Renaud Adams
Analyst · Bank of America. Please go ahead
Thank you, Martin. We will start with Cote, which you can see here on the left image on the slide, with a view of active mining activity early in the summer. Last month, we announced the Cote's preliminary Q3 operating results ahead of what was a well-attended mine tour by analysts and institutions. I want to take this moment to once again thank all the attendees for the great turnout and thank our Cote team for hosting what was a very engaging tour. Looking at the quarter, a highlight for Cote was the first quarter of positive free cash flow, as Marten just highlighted, from productions of 68,000 ounces on a 100% basis. However, I believe the real advancements were on the progress of the ramp-up and improved understanding of the operation. I am very proud about the progress we achieved in the third quarter. As we saw a definitive sign that the improvements that were deployed throughout the quarter and during the shutdown in September are having a measurable and meaningful positive impact on operation. Mining activity totaled 10.4 million tons in the third quarter of 2024, in line with the prior quarter, and our ton mines increased 3.2 million tons during the period, with an associated decrease in the strip ratio to 2.3:1 waste to ore. The average grade of mine ore was 1.02 grams a ton, in line with the mine plan. The reconciliation between the grade control and reserve model is also in line with expected tolerance. Within the pit, the mine currently has two CAT 6060 electric shovels and 18 CAT 793 autonomous haul trucks in operation, with an additional three haul trucks to be commissioned before the end of the year. Utilization rates of the primary mining equipment has been improving. Drilling and blasting activity has seen month-over-month improvement from enhanced drill fleet performance with better blast pattern preparations, resulting in a higher level of in-pit blasted ore inventory available for loading and hauling. The current mine plan is using multiple stockpiles segregated by grade, with the 43-101 estimating a total of 78 million tons of rehandled ore mill feed over the life of mine. This strategy is proving to date to require higher than expected amount of rehandling, which are seeing indications of flowing through to mining costs. Year-to-date, mining costs have averaged $3.77 per ton. This is higher than expectation due to the rehandling, as well as higher contractor costs to support the ramp-up of the mine. We expect to see unit mining costs decline as we bring in the full fleet and reduce the need for external support. Further, we are looking at refining some aspects of the mining strategy to optimize ore handling and move towards more of a bulk mining scenario when economically possible and as the mill continues to increase its overall throughput. The ramp-up of the plan was the primary technical focus of our efforts in the quarter, with a headline milestone of achieving commercial production midway through the quarter, as well as multiple days of achieving above nameplate production. Mill throughput in the third quarter totaled 1.6 million tons, a notable improvement quarter over quarter, though throughput was impacted by the mid-September planned shutdown and an unplanned shutdown at the end of the month from an electrical failure in a motor control center. Head grade of 1.41 grams a ton were in line with the mine plan, which required feed material from a combination of higher-grade direct feed ore and higher-grade stockpile. Recoveries in the plan averaged a wonderful 93% in the quarter. As we noted on the last call, the main component of the processing plan, including primary, secondary crushing, HPGR, conveyors, ball mill, leaching, et cetera., all have now proven their capability to operate at or above design low when provided with stable conditions. During the ramp-up, the primary areas of focus for the plan were one, the crushing circuit before the coarse ore dome, and two, everything else after the coarse ore dome or the downstream circuit, which is the HPGR tube to the west side of the plan. With a coarse ore dome fill, the downstream processing circuits demonstrate very strong performance and availability and capacity, so we have focused on the crushing circuit to improve the availability and capacity. In September, the companies completed an eight-day mill shutdown at Cote to deploy key optimization and improve the operating availability of the plan in support of the goal to ramp up throughput to 90% of nameplate by the end of the year and achieve nameplate in 2025. The priority of the work performed during the shutdown was to stabilize the crushing circuit and attend to the primary causes for low availability in the second quarter, which included replacing 90% of the chute with higher abrasive-resistant material to reduce the level of wear and using new types and sizes of screen in the coarse ore screening area. These improvements have made a difference, and the plan has seen further increases in availability and performance of the secondary crushing and screening over the last few weeks, achieving multi-day performance above 40,000 tons per day in the crushing plant. We are now well positioned to ramp up the overall processing facility to our 90% of nameplate objective as we exit the year. In October, we averaged just under 80% of the nameplate as daily throughput. Achieving the additional 10% at Cote is primarily about stability. The objective is to eliminate daily variances in processing, as we already know that we can meet nameplate capacity of 36,000 tons per day and potentially more. Every downtime brought new information and an opportunity to further improve. It is really now about achieving stability, more consistency. This is how we will earn the additional 10%. Furthermore, we will be installing a second cone crusher in the second half of next year at low capital requirements to provide additional capacity and redundancy in support of the operation and throughput maximization. Lastly, and as we noted previously, Cote d'Ivoire added a mobile crusher unit and conveying system that act as a dome refeed system. This addition provides flexibility and redundancy in time of shutdown by delivering up to 1,000 tons per hour to the dome and can operate in parallel with the crushing circuit for extra daily capacity when sporadically required. Based on a year-to-date ramp-up progress, we maintained our guidance set last quarter for annual production to be at the lower end of the previous guidance range or closer to 220,000 ounces on a 100% basis. At the exit rate of 90% throughput, we estimate that cash costs will, at that time, average approximately $700 to $800 per ounce and all in sustaining costs to be approximately $1,100 to $1,200 per ounce. We know, though, that costs may exceed these ranges depending on the timing and a one-time cost of initiatives and improvement implemented to achieve the ramp-up target. Looking into 2025, we will advance Cote towards the nameplate throughput rate of 36,000 tons per day while looking for an easy win to increase the processing plant capacity. As we have noted in the past, several components of the plant have been designed for 42,000 tons per day, and we have seen multiple days above 40,000 tons per day early on in the lifecycle of the project. The addition of the second cone crusher next year is aligned with our strategy of unlocking maximum value by monetizing at low capital requirements the maximum number of tons of ore mined as they become available for processing. Alongside this, as mentioned, we are evaluating the potential to adjust certain aspects of our mining plan at Cote to potentially shift over time to a more bold mining approach as the mill throughput capacity is unlocked, which offers numerous efficiencies advantages including reduced rehandling, improved pit sequencing, and less reliance on segregations for the mine plant and more on maximizing mill throughput and monetizations of gold mines. Over the current life of mine, the mining rate of ore was estimated to average approximately 50,000 tons per day, and this compared to our processing rate of 36,000 tons per day. The Cote deposit has estimated mineral reserves of 7.6 million ounces that form the basis of the current economics of the project. On a measured and indicated resources basis, the Cote zone is currently estimated at a total of 12.1 million ounces, as seen here in the dark blue pit shell at the bottom left. This does not include mineralization outside of the pit shell, highlighted in red in what we will unofficially call the Cote Northeast Zone. Further to the adjacent Gosselin Zone has an additional 4.4 million ounces of measured and indicated resources and nearly 3 million ounces of inferred, bringing the project to a total of 16.5 million ounces of measured and indicated and an additional 4 million ounces of inferred. The size of Cote and Gosselin together put the project in a very exclusive category amongst large scales producing Canadian assets. We need to consider what Cote will be when it grows up, and that is to say we need to consider Cote not as a 7.6 million ounces project, but as a significantly bigger deposit and how to bring this value to the market. Our exploration program on Gosselin and at depth under the Cote and Gosselin Zone progressed well this year, demonstrating extensions of mineralizations outside of the resource pit shell. Next year, we will plan to further increase our drilling efforts to upgrade the mineralization in Gosselin and the Cote Zone in support of a potential updated study intended for the latter part of 2026. Turning to Westwood, our other Canadian asset. It was another strong quarter for the mine as underground activities are now able to focus on operations and less on legacy rehabilitation. It may surprise some to say, but Westwood so far this year has generated 53.1 million in mine-free cash flow, and the third quarter at a cost profile below Essakane. Looking at operations, Westwood produced 32,000 ounces in the quarter for a total of 99,000 ounces year-to-date. Our mine from underground continued to play a more pivotal role in a higher grade, with 84,000 tons in the third quarter at an average head grade of 9.09 grams a ton. The mill throughput was relatively flat quarter over quarter at 289,000 tons process at an average blended head grade of 3.67 grams a ton and 93% recovery. The plant availability in the quarter of 90% was higher than the same prior year period of 86%, with plans to further improve availability through an ongoing maintenance program in addition to an annual mill shutdown plan in November. The margin for Westwood continued to improve with a strong gold price and stabilizing costs. Cash costs averaged $1,150 an ounce, and all in sustaining costs averaged $1,617 an ounce in the third quarter. Looking ahead, Westwood production is expected to be at the top of the guided range of 115,000 to 130,000 ounces, while costs are expected to be at the lower end of the range of $1,200 to $1,300 for cash costs per ounce sold and $1,775 to $1,900 for ASIC per ounce sold. Four-quarter unit costs are expected to be higher than the third quarter due to the scheduled shutdown mill shutdown in November. This is to better position the operations for next year. Later this month, we will be issuing an updated technical report and mine plan based on reserve only for Westwood, which should demonstrate the value that has been created by the Westwood teams over the last three years of rehabilitation, redesign, and operation. Finally, looking at Essakane, it was a steady quarter at the mine, with operations being able to perform effectively to plan in the quarter. Essakane reported attributable gold productions of 100,000 ounces in the third quarter, bringing the year-to-date total to 329,000 ounces. Mining activity totaled 12.2 million tons in the quarter, with only 1.9 million tons of ore mine, as mining prioritized waste stripping sequences in support of the 2025 production plan, including the opening of the upper benches of Phase 7. Head grades were 1.26 grams a ton, in line with estimates. Average head grades decreased in the third quarter from level in the first half of the year, and are expected to continue to trend towards reserve grade in the fourth quarter as the volume from Phases 6 and 7 increased, and from increased proportion of stockpile are included in the mill fee. On a cost basis, Essakane reported third quarter cash costs of $1,223 per ounce, and all-in sustaining costs of $1,730 per ounce, an increase quarter over quarter on lower ounces sold, with both cash costs and ASIC are on track to be at the low end of our cost guidance range. Looking ahead, Essakane attributable production is expected to be at the top end of the guidance range of 380,000 to 410,000 ounces. The mill is expected to continue operating at nameplate capacity, and the positive reconciliation of Phase 5 is expected to continue. However, the average feed grades are expected to decrease during the fourth quarter, as mining activities continue to transition into the next phases of the pit, resulting in a lower level of ore mine, requiring ore feed to be supplemented with low-grade stockpile material. The focus in the fourth quarter will be to further enhance the phase positioning in the pit for a strong start next year. As we begin to look into next year, Essakane continues to be a significant cash flow contributor for IAMGOLD. With a current mine life through 2028, this operation has the capability to generate over $1 billion of cash flow at current gold price, and is a significant part of our Larkin plan to deliver the company. Looking beyond the mine plan, we are continuing to examine opportunities to extend the mine life at Essakane, targeting options within the fence to ensure the safety of our teams. Thank you all, and I look forward to an exciting year ahead. With that, I would like to pass the call back to the operator for the Q&A portion. Operator?