P. Gordon Stothart
Analyst
Thanks, Brian, and good morning, everyone. I'm going to start with Slide 15 and talk about Rosebel. So at Rosebel, attributable gold production was 94,000 ounces, up 8% from the same quarter in 2011. The increase in production was a result of higher throughput and higher recoveries. The improving trend in recoveries from 90% -- 94% in the first quarter to 96% in the second quarter is partially the result of the expanded gravity circuit, coupled with improved circuit stabilization after installation of an expert control system in the grinding circuit. With the installation of the gravity circuit about 90% complete, it's been a partial operation with the first new Falcon concentrator being brought online in April and the second in May. Managed mine at Rosebel was virtually impacted by heavier rainfall as we signaled in our first quarter summary and was lower than the previous year due to longer haul since opening of the Rosebel pit. With a temporary pre-crusher already installed and the larger pebble crusher to be installed by the end of this quarter, we expect throughput to accelerate and expecting to see a good second half. In early 2013, we will complete the installation of the third ball mill, as well as complete the feasibility study to provide greater design detail around various expects of the expansion project. Essakane is operating well, with attributable gold production of 81,000 ounces in the quarter, up from 62,000 ounces in the second quarter of 2011. The issues curtailing production in the same quarter in 2011 have been addressed, although we are seeing a lower grades versus the prior year as per the original development schedule. In the first week of July, we'll be adding construction on the expanded plants, which will increase the throughput capacity for harder rock. This should be completed by the end of the 2013, with commissioning expected at the beginning of 2014. Total expenditures in the quarter were lower than originally expected, as we needed to reach final agreement on the fiscal terms as they relate to an expanded operation. As you heard from Steve, pleased with the direction negotiations have taken. With year-to-date production of 161,000 ounces, we're confident that the full year production at Essakane will fall within our guidance range of 320,000 to 345,000 ounces for the year. Moving to Sadiola. Although the unrested Mali has not had a significant impact on production at Sadiola, attributable production of 22,000 ounces was lower than last year due to a combination of factors: Lower throughput resulting from lower mill availability, lower grades and lower recoveries due to graphitic ore in the first half. To improve performance, we've installed an additional crusher to increase throughput of hard ore, we've installed equipment to increase the usage of the gravity circuit to improve recovery and we've taken steps to accelerate access to higher grade or in the satellite pits. We expect full year production to be at the lower end of our guidance range for Sadiola. Moving to Slide 18. At Niobec, production in the first quarter was up 9% from the same period in 2011 due to higher conversion of Niobian pentoxide and higher recoveries, partially offset by lower grades. On the expansion front, the feasibility study should be completed by the third quarter of 2013 and the permitting process finalized by 2014. Underground drilling continued in the second quarter with drill results as expected, and we continue to anticipate the upgrade of mineral resources to mineral reserves at Niobec. At Westwood, shaft is now at a depth of 1,705 meters, and more than 6,800 meters of lateral and vertical excavation has been completed this year to date. The project remains on track for start-up in early 2013. Infill delineation and resource expansion drilling continued to show an extension of the mineralization giving us increasing confidence in reserves and resources. And now, Craig will provide an update on exploration.