Thanks, Carol. Good morning everyone. At Rosebel, slide 14, attributable gold production was 95,000 ounces, compared to 94,000 ounces in both the previous and prior year period. Our focus at Rosebel has been on increasing the capacity to treat hard ore. With the expansion of the gravity circuit near completion, the recovery rate has continued to improve, climbing from 94% in the first quarter to 96% in the second, and in the third quarter, we actually reached 97%. Higher recoveries were partially offset by lower throughput, which was down year over year, although up from the second quarter. Throughput is improved during 2012, with the installation of the precrusher and the larger pebble crusher, and will further benefit from the completed installation of the third ball mill early in 2013. At that time, we expect to have completed the feasibility study, which will give us more design detail around the optimization project. Cash costs of $689 an ounce in the quarter were higher than in the same quarter of 2011. This was mainly due to higher power, fuel, and labor costs associated with an increase in tonnage mined and a higher proportion of hard rock. At Essakane, we produced 77,000 [attributable] ounces in the third quarter, down from 86,000 ounces in the same period in 2011. While the tonnage of ore milled was 33% higher than in the previous year, lower recoveries and the processing of lower grade ore were behind the lower production. Cash costs continue to be impacted by lower grades and a higher strip ratio. The plant expansion to double hard rock processing, which started in July, continues, with completion expected by the end of 2013, and commissioning at the beginning of 2014. As Steve mentioned, negotiations with the government on the fiscal terms took longer than anticipated, so a portion of our capital spending intended for 2012 will be pushed forward into 2013. Essakane remains a solid and well-run operation. We continue to focus on improving productivity, and we signed a labor contract last quarter providing for a 5% increase over each of the next three years. Looking at slide 16, at Sadiola, our joint venture operation at Sadiola has been an underperformer. Lower throughput and lower grades caused production to slip, with little chance of catch up by the end of the year. At 26,000 attributable ounces for the third quarter, production was down 4,000 ounces from the third quarter of 2011. Compared to the second quarter, gold production increased slightly, as lower throughput was partially offset by a significant improvement in recoveries. Recoveries climbed from 84% in the second quarter to 94% in the third, reflecting a move from sulfide ores to oxide ores and enhancements to the gravity circuit. While we can’t advance the sulfides expansion project without formal approval from Anglo’s board, we’re ready to begin prestripping the main pit to access the underlying sulfides beginning in 2013. We’ve revisited our timing assumptions for Sadiola, and will push some of the planned expenditures for 2012 into 2013. At Niobec, throughput was up 7% from both the same quarter in 2011 and the previous quarter. With lower grades, however, production in the third quarter remained unchanged from both periods. We continue to target the completion of the expansion feasibility study by the third quarter of 2013, and to complete permitting in 2014. At Westwood, we’re in the home stretch as we prepare to transition from a development project to an operating mine in the first quarter of 2013. From a project management perspective, the development team has done an outstanding job keeping the project on track. Since development began in early 2008, there’s been no slippage in the timeline. At quarter end, shaft sinking had less than 140 meters to go to reach our year-end target of 1954 meters. The [paced] backfill plant, and the plant refurbishment will be completed before year end. The new wastewater treatment plant is operational, and the sewage and potable water network is complete. Lastly, the union membership ratified a six-year contract with an effective date retroactive from December 1, 2011. Production will begin in the first quarter of next year, although the initial ramp up will be slower than expected. Craig will now provide an update on exploration.