Steven L. Busby
Analyst · UBS
Thank you, Geoff, and good morning. The third quarter of 2011 brought us a wealth of challenges that we are successfully confronting with our projects advancing very well and our operating teams adapting our business to the ever-changing political environments where we operate. As Geoff mentioned, our consolidated third quarter silver production, the 5.6 million ounces at a cash cost of $9.58 per ounce, was about 8% below our production expectation and 13% above our cash cost target. The largest contributor to our production shortfall and cost overrun came from a decision we made at our Morococha and Huaron mines in Peru to immediately demobilize roughly 25%, or 500, of our inefficient and ineffective contract miners in favor of enhancing our own employment with well-trained, safe and productive miners, whom we will develop ourselves using first-class miner training facilities that we have established at both of these sites. We had found that the quality and efficiency of the contract miners had severely degraded in the highly competitive environment that exists in Peru right now, and we were not accomplishing the production and advances needed to sustain our operations productively. Our idea is to focus quality contractors on major long-term development headings while developing trained and productive employees for stope mining that we will systematically convert as much as possible to more productive mechanized methods over the next few years. We will use our training facilities not only to recruit and develop new miners from the surrounding communities, but also to enhance the capabilities of our existing workforce. Despite suffering some production setbacks following this decision, we are extremely confident it is the right decision to maximize the long-term profitability of the Huaron and Morococha mines. These mines have both been in operation for nearly 100 years, and we see absolutely no reason they will not continue for at least 25 years or more. During Q3, we produced 383,000 ounces of silver at Morococha and 667,000 ounces at Huaron at a cash cost per ounce of $18.78 and $15.07 for Morococha and Huaron, respectively; collectively, falling about 0.5 million ounces short of our forecasted production in Q3 for these 2 mines. This is a significant and vitally important production enhancement initiative to adapt to the changing environment, and we expect it will take 6 to 12 months to mobilize new equipment and get our new workforce fully trained to maximize the profitability available at both of these long-life mines that hold significant reserves and resources. Our Manantial Espejo mine in Argentina produced 1.1 million ounces of silver at a cash cost of $6.56 per ounce during Q3 compared to 1 million ounces at a cost of $3.65 in Q3 of 2010. We were able to increase our production, even though facing delays in getting our accelerated open pit mine plan into place as we adapted the operation to the heightened importation restrictions put into place by the Argentine government. These heightened restrictions have caused considerable delays in the delivery of our important spare parts and material supplies, resulting in a decrease in our equipment availabilities and an increase in costs as we find alternatives, which in several cases included temporary mobilization of contract or rental equipment to overcome some of our critical equipment shortfalls. We are in the process of increasing our on-site warehouse stock of spares and materials to adapt our business to the added delays caused by the sudden heightening of the importation restrictions and expect our cost will eventually return to levels that we had been experiencing in the first half 2011. Moving on to Bolivia. Our San Vicente mine produced 751,000 ounces of silver at a cash cost of $14.39 per ounce during Q3 compared to 712,000 at a cost of $8.54 the year before. San Vicente has proven to be a productively stable operating mine for us, although our costs have been creeping upwards, largely fueled by external costs associated with offshore smelting and refining of our copper concentrates, as well as the high metal price effects on our government royalty payments. Our Mexican mines continue to deliver exceptional results, with Alamo Dorado producing nearly 1.4 million ounces of silver at a cost of $4.73 per ounce and La Colorada produced 1.1 million ounces at $7.84 per ounce during the third quarter, both ahead of our expectations. Last year in Q3, Alamo Dorado produced 1.8 million ounces at a cost of $2.98, and La Colorada produced 870,000 ounces at a cost of $8.67. Our Alamo Dorado leach tank expansion project is on track for a Q1 2012 completion, after which we expect silver recoveries to improve by about 2%. Our Phase 3 drilling is progressing well at Alamo Dorado, and we will be looking to secure additional open-pit mine equipment to allow us to begin pre-stripping Phase 3 during 2012. Although our analysis is not yet complete, we are confident the Phase 3 pit is economic at today's prices, and we will add at least one year of life to our mine plan. I would also like to comment that our exploration on deepening the main mineralized Candelaria structure at La Colorada continues to excite us, and we have developed an astonishingly productive and highly profitable systematic mine advanced scheme that is expected to provide us continued solid operating performance for the next 7 years and beyond. On the project front, the company released a positive Preliminary Economic Assessment for the La Preciosa joint venture project. On 100% basis, the PEA estimates an average annual production rate of 6.8 million ounces of silver and 11,800 ounces of gold at a cash cost of $11.84 per ounce, net of by-product credits, for 12 years with remaining exploration potential that could extend the mine life. The 100% basis after tax net present value at a 5% discount rate is expected to be $315 million, with a project internal rate of return of 24.3%, using prices of $25 silver and $1,250 gold. The project exists in our backyard, and it is a style of development our team in Mexico knows well how to build and how to maximize profitability. We feel that given our attraction to this style of project, along with the results of the PEA, it is justified to complete a feasibility study, and that is what we have undertaken to complete during 2012. Down in Argentina, our Navidad project continue to make good progress on the development of the feasibility study, which is expected to be completed before year end. The mine and concentrate production schedules for the feasibility study were completed, and work continues on finalizing the project capital and operating cost estimates. The 15,000 ton per day ore production plan will produce an average of nearly 19 million ounces of silver and 32,600 tons of lead per year for a 16-year life with ample opportunity to expand resources both near the existing 8 deposits as well as the potential for finding additional deposits on the site. A draft of the tailing stand design and cost estimate was received during the quarter, and the 2011 infill drilling campaign was completed just in the previous month. Work continues on the refinement of the project's environmental impact statement, which will be immediately available for submittal once the law which bans open-pit mining is reformed. We are pleased with the results of the federal and provincial elections, which solidly puts President Cristina Kirchner in power for another term both nationally and, for the first time, provincially in Chubut, along with the new governor of Chubut, Martin Buzzi, who has indicated he will align with the President's policies and objectives. The new provincial governor and legislatures take control in mid-December, and we feel confident the mining law reform debate is a high priority on their agenda as they look to bring productive industry to a very needy area of the province. Elsewhere, I'm pleased to -- with the progress we have achieved on constructing our new shops, offices and camps at Morococha to allow for the relocation of these facilities during 2012 and make room for Chinalco's Toromocho mine development. These are first-class, state-of-the-art facilities and will no doubt play a significant role in our productive mine transition initiative. So to finalize, I'd like to mention that, given our decisions to launch contractor demobilization initiative that we're on in Morococha as well as adapting our Manantial Espejo mine to the heightened importation restrictions in Argentina, we are reducing our full year consolidated silver production guidance to 22.5 million ounces from our previous estimate of 23 million to 24 million ounces, and are also reducing our consolidated base metal production guidance for zinc, lead and copper to 35,000, 12,000 and 4,500 tons, respectively. We are maintaining our previous increase in full year consolidated gold production guidance at between 80,000 and 85,000 ounces, and we now expect to come in at the higher end of our previously released cash cost guidance of between $8.25 to $8.75 per ounce. With that, I'll now turn the call over to Michael Steinmann for the exploration update.