Ron Largent
Analyst · CIBC. Please go ahead
Thank you, Chris; and good morning. I will provide some detail regarding our first half 2016 operating results for Continental Africa, Australia and the Americas region, and then discuss some priority work around the operating portfolio focusing in on the Tropicana, Siguiri and Colombia projects. Slide 14, this slide represents the quarterly all-in sustaining costs for the international operations for the past three plus years. I’d stated at the year-end 2015 results in February that our costs would be impacted by exchange rate and some levels of inflation. We actually saw this impact in our quarter two numbers with both the Australian and Brazilian currencies strengthening against the U.S. dollar. In addition to the foreign exchange and inflationary impact, we are lifting our investment in our Brownfields pipeline with aggressive drilling underway at a number of our operations and also execution of life of mine extensions that we have planned for this year and beyond. My take away from this graph is we’ve established a sustainable operating margin for our international portfolio. The next slide, slide 15. Regarding production, first half 2016 saw us deliver 1.26 million ounces, which is 9% lower than the first half of 2015. The difference is related to the completion or stop of the tailings treatment at Obuasi, a planned reduction in the ounce production at Geita and Tropicana mines, primarily due to a reduction in grade, which we flagged earlier this year, and the challenges in the Kibali sulphide processing circuit. As you’d expect, these lower volumes also impacted our all-in sustaining costs though this was somewhat offset by strong cost performances at Siguiri, Sunrise Dam and Cerro Vanguardia. The America region improved their all-in sustaining costs by 4% to $816 per ounce. We are expecting a strong second half performance from the Cuiabá mine in Brazil and the Tropicana operation in Australia. Slide 16, as we continue to develop the optionality of the international portfolio, it is important to recognize the ongoing work that we are undertaking to enhance our life of mine plan and asset values. In short, we have a slate of Brownfields projects with attractive capital and high returns that will continue to enhance the overall quality of our production base. In Brazil, the development of the higher grade ore bodies Inga and Palmeiras at the mine Serra Grande continues with ore deliveries to the mill scheduled in quarter four of this year. Additionally, the satellite ore bodies at Cuiabá are being defined. Ultimately, these ore bodies will offer mining sequence optionality and dropdown rate improvements. In Guinea at the Siguiri, we have approved the capital for construction with a combination plan, which will allow for the continuation of the current production profile by processing hard rock after the depletion of the free dig oxide material in 2018. I have slide later on where I will discuss this in more detail. In Mali, the Sadiola sulphide project is in the final stages of optimization with scheduled decision points before year-end. As we stated before, this project is an attractive one, a view shared by our partners, but it must go through our normal evaluation processes and must receive the proper undertakings from the Mali government around power supply and fiscal framework before we make our final investment commitment. In Tanzania, the Geita mine, underground mining has commenced ore production at the Star & Comet ore bodies that will be seen in quarter four production. This transition to underground has been extremely successful in quarter two. Further exploration work and underground designs are being completed in the main 9 Nyankanga and Geita Hill ore bodies. In Australia, the Sunrise Dam operation has transitioned completely to underground mining method. In 2016, ore production from the underground is scheduled to meet the 3 million tonne per year grade. The ongoing ramp up of the underground ore production will eventually equal mill capacity of 3.6 million tonnes per annum. As we progress the development to the higher grade Vogue, ore handling infrastructure will be installed to support this level of production. At Tropicana, continued success with the Brownfields drilling program, down dip and along-strike at the current ore bodies has allowed us to define a larger resource, and we plan to convert these reserves later in 2016. That was an overview of some of the ongoing value-adding work that is being actively completed in the international assets to drive longer life and improved asset value. I would like to now take us a little deeper into Tropicana, slide 17. As an example to illustrate the type of work that we are doing, I would like to highlight our effort currently underway. There is a set of parallel work that has been defined -- that is defining targets to grow the reserve, lower cost and extend life. I think it’s important to state that Tropicana mine has been built and operated in line with our investment case. The project was constructed on schedule and within the capital budget and most importantly, the payback schedule has been met despite the downward pressure on the gold price since commissioning more than three years ago. The ongoing work has included plant optimization and circuit upgrades that are targeting the 30% increase to the nameplate design. This improvement has been combined with the material growth to the ore body resource that we are increasingly confident of achieving, down dip and along-strike to the Havana South and Boston Shaker systems. The plant throughput improvements combined with the resource growth, has allowed us to reevaluate the mining sequence to ultimately reduce mining costs. We have secured a 600 tonne face shovel that is scheduled for delivery in quarter four 2016. This will drive a reduction in mining unit costs and improved productivities. All this work is aimed at making material movements at Tropicana life of mine from next year and beyond. Slide 18, as I just stated, the 600 tonne face shovel has been procured for the operation. This will allow us to alter mining schedule to manage waste stripping volume. As illustrated on this slide, our current plans which have evolved in the past year have us utilizing the mined out Tropicana pit for waste disposal, materially reducing the mining cost. In general, we have potentially reduced the vertical height and distance that waste material needed to be halted for deposition. This non-typical hard rock mining method is an example of the innovative thinking that’s been taking place to drive value. Slide 19, to back up my comment regarding the plant throughput optimization Tropicana, this slide shows the nameplate volume 5.8 million tonnes per year were met in 2014 and exceeded over the past four quarters. A series of low cost upgrades combined with the series of optimizations will increase the plant capacity to 30% above nameplate by the end of this year. These include an upgrade to the ore stockpile to decouple the client operations, additional capacity in the CIO circuit, conveyor upgrades and consuming the installed capacity of the high pressure grading circuit. Resetting the annual capacity of the plant drives optionality with the newly defined ore body resource. Slide 20, I’ve mentioned a newly defined resource. So, this slide is indicative of excellent drill result our exploration team continues to deliver. The intercepts are exciting and have effectively confirmed the potential of the two ore bodies that will take Tropicana to the next level at Boston Shaker and Havana South. They’re intersections of 10 to 20 meters in thickness and variable grades from 2 to 10 grams. Next slide on Siguiri, Siguiri has been a strong contributor to the AGA portfolio since 2004, delivering 33% internal return on investment. The free dig material quantities are limited. We have a reserve that will take the life of mine to at least 2023, if the plant is altered to allow for processing of hard rock material. It has good regional geology beyond that and this project allows us ample time to explore that capability. The design is complete, the project has been approved by our Board and the Convention de Base with the government has been signed and is on schedule to be formally ratified by the end of the year. This project’s estimated cost is $115 million, will extend the mine life at the current production rate, which is approximately 300,000 ounces per year through 2023 at competitive cost. This is a robust project in the jurisdiction we understand and has limited execution risk. Next slide on Kibali, Kibali had a tougher six-month in 2016 while it had to deal with multiple ore types and plant challenges. Looking at the medium term when Kibali is in full production, it will draw 80% of its ore from underground. And as you can see from this slide, both mining and development of the underground operation are making solid progress. At the metallurgical plant, modeling has confirmed that the capacity of the ultra-fine grind and associated pump sell should be increased and preoxidation tankage is installed to guarantee best performance on a 100% sulphide feed. The foundations for this work -- or in the plant are already installed as part of the original plant construction. There is also plan to install a hybrid crusher as a second stage of crushing for direct feed into the number 2 mill oxide circuit to ensure maximum flexibility to treat different ore types at the same time. In the short term, in addition to some of the plant improvements referred to earlier, the availability of 3 million ore from the [indiscernible] pit will ease the situation and should support a significant step up in grade and production at the end of quarter three and through quarter four. This pit is only 1 kilometer from the Kibali plant and is a relatively high grade deposit with much better metallurgical property, which means that this ore can be processed through the oxide circuit rather than through the sulphide flotation circuit. In addition, the operator, Randgold gold has tasked the exploration team with delivery 50,000 additional ounces of plus 3 gram by the end of the year. With the current pit already being fast-tracked, two smaller satellite pits are currently being evaluated as part of this exercise. Randgold has therefore maintained Kibali’s production guidance for this year on a 100% basis at 600,000 ounces per year. Slide 23, Colombia, Colombia is our medium and long-term optionality in our portfolio. We’ve committed to complete the prefeasibilities at Gramalote and Colosa project by the end of the year 2017 and Quebradona in 2018. This will allow for decisions in late 2017 and early 2018 as which direction AngloGold wants to take. It’s important to note that in 2016 Gramalote was permitted by the Colombian government and is a first major mine to be permitted in approximately 30 years. We are managing the temporary [ph] resource of 37 million to 38 ounces and we plan on making ultimate decisions as far as path forward in late 2017 early 2018. Thank you. And I’ll now hand over to Christine.