Douglas Reddy
Analyst · BMO
Thanks, Pete. So as Pete noted, in 2021, several of our open pit mines were back-end weighted for the gold production. We do see that at a few of the operations in 2022 as well. Looking first at the U.S.A. and Mesquite. In Q4, we produced 66,870 ounces. And for the year, 137,500 ounces. So majority of the ounces coming at the very end of the year. Overall production will be similar in 2022 for Mesquite. And I'll note that in 2021, we completed the stripping campaign for the Brownie pit, and that's the ore that is almost entirely being processed or placed on the leach pad in 2022. And similarly, for 2022, we're doing a $44 million stripping campaign to open up a new phase of the Vista East pit, the VE pit, and that will benefit us at the very end of 2022 and into 2023. We are also carrying on with a $5 million exploration program at Mesquite, which looks at resource to reserve conversion in Brownie, Vista East and Rainbow pits. And I do want to underscore that this mine is a consistent producer. It will be doing its 5 million ounce in 2022. So a good asset, very consistent. At Castle Mountain, our Q4 production was 8,357 ounces. We're looking at 25 -- it was 25,000 ounces for the year and it will be higher in 2022, and that will reflect modifications to our stacking and irrigation practices that have been implemented during 2021. And also, we'll be introducing crushing and agglomeration in Q1. That should increase our recoveries, avoid some of our percolation issues that we've seen with certain rock types where blending has been very important and be able to point the way forward for improving our leach times and recoveries. We are doing a leach pad expansion, which is well underway already. It's a $7 million price tag for that, but that's well underway. And we are doing the Phase 2 studies and permitting that will support the expansion to 200,000 ounces a year. The plan to submit the permit amendment is -- that will go in, in Q1. So moving on to Mexico. At Los Filos, in Q4, we produced 54,733 ounces and the total for 2021 was 144,000 ounces. It will be higher in 2022 at 160,000 to 180,000 ounces, and that will reflect a continuous mode of operations. We have ongoing development that was done in 2021 in the Los Filos open pit and Guadalupe open pit, which is our major contributor for the open pit ore going to the leach pads now. And also development from the Bermejal underground deposits where we have a small amount of contribution as we continue with the development of Bermejal focused on getting into the Zone 5 in the central and higher grade portion of Bermejal. Our work in 2022 includes $20 million of sustaining and $47 million of non-sustaining capital, principally through open pit stripping and underground development with $30 million of that being carried over from 2021 where we were rather delayed or interrupted in development work in the middle of the year. At the Mercedes mine, total contribution attributable to Equinox for 2021 is 31,800 ounces. And as noted, we have an agreement in place to sell the mine to Bear Creek for $100 million with a 2% NSR and just under 25 million shares in Bear Creek. That transaction is expected to close around the end of this quarter. In the meantime, we continue with the development into two additional deposits at Mercedes. And we will both take the cost, but also the benefit of that up until the point where we -- until the transaction closes. Moving on to Brazil. Aurizona mine, Q4 production was 41,258 ounces and the total production for the year was 135,000 ounces. We will see slightly lower production in 2022 and that reflects a small drop in the feed grade, the grade of the feed to the plant. We did set a new throughput record in Q4 with 922,000 ounces being processed -- sorry, 922,000 tonnes being processed. And we also set a record for mining in the quarter. In 2022, we are moving ahead with permitting on portal locations for the underground expansion. We've also had the results from drilling 21,000 meters of drilling come in. Part of that focused on the underground and also on other targets in the immediate area around the Piaba pit. That will benefit us as we move ahead with design work for the underground. We're also doing $8 million of spend on infrastructure, including a new pebble crusher, which helps us to maintain our feed to the plant as we move into a higher proportion of fresh rock. And we continue drilling within the mine area and nearby targets. We have $8 million slated for exploration on that. At Fazenda, in Q4, we produced 14,499 ounces for a total of 60,000 ounces in 2021. We should see that slightly higher in 2022, largely from some higher grades coming from both some underground areas and open pit production. This mine has been operating for essentially over 30 years, and recoveries are now around 89%. A big part of our work has been the underground and additional exploration on surface that's worked on reserve replacement, and we continue with that. On the plant, it set a new production throughput record of 351,000 tonnes processed. And in 2022, we will be doing an exploration program that not only works or explores immediately around Fazenda, but within the Fazenda to Santa Luz district, very exciting numerous targets in that Greenstone Belt, and we will ultimately look at developing or identifying and developing resources that could either go to Fazenda or Santa Luz depending on the metallurgy and proximity to process plants. At RDM, our Q4 production was 13,362 ounces and our total production for the year was 59,000 ounces. We anticipate that that will be higher in 2022 at 70,000 to 80,000 ounces in large part coming from a new geotechnical model that enables us to access higher grades and increase our overall production coming from the open pit. We did process more stockpile material in the fourth quarter given that we had heavy rainfall limiting some access to our open pits. And in this year, we will be doing an increase on the TSF capacity and also installing a thickener. Thickener gives us the ability to do some water conservation and it also reduces the volume of tailings going to the TSF. Water conservation because RDM is in a drought-stricken area. And typically, we are always working to maintain as much water as we can available for processing throughout the year. We do have ample water. We have a very full water storage dam. And separate to that, of course, as you've noted, we have lots of water in our TSF at the moment. So in response to new guidelines, we will be suspending the plant for the next two to three weeks, while we continue pumping and evaporating to reduce water levels in the TSF. During that time, we continue with mining and stockpiling of ore. And we anticipate that there will be a marginal impact to us overall as we restart and process the ores that we've been putting to one side during this period. I will note that there are no issues with the TSF. And all regular internal and external and independent inspections of the TSF have confirmed this. So moving on to Santa Luz. Commissioning is underway. Construction is on time and on budget. The total budget was $103 million for the construction CapEx. We are at 95% complete overall. The crushing area is close to completion. Commissioning is underway on the leach circuit SAG mill, ball mill and secondary grinding areas. First ore will be introduced this month and first gold is targeted for late in March. We'll move on to Greenstone where construction is underway. This project is being developed by Equinox as 60%, Orion as 40%. Total reserves at the project of 5.5 million ounces, and it does have significant additional exploration upside. This is a conventional open pit with leach CIP plan. The project has excellent infrastructure. It's on the TransCanada Highway and right next to the Town of Geraldton. We have great community and First Nation support for this project. And our initial capital is $1.23 billion. That includes $177 million in contingency, about 14% of the initial capital and also includes $125 million for a fleet in which we could lease to reduce the upfront cash spend. It does exclude preproduction revenue and 80% of our initial capital is Canadian dollar based. I will note that around 29% of the CapEx is now fixed by virtue of contracts that are in place and about 45% of the CapEx is committed so far. We have an overall construction period of two years and six months of commissioning. First gold pour is targeted for H1 of 2024. If you go over to Page 14, you can look at some of the construction progress. And I invite you to go to our website and you can see excellent photos for both Greenstone and Santa Luz and time lapse photography for Santa Luz so you can see how things are progressing at those sites. The engineering for Greenstone is 85% complete. And one of the reasons why we're able to be advancing with this project so well is -- I mean, it's kudos to the team. Their project readiness has been very good going from being on standby to bringing everything up to speed during 2021 very quickly. But the very experienced team, they know this project well. They've been with the project for many years and been able to have everything ready to roll. So Phase 1 road building and tree clearing is complete. Site access road and power lines are almost complete. The TSF work is ahead of schedule. And highway relocation work is actually ahead of schedule as well. Site civil works and concrete foundation work is underway. And plant earthworks are about 70% complete. So that's a big derisking thing and being able to get ahead on our earthworks. Temporary water treatment plant is already in operation, and we have a 600-person lodging facility that's in use. All principal and critical equipment have already been ordered. So very good progress at Greenstone and kudos to the team. I'm going to pass it back to Christian.