Douglas Reddy
Analyst · Dalton Baretto from Canaccord
Thanks, Pete. I just - I would like to say that there are 2 main themes for the operations on how - what's happened in the first half and how it affects in the second half of the year and going into 2022. The first one is waste stripping, where we've had large programs at Mesquite and RDM as well as waste stripping happening at Aurizona and Los Filos. So all of those investments in the waste stripping makes for a stronger second half of the year into next year. And the second aspect is a big effort on our - by our exploration team. 51,000 meters have been - has been drilled so far this year. And that's an investment in the long term at each one of our mines, both within the mines and near to the mine. So I look at those as how they affect the future for each one of our operations. If we look at Mesquite, we completed the Brownie stripping campaign, and we're looking at a stronger H2, as we mine oxide ore in that pit. The exploration has been focused on mine life extension, and that's the same thing we've done every year with Mesquite, where there's opportunity to be able to extend the life. It is a very giving overall system there. Q2 production, 24,185 ounces and an all-in sustaining cost of $1,520 per ounce. At Castle Mountain, we've continued to - our team has continued to work on optimizing the leach pad and plant. We have had issues with percolation on the leach pad, but we've managed to see the daily ounces being doubled and Q2 versus Q1 has been a doubling of the ounces being produced at Castle Mountain. Q2 production was 6,128 ounces at an all-in sustaining cost of $1,026 per ounce. Los Filos, the operations restarted well after the interruptions that we've had. H2 should be a strong second half of the year. We are in mining at the Guadalupe open pit. And as Pete mentioned, we have been doing the underground development in Bermejal underground. We should see ore coming through late in the year from Bermejal. Our Q2 production was 27,079 ounces and all-in sustaining cost of $2,016 per ounce. We also look forward to the completion of the updated CIL plant study, which will come in the second half of this year. Mercedes mine is a - it's a steady producer. We are campaign milling. So that means that we do have an opportunity to increase throughput and production, and there's good exploration upside. There's a program happening in several areas of Mercedes with good results coming in. The second quarter production attributable to Equinox was 10,708 ounces at an all-in sustaining cost of $1,226 an ounce. And H2 should be a consistent level of production from Mercedes for the company. So looking at Brazil, Aurizona had a heavy rainfall in the quarter, but the mining went really well. That was a contrast to a year prior. The team did a very good job of being able to - to be able to mine during the rainy season. And the processing plant was able to also utilize a portion of the stockpile that had been built up during the previous dry season. So we're looking at a strong second half of the year as we come fully into the dry season in that portion of Brazil. And production in the second quarter was 26,830 ounces at an all-in sustaining cost of $1,083 per ounce. We're very much excited for the delivery of the pre-feasibility study that's been looking at the underground potential at Aurizona. Large drill program was done in 2020, wrapped up at the start of 2021, and that study is coming to completion in the second half of this year. So we'll see how that impacts Aurizona and looks at the overall production that will come from that mine in the long run. For Fazenda, it's had steady underground production in the second quarter, albeit mining from a few lower grade areas. We had scheduled to open up a new open pit, which has now opened up. It just didn't happen as early as we expected. So that will be contributing in the second half of the year. Q2 production was 13,130 ounces at an all-in sustaining cost of $1,263 per ounce. And we're doing a consistent long-term exploration program, both within mine and around the mine, including the area between Fazenda and Santa Luz, which I think is going to be very exciting in the coming months for the company and results in numerous targets that we have in the 70-kilometer long Greenstone belt that's between Fazenda and Santa Luz. At RDM, we had - we now have a very full water dam, I would say. The first time I can look at that water dam and say that we have ample water for the rest of 2021 and all of 2022. And in spite of an exceptional rainy season, we mined 19% more ore than we did in Q1, and we're doing a major pit expansion through this year that provides access to the lower portion of the ore body. Q2 production was 14,089 ounces at an all-in sustaining cost of $1,073 per ounce. And we're looking at steady production through H2 and a strong 2022 based on the expansion work that's been happening in the pit. So looking at our growth and development projects, I'll say, it's really good to be with a company that has such a great pipeline of growth projects. Looking at Santa Luz, which is in construction now, as Christian mentioned, we are 50% complete on the construction, and our first gold pour is on track for Q1 of 2022. I'll elaborate a bit more on Santa Luz on the next slide, but let's move down to the other growth projects. Los Filos expansion, we've been developing additional open pit and underground mines. Guadalupe is now providing ore. So that one is already part of the expansion at Los Filos. Bermejal Underground development has resumed. We'll see ore coming from that late in the year. And we've been finalizing the study for the new 8,000-tonne per day CIL plant, which will process the higher grade ore at the site. That study will also see the potential to increase reserves and possibly extend the overall mine life. But critical for us is to work out a longer-term stability with the communities so that we can continue to work on expansions at Los Filos. For the Greenstone project, a very exciting project overall, 5.5 million ounces of reserves and a 14-year mine life. The early works are already underway, and we're looking at full-scale construction being targeted for Q4 of 2021. So keep an eye for that later on this year, as we work through all the preparatory work that's been happening on that project. And then on Castle Mountain expansion, the average gold production that was in the Phase 2 expansion is 218,000 ounces per year. We would expect to start the Phase 2 permitting in the second half of this year. So if we move on to the next page on Santa Luz. We are on budget, on schedule. The overall budget is $103 million for the initial CapEx. This project will bring in 110,000 ounces a year for the first 5 years at an all-in sustaining cost overall of $877 per ounce on average. And in the area, as I mentioned already, there's excellent exploration potential, both near surface and also at depth. We - in the photos on the left, you can see the events that we have on the leach tanks. They're going up well, the ball mill, which is in place. And there are lots of photos and videos on the website that I encourage you to have a look at as well as the time lapse that shows the progress of the site. And I want to congratulate the team. As of June, they achieved 1 year LTI free and 1.2 million ounce - 1.2 million hours LTI-free. So they had a recognition of that at site, and I just want to recognize that they've been going well, and they're going to keep up that focus on safe construction. So turning the page to Greenstone. It is one of the most attractive development assets in Canada. Previous underground mines produced over 4 million ounces in this area from the Greenstone Belt. It's got a good - excellent reserve of 5.5 million ounces and the opportunity to produce 358,000 ounces per year over the initial 14-year mine life. The project benefits from excellent infrastructure being right on the Trans-Canada Highway. Community and indigenous agreements are in place, and it's fully permitted for construction. The early works are well advanced. The team is in place. We have a very experienced team that's been with the project for, I would say, the better part of 10 years, advancing it and doing all the engineering and bringing the project up to this point. And tree clearing, the first phase is already complete. The temporary camp is already - the first phase of it is already complete. And a temporary water effluent treatment plant is complete. So very good focus by the team moving that project forward. And I'm going to hand it back to Christian.