Gil Clausen
Analyst · today's presentation and Copper Mountain's fourth quarter 2021 Management's Discussion and Analysis for your information. I will now turn the call over to Gil Clausen, President and CEO of Copper Mountain. Please go ahead, sir
Good morning everyone and thanks for joining us. We are starting on Slide 3. Presenting with me are Rod Shier our Chief Financial Officer and Patrick Redmond our Senior Vice President of Exploration and Geoscience. Unfortunately, Eric Dell our Senior Vice President of Operations won't be able to participate this morning. I'll begin by highlighting some of our main achievements in 2021, then give a more detailed discussion on our operations during the quarter along with an update on some of the projects we have at the Copper Mountain Mining. Rod will speak to our financial results and Patrick will provide an update on our job programs. I will wrap up with a further update on our Eva Copper project in a brief discussion of our 2022 guidance. We will then open the call to questions. Turning to Slide 4. We had a strong 2021 finishing the year with record revenue, net income, EBITDA, and cash flow. These results were driven by record annual production of about 90 million pounds of copper and higher copper prices. This was achieved in the face of a very demanding fourth quarter in which we experienced severe weather impacts and a major failure of our secondary crusher. We had heavy rains and flooding followed by severe cold temperatures which caused extremely difficult operating conditions in December, I'm very proud of our team for coming together and pulling through. It's because of them that we met our production guidance range which we had increased earlier in the year. We ended up coming right in at the mid-point of our original guidance and the bottom of our revised guidance range. With these strong financial and operating results we finished the year in a very solid financial position with nearly 180 million of cash and a low net debt to EBITDA ratio of 0.6. This was a significant improvement from the end of 2020 and also we completed a transformational financing earlier in 2021 with the U.S. $250 million bond raise, allowing us to repay the more restrictive debt we had in place so that now we can access 100% of our cash flow from the mine. Also in the year we commissioned our new Third Ball Mill which completes the 45,000 ton per day mill expansion project. This increases throughput and improves recovery resulting in higher production going forward. We made another step forward in our growth plans with the approval of construction for the Eva Copper project contingent of course on the lifting of COVID-19 restrictions in Queensland, easing of material and labor flow, getting project financing complete, and completing the detailed engineering to an 80% level. A big achievement in 2021 that we're very proud of is hitting our sustainability targets for the year. Our goal was to meet or exceed an A rating in each of the TSM protocols and we did just that. I will now detail our operating results and development plan but first I am going to start with an update on safety. We saw a significant reduction in our total injury frequency rate in 2021 compared to 2020, achieving a record low since the start of Copper Mountain’s operations. Our lost time injury frequency rate is also below PC average for mines, so we're proud of the accomplishments for this year and we're demonstrating that steady trend of declining injury frequency rate. I will now move on to production turning to Slide 5. As I mentioned, the fourth quarter was challenging with production of 16.7 million pounds of copper, production was lower than the fourth quarter of 2020 due to lower grades and reduced throughput. The lower grades was a result of ore being mined mainly from the lower grades Phase 2 area for most of the quarter. We did plan this for the commissioning of Ball Mill 3. Lower throughput was a result of that commissioning, damage to the secondary crusher’s main shaft in the second half of November, and severe cold weather in December. The severe cold weather created more difficult operating conditions including frozen bins and conveyor system damage due to frost chunks in feeders, particularly for the feeder belt from the SAG Mill. The secondary crusher main shaft was temporary fixed, weld repaired by early November. However, the temporary nature of that fix required us to reduce power to preserve that shaft repair and that reduced power results in coarser crushed products and so therefore we have lowered SAG throughput as a result. Because of temporary nature of this fix the mill throughput is expected to remain at a reduced level of about 35,000 to 38,000 tons per day as we baby this crusher along through to [mid 2] (ph) and that's when we expect to install a new main shaft at in or around the end of April. We expect production to be stronger in the second half of the year compared to the first half of the year with the installation of the new crusher shaft, the completion of our plant’s improvement projects, and as we begin to mine higher grade ore from Phase 4. Just to touch on cost before we move on, cash costs on a per pound basis were higher in the fourth quarter largely due to lower production and higher operating costs from diesel and steel grinding media supply and subsequent cost pressures. Turning to Slide 6. As mentioned most of our ore came from the lower grade Phase 2 area of the main pit. The Phase 4 push back continued in Q4. We moved 5.4 million tons of waste from Phase 4 accounting for 65% of the total waste movement in the quarter. Phase 4 mining is continuing to progress and it will be the main ore source for the second half of 2022 and into 2023. We have now started the North Pit pre-stripping development as well. Turning to Slide number 7. The company has been investing at our plant to improve efficiencies, copper recovery and production. We achieved a significant milestone with the commissioning of Ball Mill 3. The new mill will allow us to increase throughput as I mentioned to 45,000 tons per day and achieve a finer grind and that will help us improve our overall metal recovery by about 3% to 5%. We have run Ball Mill 3 up to capacity but we won't be able to get to a steady 45,000 tons per day until we fully repair the secondary crusher and it begins to grind at its design rate. So the SAG Mill won't be able to get up to feeding the 3 Ball Mills fully until that crusher is repaired. We're also installing another concentrate filter press and increasing cleaner circuit flotation capacity. This new filter press will be installed in an extension to the existing concentrate storage building -- sorry, as shown on the bottom left of this image. A new large flotation column cell is being installed inside the existing mill building and an expansion of the rougher flotation circuit will take place to the North of the building. Turning to Slide 8, this new filter press will allow the mill to maintain maximum tonnage rates while processing higher grade ore for extended periods. Concrete installation is nearing completion and the filter press is expected to be delivered on site by the end of March. The cleaner column expansion will support maximum cleaner circuit recovery for all ore types, eliminating a production bottleneck at higher grade and tonnage. The concrete work has been -- now been completed and we're starting the assembly of the column. The expansion of the rougher flotation circuit will enhance a rougher recovery for all ore types and provides expanded retention time in the rough re-circuit. All of these projects are advancing well, and we expect to complete construction by the end of Q2 this year. These projects are part of our longer-term growth plan and they will generate significant value by increasing our overall return on invested capital in the mill. Turning to Slide 9, we're rather excited about this project at Copper Mountain, it's the Trolley Assist project. It will significantly reduce our greenhouse gas emissions as we reduce our diesel usage. We completed the 1 kilometer haul road in the third quarter last year, the Trolley e-house is being delivered to site and installed and we finished installing the 25 KV transmission line to the e-house. We're targeting to commission the first four Trolley Assist haul trucks by the end of Q1 2022. I'll now turn the call over to Rod to go over our financial results.