Mark Isto
Analyst · Bank of America. Please go ahead
Yes, thanks, Bill. On Slide 5, I'd like to start with an update on the Khoemacau project in Botswana, currently under development by Cupric Canyon Capital. This is to decide in mid-October and met with the project team for a full review in advance of making our first funding contribution. I was impressed by the progress being made, the project organization and focus on safety. Construction is in full swing and at the end of September, a total of more than 800 people were working on site, Citizens of Botswana making up 95% of the construction workforce with 34% from the local region and 26% from the immediate area. The project is about one-third into the 30-month execution phase. At the end of September, engineering was approximately 85% complete, and overall construction progress was about 11%. Project remains on budget, and the first concentrate shipment is expected in mid-2021. We funded our first contribution to the project on Tuesday of $66 million and future funding will be made on a quarterly basis alongside contributions from other sources of capital. Slide 6 shows progress on the three boxcuts, which are the current construction priority and provide access to the Zone 5 orebody. Each excavation requires a removal of about a million cubic meters of material. As you can see in the photos, the excavations have progressed well through the soils, calcrete, and weathered rock and the finish walls look excellent. The Central boxcut is scheduled to be completed first and turned over to Barminco, the mining contractor which is targeted for the end of this calendar year. Turning to Slide 7, you can see a close-up of the geocell installation, an engineering solution to protect the slopes from erosion, the shot of the access corridor between Zone 5 and the Boseto Mill and a photo of the existing to Boseto Mill. Outside of the boxcuts, the three main project areas are the Zone 5 infrastructure, the access and infrastructure corridor between Zone 5 and the mill, and the Boseto Mill refurbishment. Most of the work currently underway is on the Zone 5 infrastructure to support Barminco consisting of accommodation, power, and water services. Development of the access corridor is progressing with the construction of light vehicle road first, followed by the ore whole road and the transmission line. One of the unique aspects of this project is the ownership of the existing Boseto Mill and work on refurbishing the plant is scheduled to start shortly upon award of domain structural, mechanical, and piping contract. Definition drilling to provide a basis for detailed stope design in the first three levels of the mines was completed in October, which will eliminate the need for this time consuming step associated with the early production stopes. As the project progresses, and prior funding and funding future contributions will be completed, further reviews on the site will be completed and updates will be provided on earnings calls. Turning to Slide 8, I'd like to discuss some recent developments at several of our key operating properties starting with Mount Milligan and Andacollo. Mount Milligan had a solid operating quarter with average mill throughput of 56,000 tons per day. Copper and gold reduction were also strong at 55,000 ounces and 21 million pounds respectively. And all-in cost at $557 per ounce remains in the bottom of the second quartile of the cost curve. Progress on sourcing water was positive, and the operation has about twice the amount of water stored now compared with this time last year. They've also had success with water exploration and expect to bring in water from additional groundwater sources in December subject to receipt of applicable permits. Centerra expects that they will be able to continue operations in the first calendar quarter without slowing production to conserve water, which is positive news. Centerra also announced last week that they will be publishing an updated 43 one-on-one technical reports in the coming months. Updating the technical report was prompted by their 2020 budgeting process when they identified that recent higher operating costs will remain steady over the medium-term, and long-term gold recoveries are expected to be lower than the original plan. This triggered a financial review of Centerra’s carrying value of Mount Milligan and caused them to highlight potential reduction in reserves and resources. The updated technical report will include the impact of costs and recoveries, as well as recent exploration results and other optimization work. It's worth keeping all of this in perspective. While increased costs and lower recoveries will likely impact the economics of lower grade material. Assuming a new mine plan focuses on higher grade ore, it may bring metal production forward, which may mitigate the NPV impact of losing metal from the latter years to mine life. At this point it is unclear what the impact may be at Royal Gold and we'll look forward to receiving the report when it becomes available. In the meantime, Centerra has reaffirmed their 2019 production and cost guidance for Mount Milligan. At Andacollo, operations were suspended on October 14 due to a strike by the Workers Union. It's an important asset for us and we currently receive 100% of the payable gold from Andacollo which contributed approximately 17% of our gross revenue in the quarter. We understand that negotiations are ongoing between Tech and the Union and we continue to monitor the situation. It's worth noting that the strike started before some of the recent widespread protests in Chile. And that strike is unrelated to these events that are occurring. We expect the impact of production suspension to be in the June quarter, as we typically receive deliveries within 12-months of concentrate shipment. Moving on to Slide 9, I'll provide some comments on Rainy River and Peñasquito. At Rainy River, New Gold turned in another quarter of solid operating results, mill throughput for the quarter averaged 24,500 tons a day, which is the first full quarter the mill has achieved the target 24,000 tons per day rate. Gold recovery of 91% was in line with the mine plan and efforts continue to further improve recoveries through additional circuit optimizations, as well as the commissioning of the gravity circuit. Mining operations continued to transition from Phase 1 to Phase 2 of the pit and production included planned lower grade ore from Phase 2 as well as the remaining higher grade ore from Phase 1. New Gold expects grades in the December quarter to decline an average between 0.8 and one gram per ton as ore from Phase 1 is now mined out. We continue to advance a comprehensive mine optimization study that includes a review of alternative open pit and underground mining scenarios. The New Gold and New Gold expects to release this study in mid-February 2020. At Peñasquito, we were pleased to see the removal of the blockade that caused operations to be suspended on September 14. The dispute leading to this suspension was the same as the one that caused operations to be suspended from April 29 through June 17, which was an illegal blockade of the mine by a trucking contractor and some members of the Cedros community. The last blockade was lifted on October 8, concentrated shipments started immediately, and a 10-day ramp-up commenced on October 22. And the site is now back in full operation. The impact of Peñasquito during the quarter was lower production of approximately 51,000 gold equivalent ounces. Newmont Goldcorp is seeking a sustainable long-term solution to the dispute and has been working with state and federal governments to ensure rule of law is upheld and government sponsored negotiations with the Cedros community started earlier this week. Newmont Goldcorp also reported the stripping of the Main Piniasco pit is near completion, and higher grade ores are expected during the December quarter and into 2020. I'll now turn the call over to Bill to discuss our financial results.