Renaud Adams
Analyst · CNBC World Markets. Please go ahead
Thank you, Maarten. We will walk through our operating performance at Essakane and Westwood before we dive into Cote. At Essakane, the mine reported attributable gold production of 111,000 ounces in the second quarter, up 26% from prior year periods and bringing the year-to-date total to 229,000 ounces. This was another very strong quarter of operation for Essakane and made possible by our mining operation being able to perform to plan in a quarter compound with continued higher than expected grades. Mining activities total 11 million tons in a quarter with only 2.2 million tons of ore mined as mining worked through a higher strip sequencing of the mine, coupled with limited mining in a part of Phase 6 due to localised instability which required enforcing and has been addressed since then. Head grade remain high at 1.46 grams a ton due to the continued positive reconciliations of grade from the reserve model as we continue to mine deeper into the Phase 5. This positive grade reconciliation in the deeper portions of Essakane was seen previously in Phase 5 and is continuing in Phase 4 and continuing in Phase 5. However, we are seeing head grades decline in line with the life of mine plan as volumes from Phases 6 and 7 increase and from increased proportion of stockpiles ore included in the mill fee. On a cost basis, Essakane reported second quarter cash cost of $1,081 per ounce and all-in sustaining costs of $1,481. The slight increase from the prior quarter went below our previous guidance due to strong productions and gold sales. With a strong first half of operations in 2024, Essakane production guidance has been revised upwards with attributable production expected to be in the range of 380,000 to 410,000 ounces. This compared to the prior guidance of 330,000 to 370,000 ounces of gold. The mill is expected to continue operating at nameplate capacity, though at average head grade slightly lower than in the first half of the year as per the mine plan. The cost guidance for Essakane has also been revised downward and is expected to be in the range of $1,175 to $1,275 for cash cost per ounce sold, and $1,575 to $1,675 for ASIC per ounce sold, approximately $100 to $125 per ounce improvement on both metrics due to the outperformance in the first half of the year. Capital expenditure guidance has been increased to approximately $175 million, primarily due to an increase in the strip ratio, not total tons mined, resulting in more mining costs being included in capitalized waste and equipment replacement. Essakane continue to be a significant cash flow contributor for IAMGOLD. With the current mine life through 2028, this operation has the capability to generate over a $1 billion of cash flow at current gold prices. We are continuing to examine the opportunities to extend the mine life of Essakane targeting options within [defence] (ph) to ensure the safety of our teams. Turning to Westwood, I want to congratulate the team on another improvement in the quarter. As the mine continues to test new highs and quarterly volumes from underground grades and production since the mine restarted in 2021. This improvement has meant that Westwood has generated, as Maarten noted, positive mine-free cash flow of nearly $22 million in the second quarter, bringing the year-to-date total to just over $32 million. On operation, Westwood produced 35,000 ounces in the quarter, a significant 84% over prior year period and bringing the year to date total to 67,000 ounces here today. Our mines from underground continue to step up and at a higher grade with 89,000 tons in the second quarter contributing to an average head grade from undergrown ore of 9.2 grams a ton. Mill throughput also increased in the quarter to 302,000 tons processed at an average blended head grade of 3.92 grams a ton and 92% recovery. The increase in throughput was driven by improved availability of 89% due to the ongoing maintenance program. The cost profile for Westwood continues to decline as operations improve. Cash cost averaged $1,131 an ounce and all-in sustaining cash averaged a promising $1,663 an ounce in the second quarter, continuing the trend of quarter-over-quarter cost improvement. Looking ahead, we have raised our guidance for this year, with Westwood now expected to produce between $115,000 to 130,000 ounces of gold at lower cash costs of $1,200 to $1,300 per ounce and ASIC of $1,775 to $1,900 per ounce. In the fourth quarter, we will be issuing an updated technical report and mine plan for Westwood, which will provide an updated mineral resource and reserve estimate and life of mine based on the last 2.5 years of mine optimizations efforts at Westwood. Turning to Cote Gold, we couldn't be more impressed with the work of our teams on the ground as they brought Cote to commercial productions only four months after the initial gold pour on March 31st, 24th, which was achieved within 90 days of first pre-commissioning activity. The ramp up of Cote has seen the project hit significant milestones in its first few steps as of mine. We took the path of testing first the capacity of the main equipment that drives the ultimate nameplate objective, and then build availability as we ramp up. From early on, the primary components of the processing circuits, primary and secondary crushing, HPGR, conveyors, ball mill, leaching, et cetera. All have proven their capability to operate on their design load when provided with stable conditions. During the same period, we also took the time to all of the team to stop and correct several deficiencies, as it is usually the case at early days of ramping up a large scale facility. The first week took about the whole first half of the second quarter, where 45 days go fast. In the second half of the quarter, efforts were made on slowly but surely cranking up the engine and testing the stability and the overall availability of the processing facility, while identifying all potential limiting factor to objective of exiting the year at 90% nameplate. In early July, the team pushed a commercial production button and reached our objective 30 days later, with nameplate production of 36,000 tons achieved on August 1st as the last day. On the dry side, we can report that we are very pleased with the performance of our HPGR and believe that it will bring great value down the road. During the ramp-up phase, we have identified some improvement required on the dry side in order to achieve design availability and performance. The first one has to do with mitigating the effect of abrasiveness on wear parts. The art Cote is highly abrasive, which was always known, but with actual effect to be experienced. Availability of the crushing and screening circuit in the second quarters was somewhat impacted by accelerating wear on the liners, feeders, and chute due to this abrasiveness. The new lining material has been identified and tested with good results in some critical area. Second, the continued core screening performance was also limited during ramp up. A new panel design are being proposed. Finally, dust management was challenging in the early days, and in particular, in the screening building. And while significant improvement has been made, more corrective action needs to be made. We have tested additions of suppressions, both water and surfactants, system in critical area with great results. So all in all, everything is solvable. We have identified corrective actions and we have initiated implementation of that. The company is planning a multi-day shutdown in September, at which time we will deploy key optimizations to address all of the issues and improve the long-term availability of the plant. We are very confident in the ability of Cote to ramp up well this year once we address these issues. Further, the power requirement of the plant has been lowered and unsuspended, providing important available capacity for down the road. In the second quarter, mining activities achieve a new high of 10.5 million tons of total material mined. Further, grade mined are continuing to come largely in line with our grade control block model in the current life of mine. Mining costs in the quarter, despite not yet running at full run rate, were comparable to Canadian open pit peers at just under the $4 a ton. An increase from the prior quarter due to temporary optimization activities on blasting patterns and production drilling, as well as some power curtailments experienced in June due to unseasonal heat wave. On processing, mill throughput in the second quarter was 834,000 tons at an average head grade of 1.4 grams a ton for a total of 34,000 ounces produced on a 100% basis. Revenue circuit would successfully commissioned toward the end of the quarter and recovery has responded well to the ramp up of the operations, averaging 90%. In July, Code Gold processed over 620,000 tons of ore with productions of nearly 26,000 ounces of gold. We have maintained our guidance at Code for this year, though we have guided to the lower end of the range of 220,000 to 290,000 ounces on a 100% basis. As improvements to mail availability are made during the ramp up of operations, reducing [indiscernible] prior to completing those solutions. We believe that exiting the year at nearly nameplate will set Cote and IAMGOLD for huge success starting early 2025. I will now hand the call back to Maarten for a brief update on projects ending this year.