Gord Stothart
Analyst · CIBC. Please go ahead
Thanks Carol. So operationally we had a decent quarter, not as strong as the first two quarters but solid enough to confirm total production and cost guidance for the year. Despite the lighter production at Rosebel, besides making excellent progress with initiatives to increase productivity and reduce costs. Essakane's mill output continues to be stellar and Westwood's production ramped up is on track. We finalized the new two year collective labor agreement at Rosebel and union members at Westwood would favorably on a new 5-year selective labor agreement. We continue to execute on our growth projects with success in enhancing expected returns. Attributable production for the third quarter of 208,000 ounces brings year-to-date production to 651,000 ounces. Although Rosebel's lower grades and mining tonnage impacted their performance during the quarter, after nine months we're 75% of the way to achieving the mid-point of our consolidated annual guidance. So we're right on-track. Year-to-date all-in sustaining costs were $1,035 an ounce. All-in sustaining costs for the quarter were impacted by lower sales of Rosebel and lump-sum payments to employees at Rosebel and Westwood in accordance with the new collective labor agreements. Although there's no change to our total production and cost guidance for the year, we have revised relative allocation to production guidance between the operations. As again guidance has been raised to reflect higher throughput and grades and Rosebel's was lowered with the decline in mining tonnes and head grades in the third quarter due to timing issues. Sadiola's guidance has been revised slightly upwards and Westwood's remains unchanged. At the consolidated level, 2018 production guidance remains unchanged at 850,000 to 900,000 ounces. We reassessed our CapEx outlook and have lowered guidance for 2018 to $305 million plus or minus 5%. This reflects a $20 million reduction in non-sustaining capital expenditures to $145 million. The $10 million reduction at Rosebel is mainly the result of deferred spending for the Saramacca project based on final engineering work, lower spending on indirect costs and the removal of the 2018 cost contingency. This has no impact on the completion date for the Saramacca project, the $5 million reduction at Essakane reflects the deferral to Heap Leach Project as we refocus the feasibility study on mill optimization. The $5 million decrease at Sadiola reflects where we stand with the Sadiola Sulphide Project. Turning to a site-by-site review of our operations and beginning with Essakane, so Essakane continues to perform very well. Attributable production of 96,000 ounces in the third quarter was up 3,000 ounces from the same quarter 2017. The increased output was mainly due to higher grades. As I said, Essakane's production guidance has been increased for the year, with commissioning of the oxygen plant this quarter, we expect a 0.5% increase in recoveries moving into 2019. Throughput as well has increased for the year as mill availability has been running higher than originally programmed. The mill continues to run 25% above nameplate capacity with annualized throughput of approximately 13.5 million tonnes on an 85% hard rock blend. The third quarter all-in sustaining cost at Essakane were $993 per ounce. The increase from the same quarter last year was due to higher sustaining capital expenditures. On last quarter's conference call, we talked about the 39% increase in reserves at Essakane, with higher grades encountered during PFS drilling accounting for about a third of the increase. We indicated that we could run Heap Leach in parallel with the existing carbon-in-leach processing. After reevaluating our options, we've decided that due to encouraging drill results in the push back zone, it is strategically and economically better to refocus the feasibility study on optimizing the performance of the carbon-in-leach circuit in the near term. We will still build the heap leach facility but not until the end of the CIL operations. In the interim, we will stockpile the heap leach grade for protecting the reserve declaration from June. This alternative will reduce our capital requirements at Essakane by at least $100 million next year, freeing up capital that can help fund our other growth projects. Turning to Rosebel, attributable production of 67,000 ounces in the quarter was 11% lower than the same period in 2017. The main reasons were lower head grade and throughput. We're already seeing good improvement in the fourth quarter along with further improvements expected once Saramacca with grades nearly double that of Rosebel's brought into production. Mine production was lower than the same period in 2017 mainly due to lower labor productivity during the collective labor agreement negotiations. With the new agreement signed on September 14, we are now seeing an improvement in mining productivity particularly with components of the variable compensation which are tied to productivity targets. Rosebel's all-in sustaining cost per ounce were significantly higher than the previous year, reflecting lower sales. Additionally, there was $1.7 million lump sum payment to employees in accordance with signing the new CIL and that had a $26 per ounce impact. Other factors were higher energy costs, increased maintenance, and lower capitalized dripping due to mine sequencing. On September 23, we announced 51% increase in Rosebel's reserves, a number of you were on the call so to briefly recap the highlight, the declaration of 1 million ounces in reserves for Saramacca on a 100% basis account for nearly two-thirds of the increase. Incorporating soft rock from Saramacca provided greater flexibility around blending ores, so we were able to add 400,000 ounces from the Koolhoven deposit. The additional 1.6 million ounces of reserves extends Rosebel's mine life by five years to 2033. Once Saramacca is at end or close to full production, Rosebel's average annual production will increase by 11% to 295,000 attributable ounces with 362,000 ounces during the peak years. We're progressing towards a production start in the second-half of 2019. Permitting is expected to be completed this quarter. Engineering and construction work is progressing well. Firm orders have been placed for the acquisition of the long haul fleet and the initial mining equipment fleet. The haul road between Saramacca and Rosebel is in the final phases of detailed engineering and road construction work is commenced on the Rosebel mining concession. The project team continues to work in improving the project economics. We feel it's too early to be publishing definitive class numbers when we see several strong opportunities for improvement. As I mentioned last quarter, we are also planning to begin conceptual studies next year to look at the potential for underground mining given the high grades intercepted during the initial expiration of the project. Once we've completed a preliminary round of the life of mine plan incorporating Saramacca, we should be in a much better position to provide more color so you can update your models. At Westwood, third quarter production was 30,000 ounces, a 3,000 ounce decrease from the previous year reflecting lower grades and slightly lower throughput. As per planned, Westwood mined lower grade stopes during the quarter. As in previous periods, reported mill grades were lower than mined grades, which is due to processing a proportion of marginal ore stockpiles to leverage available no capacity as the mine continues to ramp up. A new five-year collective labor agreement was signed on September 20, 2018. The inclusion of a $1.1 million lump sum payment had a $38 per ounce impact on cost of sales. All-in sustaining costs increased by 15% year-over-year due to the higher cost of sales, as well as lower sales volumes and higher sustaining capital expenditures. The increase was partly offset by a stronger U.S. dollar relative to Canadian dollar. As we progress toward the ramp up to full production in 2020, underground development continues to open up new mining areas. During the third quarter, the central ramp breakthrough was completed. While development work continued on the ramp breakthrough on level 132, this breakthrough at this level should provide access to higher grade areas for 2019. Infrastructure development continues in blocks at the lower levels including the 180 west level from which production is expected in 2019. At our Sadiola joint venture, attributable production in the third quarter of 2018 was 14,000 ounces, down slightly from Q3 2017, with the lower head grades. As in past quarters, the continued drawdown of marginal ore stockpiles is reflected in the higher cash cost. Lower all-in sustaining costs reflected nominal amount of sustaining capital expenditures compared to the previous year. Processing of stockpiles will come to an end midway through next year. While the agreement with the Government of Mali has not been reached around the terms necessary to proceed with the Sadiola Sulphide Project, we have together with our partner EGA initiated a process to identify third parties who may be interested in acquiring our collective interest in Sadiola. This process is at a preliminary stage and there is no certainty of its outcome. Now turning to our development projects. We announced feasibility study results for the Côté Gold project on November 1 that demonstrated significant economic and operational improvements from the prefeasibility study. For benefit of those not on the conference call following the announcement I’ll recap the highlight and I’ll speak to the numbers on a 100% basis. So compared to the PFS proven and probable reserves increased by 23% to 7.3 million ounces measured and indicated resources inclusive of reserves increased by 24% to nearly 10 million ounces and referred improved resources nearly doubled to 2.4 million ounces. A significant amount of derisking has been completed with multiple reserve and resource updates. So when we acquired Côté in 2012, the deposit comprised 6 million inferred ounces and just under 1 million indicated ounces and since then M&I resources have increased tenfold on a 100% basis. The feasibility study presented both a base case mine plan and extended mine plan. The base case is supported by 88% of the reserves and is aligned with the current permitting process. The extended mine plan exploit all of the mineral reserves, demonstrating the full potential of this project both scenarios assume $1,250 gold price unchanged from the PFS compared with the prefeasibility study both plans show mill throughput increasing to 36,000 tonnes per day. A lower strip ratio and slightly higher grades with the base case mine plan the after-tax IRR has increased to 15.2% and the after-tax MPV by 13% to $795 million. The mine life for the base case is 16 years the average annual production increased by 15% to 367,000 ounces and actually averages 428,000 ounces for the first 12 years. LOM average total cash costs were $594 per ounce and all in sustaining costs were $694 per ounce. With the extent in mine plan the after-tax MPV increased by 29% versus the PFS to $905 million with an after-tax internal rate of return of 15.4%. In this case the mine life would be 18 years with an average annual production increasing 16% to 372,000 ounces per year averaging 407,000 ounces for the first 15 years of production. LOM average total cash costs were $606 per ounce and all in sustaining costs at quarter $703 per ounce. The payback period of under four and a half years remains the same for both scenarios with no change in the initial CapEx. With the extended mine plan additional permits to raise the height of the mine rock area and the tailings management facility may be required. We expect construction decision in the first half of 2019 which would allow to begin production around mid 2020/2021. Turning to our Boto gold project we published the feasibility study results in October 22 again having gone through the details in the conference call I’ll just run through the highlight. And these results showed significant economic and operational improvement compared to the prefeasibility study which we announced earlier this year. On a 100% basis and compared to the PFS reserves increased by 36% to 1.9 million ounces indicated resources inclusive of the reserves increased by 29% to 2.5 million ounces after-tax IRR increased to 23% with a 3.4 year payback period compared to 13.3% after-tax IRR in the PFS. After-tax MPV increased by 151% to $261 million despite a lower gold price assumption of $1250 per ounce. Life of mine average annual production increased to 140,000 ounces over 12.8 years with a 160,000 ounces being produced on average in the first six years. Life of mine total production is expected to be 35% higher at approximately 1.7 million ounces. Life of mine AISC averages $753 per ounce, mill throughput is 37% higher with only a minor change in upfront capital costs. We’re still in the early stages of preparing a development timeline as a final investment decision needs to be made and there's permitting work to be completed. An application for mine concession for the project has been submitted to the Government of Senegal and we expect approval in the first half of next year. In the meantime we’re working to optimize certain aspects of the project design and expiration is focused on expanding resources near the pits and identifying targets for additional resources. And on that note, I’ll turn it over to Craig to talk about exploration in our other projects.