Tom Fanning
Analyst · Evercore ISI. Please go ahead
Good morning and thank you all for joining us. This morning, we reported strong earnings per share substantially above our estimate. Year-to-date earnings through September have also exceeded our expectations and the fourth quarter is off to a strong start for our electric utilities with unseasonably warm temperatures in early October. Drew will further discuss our earnings results and expectations in a few minutes. Before providing you with an update on our progress at the Vogtle site, I want to highlight our outstanding operational performance this quarter. We experienced record heat in the Southeast this summer, recording all-time September peak load days, four times during the month. Our electric system demonstrated resilience with record peak season generation in transmission performance, resulting in exceptional reliability for our customers. Importantly, even amid these conditions, a diverse field mix enabled Southern Company system to reduce our carbon emissions by approximately 35% compared to the strongest demand of 2007, our benchmark year for carbon emissions. Let's now turn to an update on Plant Vogtle Unit 3 and 4. The site continues to make progress as demonstrated by the achievement of several milestones during the quarter, including the start of integrated flushing activities. We remain focused on meeting the November 2021 and November 2022 regulatory approved in-service dates, and we continue to maintain an aggressive work plan on site as a tool to help position us to meet those dates. There is no change in our total estimated cost to complete the project. Last quarter, we discussed at length the contingency we established for the project in the second quarter of 2018. Recall the total amount we established is $800 million for the entire project of which Georgia Power’s share is $366 million. For the quarter, Georgia Power has allocated $30 million of its project contingency into the base project capital cost forecast. There are a host of factors both positive and negative that go into that analysis. But the biggest factor in allocating contingency was probably increased costs forecast related to craft attraction and retention. To give you context, contingency as a proportion of the estimate to complete is larger today than when it was established 15 months ago. We continue to believe that we have sufficient contingency to meet the budget associated with the November regulatory approved in-service dates. Overall, including engineering, procurement, and initial test plan activities, the entire project is approximately 81% complete with Unit 3 direct construction currently 77% complete. The project major milestones for 2019 have been achieved, or are expected to begin as planned later this year. We continue to successfully attract and retain craft labor. And currently, we believe, we have the resources necessary on site to support our aggressive work plan. Over the past several quarters, we have experienced periods of fluctuation and productivity around significant startup and construction activities. This variability has resulted in a sawtooth or S-curve shape in our performance charts, an effect we discussed on our last earnings call. In August, as we started our integrated flushing activities, we saw a similar effect on Unit 3’s productivity. Production levels have improved in recent weeks, and we are seeing the positive impact of a mature workforce with an increased ability to balance the needs of both construction and testing on site. The site has averaged nearly 150,000 earned hours over the past four weeks, with two recent weeks at about 160,000 hours, a record on the site. Cumulative CPI remains near last quarter’s levels, reflecting the construction and testing balance I just mentioned. On previous calls, we have focused on both Units 3 and 4 in the aggregate. At this point in the project, Unit 4 is progressing slightly ahead of its aggressive site plan. As you can see on Slide 7, Unit 3 construction is currently lagging its aggressive site plan. The primary driver is a backlog in the installation of electrical commodities and increased system turnover activity, trends we discussed last quarter. Southern Nuclear and Bechtel are implementing a productivity improvement plan to address the electrical backlog. Additionally, project leadership is utilizing specialized teams to focus on commodities installation and adds further enhanced night shift efficiency and has streamlined preparation for system turnovers. These initiatives have demonstrated initial success, as I have already noted, and further improvement is expected. With these actions, we believe there is sufficient flexibility and margin in future testing and startup activities to maintain Unit 3’s aggressive site plan milestone targets. To that end, we began the start of integrated flush activities for Unit 3 in August consistent with the aggressive site plan. Integrated flush is proceeding as we expected at over 60% complete and continues to support the start of open vessel testing later this year our next major milestone expected for 2019. Open vessel testing will continue through the first quarter of 2020 as we prepare for cold-hydro testing. Additionally, we expect to have the ability to test plant systems from the main control room before the end of the year. Each of these major milestones is important to the successful startup and operation of the plant and will lay the foundation for commercial operations. We continue to believe that working to an aggressive site plan is the right strategy in support of our primary goal of bringing Vogtle Unit 3 and 4 online by the regulatory approved November 2021 and 2022 in-service dates. This is a very exciting time for the Vogtle project. Within a year, we expect construction to be largely complete for Unit 3 and we expect to be preparing Unit 3 for fuel load. Consistent with past practice, we will continue to provide updates on our earnings calls and through the regulatory process as we move towards these major milestones. I will now turn the call over to Drew to cover our quarterly performance in greater detail.