Thomas F. Farrell
Analyst · ISI Group
Good morning. During the third quarter, Dominion's employees were twice challenged by Mother Nature, not just in the same quarter, but actually during the same week. We've done some research and cannot find an occasion during this century or the last, when a particular area was hit by both a significant earthquake and a major hurricane within a 7-day period. While we had time to prepare for hurricane Irene, there is no advance warning for an earthquake. However, in both cases, Dominion's employees responded to the emergency safely and professionally, and I'm proud of their efforts. On August 23, a 5.8 magnitude earthquake hit the eastern United States. The epicenter of the quake was just 11 miles from our North Anna nuclear power station. Sensors at this station immediately triggered an automatic shutdown of both units, just as they were designed to do. The quake also impacted the transformers that connect the plant to the grid. Diesel generators at the plant powered the necessary safety-related systems until off-site power was restored. Both units at North Anna are shut down and in safe condition. Inspections by engineering since the earthquake occurred have found no significant damage to any nuclear structures, equipment, pipes, valves, pumps, the Lake Anna dam or any safety-related equipment. We have notified the Nuclear Regulatory Commission that Unit 1 is ready for restart as soon as the Commission is satisfied that it can be done so safely. Additionally, the fall refueling outage for Unit 2 was advanced and completed during the shutdown and it is also ready for restart. Two teams of inspectors from the Nuclear Regulatory Commission have conducted their own walk-downs and posted seismic event inspections. At a public meeting in early October, the NRC said that Dominion responded appropriately after the earthquake shut down the reactors and that there was no significant damage, despite ground movement that exceeded the levels to which the plant was originally licensed. On October 21, the NRC held another public meeting, at which the results of the analysis of the event and the inspection of the plant were discussed. Significant safety margins built into the design of the plant prevented damage to safety equipment. After the meeting, a senior NRC official stated that North Anna will probably be allowed to restart within weeks. There is another public meeting scheduled for next Tuesday to present the results of the startup inspection completed by the NRC. Hurricane Irene was a massive storm that inflicted significant damage to our electric transmission and distribution systems during the weekend following the earthquake. Although we knew the storm was coming, it's path and intensity were unpredictable. While we had originally expected the worst of the storm to hit the southern and eastern areas of our service area, the bulk of the damage actually occurred in and around Central Virginia, where winds in excess of 40 miles per hour continued for more than 17 hours. The storm prompted the second-largest restoration effort in the company's 100-year history, exceeded only by hurricane Isabel in 2003. The incorporating lessons learned from that storm improved our responsiveness to Irene. About 1.2 million, or half of Virginia Power's customers, were affected by the storm. More than 7,000 line, patrol and support personnel, including 3,100 mutual aid and tree crews, for more than 20 different utilities and contractors repaired damage at 35,000 work locations and restored service to more than 92% of our customers within just 5 days. Compared to our restoration efforts for Hurricane Isabel, we had about 2/3 as many customers affected but restored service in about half the time. We applaud the outstanding work of our employees, and we thank our fellow utilities for their mutual aid personnel. I'll now turn to operating results for the quarter, beginning as always, with safety. Both Dominion Generation and Dominion Energy reported record for improving safety performance for the first 9 months of the year. At Dominion Virginia Power, hurricane restoration work led to an increase in both OSHA recordables and lost time restricted duty incidents. Our electric transmission business has gone 122 days without an OSHA recordable. Moving to operations, our generating plants performed well in the third quarter. Surry Units 1 and 2, Millstone 3 and Kewaunee achieved capacity factors greater than or equal to 98.7% during the quarter. Before the earthquake, North Anna Unit 1 had been online for 298 consecutive days, and Unit 2 for 289 consecutive days. Millstone Unit 3 had been online 409 days through the end of the third quarter. Millstone Unit 2 experienced a 14-day outage due to a leak in the service water piping. Economic growth continues to drive improving results for Virginia Power. Projected demand growth in Dominion's service territory is the highest in PJM. Unemployment in Virginia is about 6.5%, which is well below the national average of over 9%, and is actually below 5% in Northern Virginia. Weather-adjusted sales were up 1.4% through the third quarter and 1.7% if you exclude the impact of Hurricane Irene. We expect demand from data centers to grow from 295 megawatts at the end of 2010, to a total of 370 megawatts by the end of this year. Much of which has already been realized through the third quarter. Data center load is expected to grow approximately 545 megawatts by the end of next year, and to approximately 715 megawatts by the end of 2013. We continue to move forward on our long-term infrastructure growth plan. The Virginia City Hybrid Energy Center is about 93% complete, and is proceeding on-budget and on-time, with about 1,900 workers on-site during the quarter. Chemical cleaning of the boilers was completed last month, in preparation for a first-fire of the boilers by the end of this year. More than 50% of the systems at the plant have been turned over for testing and commissioning. Initial synchronization is scheduled for early 2012, and commercial operation is scheduled for the summer of next year. Our next new generating plant will be a gas-fired 3-on-1 combined cycle project in Warren County, Virginia, that will provide more than 1,300 megawatts when operational. The CPCN and Rider applications were filed with State Corporation Commission on May 2. And an EPC contract was executed on June 30. EPC contract is fixed price, which significantly reduces the risk of cost overruns to the company and its customers. Site work has commenced, and the final Notice to Proceed was issued for the combustion turbines and the steam turbine. Once regulatory approvals are received, construction should begin in the spring of next year, and the plant should be in commercial operation in late 2014. The estimated cost of the project is approximately $1.1 billion, excluding financing costs, or only about $821 per installed KW. Combined with its 6,600 heat rate, Warren County will provide substantial economic benefit for our customers. Even with the planned addition of the Warren County plant, Virginia Power will still need to construct additional generating capacity to overcome its existing shortfall and to meet the demands of its growing service territory. We have identified the need for up to 3 additional combined cycle plants similar in size to the Warren County project, 2 to meet demand growth, and another to replace coal-fired units at our Chesapeake and Yorktown power stations. They will likely have to be retired as a result of proposed new emissions regulations from the Environmental Protection Agency. Virginia Power has also announced plans to convert 3 small generating plants from burning coal to less-expensive waste wood as fuel. The air permit applications were filed at the end of May, and the CPCN and Rider applications were filed with the State Corporation Commission on June 27. An EPC contract, which is also fixed-price, was executed on June 30, and we have finalized our fuel aggregator contracts for each of the facilities. The estimated cost of the conversions is $165 million. And once the projects are approved by regulators, it should be completed in 2013. The upgrade of our transmission system is a key component of our infrastructure growth plan. The modernization of the Mt. Storm-to-Doubs line was approved by the State Corporation Commission last quarter. Work is underway on this project, and will be conducted during the spring and fall of the next 3 years, and is estimated to cost about $350 million. Our electric transmission project pipeline contains over 40 additional projects, totaling about $450 million per year, for at least each of the next 5 years. Recently, our electric transmission operations were ranked first in reliability among all of our peers. Our transmission investments are providing excellent service to our electric utility customers. The growth program at our natural gas infrastructure business continues to move forward as well. Construction of our $634 million Appalachian Gateway Project began this summer, and the project should be in service by September 2012. FERC approval for the Northeast expansion project, as well as the Ellisburg to Craigs project was received this quarter. Both projects are expected to be in service by November 2012. We should expect to see a focus by us on a variety of midstream investment opportunities available to -- in both the Marcellus and Utica shale formations. Last quarter, we announced the Natrium processing project. The Natrium site can access production in both the Marcellus and Utica shale regions, and is able to ship products via barge, rail, truck and pipe, offering significant value to producers. On July 1, we executed an EPC contract for the construction of facilities that can process 200 million cubic feet of natural gas per day, and fractionate 36,000 barrels of NGLs per day. Recently, we executed an agreement with the producer that now fully contracts Phase I of Natrium. This phase of the project is expected to cost about $500 million and should be in service by December 2012. We can also expand the facility to accommodate additional demand from producers. Since we announced Phase I, interest from producers in the second phase at the site has been strong. We are in detailed negotiations with multiple producers for volumes to support the possible construction of Phase II at Natrium, which could be in service by the fourth quarter of 2013. With the continued successful development of the Marcellus and Utica shale formations, interest in our potential Cove Point liquefaction project is growing as well. We are engaged in discussions with numerous potential customers in Europe and Asia, as well as producers in the Appalachian basin. We filed a request on September 1 with the Department of Energy for authorization to export LNG to countries with which the U.S. has entered into a Free Trade Agreement. The DOE approved that request on October 7, authorizing for export up to the equivalent of 365 billion cubic feet per year for a 25-year term. On October 3, we filed for approval to export LNG to non-Free Trade Agreement countries. This phase of the approval process requires market demand, supply and economic studies to show that the export of LNG is not inconsistent with the public interest. Our filing supports our belief that the project will have many positive economic benefits. Our application requests approval by June of next year, but it could take longer. Our regulatory calendar has been fairly active this year as well. As many of you know, the first biennial review on the Virginia's reregulation statute is taking place. Hearings were held last month, and the State Corporation Commission must issue an order by the end of November. The purpose of the review is to determine: One, whether the company's average earnings for 2009 and 2010 covered by base rates were within the authorized return on equity range of 11.4% to 12.4%; and two, what returned on equity will be used in the next biennial review and be incorporated into future project Rider filings. Hearings are scheduled to begin in December for State Corporation Commission approval of our Warren County project and in January, for the proposed biomass conversions. We are confident in the value of these projects bring to our customers and are hopeful for commission approval next year. So to conclude, third quarter operating earnings were at the midpoint of our guidance range. All 3 of our business units performed well and delivered results that met our expectations, despite the major earthquake and Hurricane Irene. We continue to move forward with our growth plans and expect to deliver 5% to 6% earnings per share growth beginning next year. We also plan to request board approval for an increase of at least 7% in the dividend for 2012. Thank you, and we are now ready for your questions.