Dan Dickson
Analyst · H.C. Wainwright. Please go ahead
Thank you, Alison, and welcome, everyone. It's been a busy third quarter at Endeavour Silver. As gold reached new all-time highs, and with silver starting to fall, the company's cash flow and financial position should continue to benefit from these higher prices. From an operational standpoint, Q3 brought an unexpected challenge as the company operated at reduced capacity due to a trending failure of the primary ball mill at the Guana City mine. Temporary modifications were completed in August, allowing processing to continue at roughly 50% of capacity. The estimated timeline back to full capacity remains at 15 weeks, with the mine being in full operation next month. I would like to extend my thanks to our operations team for their dedicated efforts in mitigating the issue. Q3 silver equivalent production totaled 1.6 million ounces, or 875,000 ounces of silver and 9,300 ounces of gold, tracking well towards the updated 2024 production guidance of 7.3 million to 7.6 million silver equivalent ounces. Silver equivalent grades have been in line with expectations, with gold grades slightly higher and silver grades slightly lower. This is expected to be similar going forward, and we expect the production profile in the fourth quarter to be similar to Q3. At Terronera, substantial progress was made during the third quarter. Surface construction reached 77% at September 30th, with more than $258 million spent to date. The finish line is in sight as Terronera continues to remain on track for commissioning near the end of the year, and we are excited to have this transformative project added to our production profile in 2025. Moving to our financials, we reported top line revenue of $53 million, up 8% year-over-year, benefiting from the higher precious metal prices compared to Q3 2023. Cost of sales totals $41 million, a decrease of 12% compared to Q3 2023, driven by lower silver ounces sold in the quarter, as well as cost management measures undertaken at Guanacevi following the trunnion failure, which also includes the termination of third-party contract mining activities. Direct operating costs on a per-ton basis and per-ounce basis were elevated due to the reduced operating capacity at Guanacevi. Because of the reduced operating capacity, management withdrew cost guidance for 2024 in August. The company reported a net loss of $17 million for the three-month period ended September 30, 2024, compared to a $2.3 million loss in Q3 2023. Excluding certain non-cash and unusual items, and items that are subject to volatility which are unrelated to the company's operations, adjusted income was $1.6 million, compared to an adjusted loss of $8.3 million in Q3 2023. As of September 30, the company's cash position was $55 million, and working capital was $29 million. During the quarter, the company completed drawdowns of $25 million from the Senior Secure Debt Facility for Terronera, and subsequent to the quarter, the company completed its final drawdown of $35 million. As I mentioned earlier, the overall progress at Terronera reached 77%, with more than $258 million of the project's budget spent to date. Project commitments totaled $270 million, which is 99% of the $271 million capital budget, and remains on track for commissioning near the end of Q4 2024. During the third quarter, 1,050 meters of underground mine development was completed, for a cumulative total of 5,550 meters, and the team continued progressing portals 1, 2, and 4. With long-wall stokes being developed and an initial production plan for Q4. The underground explosive magazines were also completed, with the explosive use permit application submitted for approval and anticipated in the New Year. On the upper platform, surface mill and infrastructure construction is 90% complete, and continues to transition to operations. The Coarse ore stockpile reclaimed tunnel reached 100% completion, with pre-commissioning testing beginning in Q3, and the primary jaw crusher was commissioned with ROC in August, marking a major project milestone. The excavation of the tailing storage facility embankment key trench is 100% complete, with the secondary key at 40% complete. Structural steel columns and beams were erected for the concentration filter building and equipment mechanical structures, and remains on the critical path for commissioning in Q4. Through September 30th, procurement was 99% complete, and the project team continues to excite pending arrivals. And lastly, from a community relations standpoint, with local community support continue to be a major commitment. In Q3, the company supported a series of local initiatives and investments, such as the inauguration of an early childhood development center, scholarships for university students in Santiago, municipal road maintenance, workshops for business entrepreneurship for local residents, environmental education programs for primary schools, community tree donations, and summer community workshops for children and youth. For a fulsome construction update at Terronera, I encourage you to visit our website, where you'll find our quarterly photo gallery, showcasing the latest developments, progress, and information. With that, I'm happy to open up to questions. Operator, please proceed to our Q&A session.