Thank you, Jason. Musselwhite mine, 326,000 tonnes of ore and milled 329,000 tonnes at a mill head grade of 5.87 gram per tonne gold. Gold recovery rates of 95.3% resulted in production of nearly 58,000 ounces of gold. Our investment in new underground mobile equipment and preventative maintenance program on the existing equipment are contributing positively to the working conditions and productivity. Ventilation upgrades and underground infrastructure projects remain on track for completion in early 2026. The company continues to expect steady production and cost performance from the fourth quarter. At our Camino Rojo oxide mine, mining operations were temporarily suspended in late July following an uncontrolled movement material along the north wall of the open pit. Once again, I'm pleased to highlight 0 injuries, 0 equipment damage, 0 environmental impact as a result of the pit wall event. Our pit wall moderning systems worked well, detecting the movement early and allowing us to pause mining and respond in a controlled manner. This incident validated our commitment to monitoring and safety protocols. We maintain production continuity by crushing and stacking existing stockpiles. I would like to thank our team who successfully mitigated the short-term impact, ensuring consistent processing. The current plan includes mining from surface downwards to pushback and stabilize the entire north wall and reestablish safe working conditions along the north side of the pit. The north wall will be reestablished at a lower overall stope angle at single 10-meter benches based on a design that reduces the risk. During the quarter, Camino Rojo mined nearly 0.7 million tonnes of ore and 2.4 million tonnes of waste for an implied strip ratio of 3.34. A total of 1.7 million tonnes of ore was stacked at an average grade of 0.44 grams per tonne of gold, equating to an average stacking rate of approximately 18,900 tonnes per day. In addition, 1.1 million tonnes of low-grade ore were rehandled and placed on the leach pad at an average grade of 0.32 grams per tonne gold. In total, 2.8 million tonnes of ore at an average grade of 0.4 gram per tonne gold were placed on the heap leach pad during the quarter. Total quarterly production for Camino Rojo was 22,059 ounces of gold. South Railroad hit an important milestone this quarter with the Bureau of Land Management publishing the notice of intent in the Federal Register on August 13, which initiates the formal environmental impact statement process under NEPA. More recently, in November, South Railroad transitioned from participation under the FAS-41 transparency process to a FAST-41 coverage project. The importance of this shift is that FAS-41 coverage provides tools to support efficient review, reduce uncertainty and help ensure the project meets the highest standards of environmental stewardship and regulatory compliance. In parallel, the U.S. Army Corps of Engineers Section 404 permit application, addressing wet land and surface-disturbance impacts was submitted in August 2025 and deemed administratively complete. The BLM NEPA public-comment period closed on September 18, with the largest category of submissions being letters of support, reflecting strong community and stakeholder backing for the project and the U.S. Army Corp Engineering Section 404 public-comment period ended on September 15 with no significant comments received. At the state level, the company has secured a Class I and II Air Operating Permits while water-related applications continue to progress with the Nevada Division of Water Resources. The Water Pollution Control Permit and the National Pollutant Discharge Elimination system, discharge permit applications have been submitted for review in the third quarter 2025. The BLM's Record of Decision, the final permitting decision is targeted for the second quarter of 2026. Following this approval, on-site construction on the South Railroad project would commence and its first gold targeted for early 2028. We continue to engage with local, state, federal stakeholders to sustain momentum in the permitting process in the United States. Our project team continues to work with M3, our EPCM on the engineering for the projects to be prepared for on-site construction starting next year. We are planning on providing a project update in the weeks ahead, which will include a feasibility study update on the South Railroad project. The feasibility study we will release and construct honors the plan of operations submitted initially in 2020, but is significantly more advanced to a construction-ready project supported by detailed engineering, vendor pricing and refined execution planning to enhance the overall confidence in the project. Our team is gearing up for the successful development of the South Railroad project. Etienne Morin, our Chief Financial Officer, will now discuss the financial results for the quarter.