Dan Dickson
Analyst · Alliance Global Partners. Please go ahead
Thank you, Allison, and welcome, everyone. It's been a productive second quarter at Endeavour Silver as gold reached new all-time highs and with silver starting to follow the company's cash flow and financial position should continue to benefit from these higher prices. At Terronera, there was significant advance of the upper platform surface infrastructure and the overall project progress reached 65% at June 30. Terronera is on track for commissioning in Q4 2024, and we're excited for it to contribute to our production profile next year and become a cornerstone asset. Q2's silver equivalent production totaled 2.2 million ounces or 1.3 million ounces of silver and 10,500 ounces of gold. We are in great position to meet the upper range of our 2024 production guidance. Silver equivalent grades have been in line with expectations, with gold grades slightly higher and silver grades slightly lower. This is expected to be similar going forward, and therefore, we expect a similar production profile for the second half of the year. We reported top line revenue of $58 million, up 17% year-over-year due to higher metal prices compared to Q2 2023. Cost of sales totaled $48 million, up 28% from Q2 2023 due to the strength in Mexican peso contributing to higher labor, power and consumable costs and continued inflationary effects from 2023 that flowed into 2024. At Guanacevi, purchased material from local miners increased to 18% of throughput and accounted for $5 million of our cost of sales. In Q2 2023, purchased material was $1.5 million. With higher purchased metal prices, the availability and costs of the purchased material have both increased. There are a number of benefits of purchasing the local material and management expects the purchase of materials remain elevated for the foreseeable future. The higher prices also means higher royalty expense, and we are generating mining profits increasing our special mining duties, which are impacting our cost metrics. Direct operating costs or mining, processing and site administrative costs are within management's expectations. Cash costs and all-in sustaining costs benefit from the higher gold credit than estimated at the beginning of the year, offsetting the higher royalties, special mining duty and increased purchased material. The company reported a net loss of $14 million for the three-month period ended June 30 2024 compared to a $1 million loss in Q2 2023. Excluding certain noncash and unusual items and items that are subject to volatility, which are unrelated to the company's operations, the adjusted loss was $1.0 million compared to the adjusted earnings of $1.6 million in Q2 2023. With production results and construction results previously released, today's substantial share price action was unexpected and still the magnitude is somewhat puzzling. With higher precious metals prices clearly, there's an expectation for better earnings. And I believe this is one data point over time, we will deliver on those expectations. As of June 30 2024, the company's cash position was $68 million and working capital was $65 million. The company raised $14.7 million through share issuances primarily to fund Terronera. And during the quarter, the company completed its first drawdown of the Terronera senior secured debt facility drawing $60 million. Subsequent to the reporting end, the company completed a second draw of $50 million and has an additional $45 million committed and available for future drawdowns, expected in the third or fourth quarter. As I mentioned earlier, the Terronera project reached 65% completion with more than $204 million in the project budget spent to date. Project commitments totaled $260 million, which is 96% of our $271 million capital budget, and remains on track for commission in Q4 2024, as we continue to advance on schedule. Over 1,250 meters of underground mine development were completed in Q2 for a cumulative total of 4.5 kilometers, and our mine crews continue working in portals one, two and four declines. Development has cut through the Terronera vein and we started to develop test stopes. On the upper platform surface and infrastructure construction is 88% complete, with concrete and structural steel erection being fully complete and mechanical piping and electrical installation, is well underway. The excavation of the tailings storage facility maintenance key tranche is about 95% complete, and the lower platform is nearly 50% complete. Concrete work on the lower platform is scheduled to start early Q3 and remains the critical path for commissioning in Q4. Through June 30 87 to 95 procurement packages are now complete and it's now really an exercise in execution and productivity, over the next six months. The company anticipates commissioning using temporary power with the LNG and power generation to be operational subsequent to commissioning. The temporary power has been planned and is expected to be available for Q4. Similarly there will be other minor structures under construction during commissioning. And lastly, from a community relations standpoint with the local community support continue to be a major commitment a plant operator training program was established a comprehensive training and support service plans is being prepared for groups, and individuals seeking to form businesses that can provide local business and services within the community. Again for a wholesome construction update at Terronera I would encourage you to visit our website, where you'll find our early photo gallery showcasing the latest development progress and information on Terronera. Before we move to the Q&A part of the call, I would also like to highlight that we published our 2023 Sustainability Report titled Transformation in Motion in May, that provides a deep dive into Endeavour's sustainability commitments performance and ongoing approach to responsible mining. You can view the full report and the company's strategy, on our website under the Sustainability tab. With that operator I'm happy to open this up to some questions. Let's please proceed to that session operator.