials and our outlook.