Earnings Labs

Fortuna Mining Corp. (FSM)

Q4 2022 Earnings Call· Thu, Mar 16, 2023

$9.58

-4.87%

Key Takeaways · AI generated
AI summary not yet generated for this transcript. Generation in progress for older transcripts; check back soon, or browse the full transcript below.

Same-Day

+7.14%

1 Week

+9.32%

1 Month

+15.53%

vs S&P

+10.52%

Transcript

Operator

Operator

Greetings, and welcome to the Fortuna Silver Mines Fourth Quarter and Full Year 2022 Financial and Operational Results Call. [Operator Instructions] I will now turn the conference over to your host, Mr. Carlos Baca, Director of Investor Relations. Please go ahead.

Carlos Baca

Analyst

Thank you, Ali. Good morning, ladies and gentlemen. I would like to welcome you to the Fortuna Silver Mines fourth quarter and full year 2022 financial and operational results call. Hosting the call today on behalf of Fortuna will be Jorge Alberto Ganoza, President and Chief Executive Officer; Luis Dario Ganoza, Chief Financial Officer; Cesar Velasco, Chief Operating Officer, Latin America; David Whittle, Chief Operating Officer, West Africa; and Paul Weedon, Senior Vice President, Exploration. Today's earnings call presentation will be available on our website, fortunasilver.com. As a reminder, statements made during this call are subject to the reader advisories included in yesterday's news release and in the earnings call presentation. Financial figures contained in the presentation and discussed in today's call are presented in U.S. dollars, unless otherwise stated. Before I turn over the call to Jorge, I would like to indicate that this earnings call contains forward-looking information that is based on the company's current expectations, estimates and beliefs. This forward-looking information is subject to a number of risks, uncertainties and other factors. Actual results could differ materially from a conclusion, forecast or projection in the forward-looking information. Certain material factors or assumptions were applied in drawing a conclusion or making a forecast or projection as reflected in the forward-looking information. Additional information about the material factors that could cause actual results to differ materially from the conclusion, forecast or projection in the forward-looking information and the material factors or assumptions that were applied in drawing a conclusion or making a forecast or projection as reflected in the forward-looking information is contained in the company's Annual Information Form and MD&A, which are publicly available on SEDAR. The company assumes no obligation to update such forward-looking information in the future, except as required by law. I would now like to turn the call over to Jorge Alberto Ganoza, President, Chief Executive Officer and Co-Founder of Fortuna.

Jorge Ganoza

Analyst

Thank you, Carlos, and greetings to all. Safety first, we closed the year with a strong trend of improvement on key safety performance indicators, which year-over-year continue coming down as a result of multiple initiatives implemented across the business. Our KPI for total recordable injury rate closed the year at 2.3, down from 3.2 in 2021 and below the industry average of 2.9. Lost time injury rate also showed a strong improvement ending the year at 0.39, down from 0.53 in 2021. We recorded 5 lost time injuries in the year, down from 6 in 2021. However, all this work was tainted by a fatal accident at our Lindero Mine in January 2022. Safety is a precondition for business, and we remain firmly committed to a zero harm work environment. On December '21, we made public or position statement on the adoption of the global industry standard for tailings management. Our commitment to generate shared value over the long term for our stakeholders involves adapting strategically our business practices and standards, enabling us to better cope with risks, opportunities and heightened expectations. We consider tailings management to be paramount to responsible mining and the adoption of GISTM allows us to refine our approach to safe tailings management in a way to ensure operational excellence. On March 14, we informed of positive news coming from Mexico with the court granting a permanent injunction to our San Jose Mine, effectively protecting the 12-year environmental impact authorization of the mine. Cesar, our Chief Operating Officer for Latam, will expand on this later in the presentation. Our business generated adjusted net income of $7.2 million or $0.02 per share in the fourth quarter, in line with analyst consensus; and for the full year, $42.4 million or $0.15 per share, slightly ahead of the analyst…

Paul Weedon

Analyst

Thank you, Jorge. Sunbird, the latest at Séguéla deposits and is shaping up as potentially the largest. The current focus at Sunbird is on the conversion drilling to upgrade and expand the 506,000 ounces of inferred by the end of Q2 2023. We've currently got two drill rigs turning on that program. As seen in the news release this past Monday, results to date are consistent with or better than what was previously modeled in the optimized shell. We've also extended mineralization of approximately another 100 meters further North and beyond the optimization shell with several high-grade intersections, such as the 5.6 meters of 12 grams gold from 28 meters downhole in hole SGRC1566. In addition, deep drilling to the further North to extend these high grade -- sorry, to the South to extend these high-grade shoots we resume in Q3, potentially setting up the foundations for a future underground development. In our non-Séguéla division, exploration will continue into Q3 with the recently discovered high-grade at Kestral, Badior and Barana prospects, which we highlighted in December 5 news release. And then further target generation will continue on Séguéla with more than 30 known drills remaining to be tested. Moving further inferred into Burkina Faso, exploration work around Yaramoko continues to generate new anomalies. Our underground drill test in the Western strike extensions of the Zone 55 mineralization has extensive mineralization approximately 100 meters further beyond the current resource envelope and drilling is continuing in those areas. Moving to Peru, currently Caylloma is due to test the depth extensions of the 4-kilometer long Animas Vein later in Q2, targeting down depth projections of ore shoots 1 and 3, some 200 to 400 meters below the previous drilling in the previous mine and current mine workings. Additionally, regional exploration work around Caylloma continues to highlight the prospectivity, including the emerging Antacollo area. And then finally, in Mexico, work at San Jose continues to test the depth extensions in the Northern strike extent as well as planned exploration work announced toward Taviche [work in Oeste]. Jorge, back to you.

Jorge Ganoza

Analyst

Thank you, Paul. We'll move on to update and from the Chief Operating Officer. We can start with LatAm. Cesar, please.

Cesar Velasco

Analyst

Thank you, Jorge. And as you have already mentioned, last Tuesday, Fortuna announced that the Mexican Federal Administrative Court granted a favorable permanent injunction to Minera Cuzcatlan, which allows the San Jose Mine to continue operating under the terms of the original 12-year environmental impact assessment permit which the court reconfirmed in November of 2022. This permanent injunction will remain in effect, allowing for continued operations at the San Jose Mine up until the court rules in response to the resolution issued in January 2023 by the SEMARNAT to revoke San Jose's EIA. Although uncertain, we expect that it could be in 1.5 to 2 years. Moving down to Peru despite social unrest and numerous road blockades throughout the country, operations at the Caylloma Mine have been unaffected and 2023 annual production guidance is the remaining. I will now discuss the original results of our three operating mines in Latin America. The fourth quarter of 2022 marked the fifth consecutive quarter of consolidated gold production of over 35,000 ounces. For the full year, Latin America achieved record gold production of 153,319 ounces, a 14% increase compared to 2021. Consolidated silver production was 6.9 million ounces, achieving the higher end of annual guidance. All three mines delivered production results in line with their mining plans and mineral reserves estimates. In Argentina, the Lindero Mine delivered another consistent year with gold production totaling 118,000 ounces. This represents a 14% increase from 2021 and is directly related to an improvement in the performance of the 3-stage crushing and stacking system. Throughout 2022, management implemented numerous high-impact optimization initiatives to better capture efficiencies, allowing the operation to offset some of the cost increases from inflationary pressures on key consumables. These initiatives included improving the efficiency of the SART plant, subsequently decreasing consumption of fresh…

Jorge Ganoza

Analyst

Thank you, Cesar. We can move on to David and West Africa.

David Whittle

Analyst

Thanks, Jorge. Operations in West Africa continued solid performance in the year 2022 with Yaramoko delivering gold production of over [106,000] ounces as a midpoint of annual guidance. Séguéla's construction is striking well with respect to our schedules and budgets with first gold ore projected for mid-2023. Ongoing worldwide inflationary and supply chain pressures did not impact budgetary expectations at Yaramoko nor the construction progress at Séguéla. Recent political disturbances in Burkina Faso have had no impact on Yaramoko's operations. Safety performance at the Yaramoko Mine was strong. Unfortunately, LTI incidents took place in the fourth quarter. The Yaramoko underground grade control and brownfields exploration program continued with encouraging outcome, extending our planned mining boundaries on the Western side of the [ore bit]. Construction progress at Séguéla continues to track on -- sorry, continued on track and on budget. As of the end of February, the project was 93% complete with approximately $160 million incurred on the initial $173 million capital budget. The water storage dam is complete and is currently storing sufficient water for commissioning and operating activities. And the processing plan, structural mechanical and piping and electrical and instrumentation installations are nearing completion, with energization and commissioning activity about to initiate. First ore to the crusher for commissioning is expected in early April, followed by first ore to the mill later in the month. In parallel with the excellent progress on the ground, operational readiness at scopes, are advancing well. The mining tactical, processing and maintenance teams are being recruited with all senior management positions currently filled. Mota-Engil, the mining contractor, continued with on-site mobilization and establishment activities, together with the recruitments of key positions and equipment operators. The first phase of grade control drilling has been completed with more than 12,000 meters drilled. Initial results are bearing to align closely with the current geological models. As of the end of February, cleaning of the Antenna pit has occurred and excavation of waste is taking place with over 60,000 cubic meters of waste stripped and being utilized for the construction of the ROM pad. Preparations are currently underway for the start of the blasting operations in order for the first ore to be available for the commissioning of [the same]. Back to you, Jorge.

Jorge Ganoza

Analyst

Thank you, David. The team does a good job keeping our website updated on the construction gallery for Séguéla. So I invite you to visit the website and the construction gathering. So Luis, do you want to give us a briefing on the financials?

Luis Ganoza

Analyst

Yes. Thank you. I will start addressing the impairments we have recorded in Q4. We recorded total impairment charges, as Jorge mentioned, of $188.8 million before tax and $164.5 million net of tax. At Yaramoko, we have recorded an impairment charge of $103.5 million before tax. The impairment is related to the write-off of exploration and evaluation assets of $60 million and lower expected cash flows as a result of higher costs and lower reserves from the elimination of [brownfield] recoveries from our reserve base. At Lindero, we have recorded an impairment charge of $70.2 million before tax. The impairment is related to lower expected cash flows as a result of higher costs to a large extent related to inflationary pressures seen throughout 2022 and the effect of higher discount rates. At San Jose, we have recorded an impairment charge of $9.1 million before tax. The impairment is related to car costs as well as capitalized exploration expenses over the past few years which can't fully replace depletion. Also contributing to the impairment is the fact that the partial replacement of the dilution we have seen has been at a lower head grade compared to the previous average head grade of the reserve. As a result of the impairment, for Q4 2022, we recorded a net loss of $160.4 million. After adjusting for the impairment and a write-down of ore stockpiles at the Lindero mine of $3.8 million, adjusted net income was $7.2 million compared to $29.1 million in Q4 2021. The reduction in adjusted net income was mainly due to lower sales volume, lower silver prices and higher costs year-over-year across our operations. The lower volumes were largely in line with our mine plan. EBITDA for the quarter was $55.8 million, a $33 million reduction over Q4 2021, as…

Jorge Ganoza

Analyst

Thank you, Luis. Carlos, to you.

Carlos Baca

Analyst

Thank you, Jorge. We would now like to open the call to any questions that you may have.

Operator

Operator

[Operator Instructions] We have a question from Adrian Day with Adrian Day Asset Management.

Adrian Day

Analyst

I just wanted to ask, you had mentioned when you were discussing impairments, you mentioned that San Jose below head grades. Can you kind of quantify that?

Jorge Ganoza

Analyst

Luis, do you want to expand on that?

Luis Ganoza

Analyst

Yes. I mean the extension of life of mine at San Jose, has mostly to do with Victoria Vein, which does carry a lower head grade with respect to average grade of the reserve. That is in our reserve statement. I'm not able to give you exact head grades out of the Victoria Vein out on the head right now, there isn’t, but I'm not sure if I -- Paul or Cesar, if you want to jump in there.

Adrian Day

Analyst

Could you characterize those as meaningful or marginal or…?

Jorge Ganoza

Analyst

Go ahead.

Luis Ganoza

Analyst

I was just going to say that we're not going to get an exact number on the head grade. But what I can say on my end is that the projected life of mine, the remaining life of mine at San Jose is still based on those lower head grades with respect to our historical production is still contributing significant margins and free cash flow, not at the same rate certainly as before. But I mean, for instance, in our current mine plan, you could -- based on our production guidance for the year, you can appreciate lower head grade, lower production with respect to 2022. And in 2022, lower with respect to 2021, but nonetheless, this -- in the current price environment, we're still projecting healthy free cash flow out of San Jose in the range of $25 million to $30 million. That, I think, additional color I could provide on what those lower head grades imply for San Jose moving forward at this stage.

Adrian Day

Analyst

Okay. Okay. I appreciate that. And one other question, if I may, also on the impairments. At Lindero, you mentioned the impairment was mostly due to higher costs. I mean, none of us knows what's going to happen to costs going forward. But assuming the costs stay where they are, does this affect -- will this affect either your production, your annual production or maybe even your ultimate production from the mine, in terms of volume?

Luis Ganoza

Analyst

No. I mean the guidance we have provided already for the year, for 2023 already incorporates our view as to inflation trends in the new year, right? So there is low new information here with respect to what's already been shared as part of our guidance for 2023, either on production or on costs.

Adrian Day

Analyst

Okay. Sorry, I didn't express myself clearly. Do the -- will the higher costs make any of the -- or uneconomic that you were expecting to be economic? I think our reserves -- I think we're going to update our reserve inventory as we publish every year in the coming weeks. But we do not expect any significant deviation to what you have been seeing in the reserve. If you look at our production for 2022, San Jose delivered 5.7 million, 5.8 million ounces of silver for the full year and 34,000 ounces of gold. If you look at our guidance for 2023, San Jose is delivering again between 34,000, 37,000 ounces of gold and 5.3 million to 5.8 million ounces of silver. If you look at the reserve average grade, the Victoria Vein comes later in the life of a mine, in the remaining life of mine. So the grade in the reserve, it's where we provided an average and in the later years, is we have the lower portion of grade that make that average, right? So you see a bit of a decrease in grade and a decrease in production. For 2023, we're still seeing similar figures in line with what we have in reserves. But certainly, from the impairment perspective, we've been investing heavily in exploration for a number of years at the tune of $9 million to $10 million a year. And that exploration investment has not been able to offset the depletion of the mine. We've been only marginally successful with the exploration to date and that has weighted on the impairment and also the cost inflation that we see at the asset level has also weighted on that, right? So it's a mixture of things there, Adrian.

Operator

Operator

We have had a question come in from Dave Kranzler. "What do you expect generally to be the annual sustaining CapEx at Séguéla once it is fully ramped up?"

Jorge Ganoza

Analyst

David, do you want to tackle that one?

David Whittle

Analyst

Yes, certainly for the budget that we've -- guidance we put forward for this year, we have always sustaining costs there in Séguéla between [10,080] and $1,080 per ounce. Obviously, as the first year of commissioning with 71,000 ounces, we're obviously expecting the profile to grow beyond there. And with the exploration work that Paul is doing, we would expect the mine plans to be quite dynamic over the next year as well and certainly provide us some growth expectations. So in terms of life of the mine at the moment, we would still be expecting to be below that $1,000 an ounce all in sustaining area.

Luis Ganoza

Analyst

Maybe just to complement on David's answer. In terms of an absolute dollar figure, CapEx at Séguéla for the life of mine, right, consistent with the numbers implied in AISC just provided by David should be in the $16 million to $20 million range.

Operator

Operator

[Operator Instructions] Okay. We have no further questions in queue. So I will hand it back to Mr. Carlos Baca.

Carlos Baca

Analyst

Thank you, Ali. If there are no further questions, I would like to thank everyone for listening to today's earnings call. Have a good day.

Operator

Operator

Thank you, ladies and gentlemen. This does conclude today's call. You may disconnect your lines at this time, and have a wonderful day. We thank you for your participation.