Gord Stothart
Analyst · National Bank
Thanks, Carol. Well, our operations performed well in the second quarter, but that first quarter was a tough act to follow. Production in Q1 benefited from the planned mining of higher grade zones and significant positive grade reconciliation at both Essakane and Westwood, whereas Q2 was impacted by planned maintenance at Rosebel and Essakane and the planned mining of lower grade stopes at Westwood. Nevertheless, the performance was in line with our expectations. Production continues to attract post the guidance. Second quarter production of 214,000 attributable allowances brings us to 443,000 ounces year-to-date, which puts us just over the halfway mark of the midpoint of our full year guidance. As Steve said, our annual guidance is reiterated at $850,000 to $900,000 attributable allowances. All-in sustaining costs in the second quarter were $1,077 an ounce and $1,012 an ounce year-to-date. Full year guidance remains unchanged at $990 an ounce to $1,070 an ounce. Turning to our capital spending outlook for 2018, we are reducing our guidance by $40 million to $325 million plus or minus 5%. This was the net result of the $60 million decrease in non-sustaining capital and a $20 million increase from sustaining capital. The $60 million decrease in non-sustaining capital was primarily due to a $40 million decrease at Rosabel relating to the Saramaca project. As a result of more specific scheduling of construction work and equipment procurement timelines based on detailed engineering studies, we’ve been able to defer certain expenditures to 2019. There’s no change to the targeted completion date of the project, which has production starting in the second half of 2019. At Essakane, we reduced non-sustaining capital guidance by $25 million of that amount $20 million is related to the Heap Leach project. This was due to deferring procurement activities until after the feasibility study is completed in the first quarter of 2019. As with Saramacca, this does not affect the project delivery timeline. The change in non-sustaining capital guidance also includes a $10 million increase for the Coté Gold project reflecting the advancement of some detailed engineering and equipment design work. The $20 million increase to sustaining capital reflects a $15 million increase at Essakane due to higher capitalize stripping. Because this is a shift in expenditures from operating costs, there is no impact on all-in sustaining costs, it’s merely a categorization change. So to reiterate, these revisions to our 2018 capital spending guidance have no impact on our overall project timeline. The targeted completion dates for all projects remain intact. Moving on to each of our operations, starting with Essakane, attributable production for the second quarter at Essakane was 97,000 ounces down about 4% in the same quarter in 2017. This was mainly due to lower throughput resulting from planned mill maintenance. Gold recovery at 91% was consistent with the past four quarters. We do expect to see an improvement in recovery following the commissioning of the oxygen plant, we expected in the fourth quarter of this year. All-in sustaining costs were $1,003 an ounce in Q2, up $81 an ounce from the previous year. This is was mainly the result of higher sustaining capital expenditures and higher cost of sales per ounce. Cost of sales were higher due to a number of factors, including no maintenance, a weaker U.S. dollar relative to the euro and higher contractor costs due to the longer lead times on some new production equipment purchases. On June 5th, we announced the positive results from the pre-feasibility study of our Heap Leach Project of Essakane. The study represented a very positive scenario combined Heap Leach -- combining heap leaching in parallel with the existing CIL process plant. To recap the highlights, reserves increased by 39% or $1.3 million ounces on 100% basis before depletion. Please note that the technical report which was filed on CEDAR on July 19th, included depletion from January 1st to June 5th, whereas the reserves and resources reported on June 5th, were before depletion. While we knew that heap leaching would unlock ounces that would otherwise not be economical to mine, we didn’t expect to encounter the high grades that we did which accounted for one-third of the reserve increase. To appreciate the full benefits of this project you have to consider the combined benefits of heap leaching together with the incremental production from CIL processing. Incorporating heap leaching into the operation, results in additional CIL production that will extend the life of the mine three years from that reported in the 2016 technical report. Mine life is expected to be eight and a half years with CIL mill throughput of 12 million tonnes per annum and heap leach throughput of 10 million tonnes per annum. Once heap leaching begins, average annual production will increase by 16% from our previously disclosed plan to 480,000 ounces annually on 100% basis with peak production exceeding 500,000 ounces. A feasibility study is evaluating additional development alternatives such as a gravity circuit upgrade and an increase in grinding capacity to increase throughput and recovery of the CIL and gravity circuits, as well, the feasibility study will allow us to optimize the number of conservative assumptions that were included in the PFS, such as heap leach recoveries and manpower requirements. So, when you consider this reserve increase along with the additional ounces that could come from satellite resources, we believe there’s strong potential to extend Essakane’s mine life beyond 2030. As I said earlier, the feasibility study is on track for completion in the first quarter of 2019 followed by an expected production start in 2020. Turning to Rosebel, second quarter attributable production was 70,000 ounces. Production was lower than the previous year by 4,000 ounces due to planned mill maintenance and an increasing hard rock land. All-in sustaining costs were $1,035 an ounce. The increase from the same period in the previous year primarily reflected the planned mill -- mine and mill maintenance and the higher energy costs. At the Saramacca project development work is progressing well. The initial reserve estimate is expected in the second half of this year. Detailed engineering work related to site infrastructure in the haul road is nearly completed. The long haul trucks have been selected and orders placed and the environmental social impact study to support the permitting and engineering work was submitted to the National Institute for Environment and Development or NIMOS in Suriname last week on July 31st. So permitting should be completed by the end of this year. As I said earlier, despite pushing out some of the capital expenditures into next year, the timeline remains intact when the production starts in the second half of 2019. In the first four years to five years, we expect the mill to be exclusively saprolite with transition and hard rock in the following years. We see an optimal throughput rate of somewhere between 2 million tonnes per and 3 million tonnes per year additional. Annual attributable production from Saramacca could be between 70,000 ounces and 90,000 ounces a year over 10 years to 12 years of life. At Westwood, second quarter production was 31,000 ounces, down 2,000 ounces from the previous year, compared to record production in the first quarter with the mine of high grade zones, lower grade stopes remind in the second quarter as planned. As in previous periods, reported mill grades were lower than mine grades. This is due to processing of marginal grade or stockpiles in addition to the underground ore to utilize available mill capacity as the mine ramps up. Excluding this marginal lower, the head grade was about 32% higher than was reported for the mill in this quarter. All-in sustaining costs were $1,129 an ounce for the quarter. The year-over-year increase reflects a weaker U.S. dollar relative to the Canadian dollar and higher sustaining capital expenditures. Underground development continues to open up new mining areas. The focus is now on ramp breakthroughs on the center ramp and on level 132, which will provide access to high grade areas to be mined in 2019. Infrastructure development continues in blocks on the lower levels including the 180 West level from which production is expected next year. We may on -- we remain on track to reach full production rates in 2020. At our Sadiola joint venture, attributable gold production in second quarter 2018 was 16,000 ounces. With the mining of oxide ore now depleted, mining activities has ceased and the mills processing stockpiles. Once the stockpiles are depleted, which we expect will be around mid-2019 and if there is no agreement in place to advance the Sadiola Sulphide project, Sadiola will be placed on suspended operations. Turning to the Côté Gold Project, the feasibility study is on track for completion in the first half of 2019, our production start is targeted for early 2021. Results from delineation drilling completed in the first quarter will be reflected in the reserve and resource update that will accompany the feasibility study. Geotechnical investigations to evaluate pit slope stability and investigate proposed locations for key project infrastructure were completed in the second quarter and will be reflected in the project design. An important goal of the feasibility study is to identify opportunities for improving project returns. One change we’ve made in the feasibility study is to increase mill throughput by about 10% to 36,000 tonnes per day or around 13.2 million tonnes per annum. We’re committed to autonomous haulage and autonomous drilling as the base case and we are looking at other proven technologies that could be applied where it is advantageous to do so. And as I said earlier, detailed engineering and equipment design activities have been advanced as part of an early works program. Turning to the next slide, the feasibility study for the Boto Gold Project is on track for completion in the second half of this year. As with our other projects at this stage, we’re looking at opportunities to enhance project returns. For example, we’ve increased mill throughput by 25% from what was used in the PFS to 2.5 million tonnes per annum, we believe we can do this without increasing capital costs. Exploration work continues in support of the feasibility study and to identify potential targets for additional mineralization. And with that, I will now turn you over to Craig to talk about exploration.