Stephen L. Schroeder - Senior Vice President and Chief Operating Officer
Analyst · Neal Dingmann
Thanks Danny. First I would like to give you an update on the progress on the number of fore well [ph] at our Green Canyon number 82 prospect which we refer to as the Healy prospect. We drilled to 3,920 feet and ran surplus casing and cement. We have temporarily pulled the rig off the well due to eddy currents. We plan on returning to the well in approximately 30 days assuming conditions will improve. Secondly I would like to up date you on our current drilling activity at South Tim 41 B-3 well or Cap Rock with -- from both oil and gas in several zones. Jeff Durrant will further update you on this well. With respect to production, in the second quarter production average 343 million cubic feet equivalent per day down slightly from 357 million cubic feet equivalent per day in the first quarter of this year. In fact the week ending July 31st, we had an average production rate of 309 million cubic feet equivalent per day. Production has declined because the natural decline in the producing wells and the unexpected loss of a few key completions. For instances during 989 Cyprus, the completion was lost after it tainted up in late June. This well was producing at a net rate of 6.5 million cubic feet equivalent per day. Due to the MMS anchoring requirements we have elected to differ the work until fourth quarter at which time we expect to have a rig on location. The Eugene Island 205 C-4 Sidetrack completion watered out late in March of this year which is earlier than was forecasted. The completion had been producing at a net rate of 1244 million cubic feet equivalent per day in late March which quickly declined to 2.1 million cubic feet equivalent per day in late May before finally watering out. We have since re-completed the well to a new reservoir which is producing at 8 million cubic feet equivalent per day. Four days ago on August 3, 2007, a third party pipeline in the main path area began experiencing operational difficulties and producers were required to shut in. This has reduced our current production by approximately 17 million cubic feet equivalent per day and this reflected reduction is not reflected in our current third quarter guidance. Now turning to guidance for the third quarter. We expect to produce between 1.8 and 2 million barrels of the oil and 16.6 and 17.9 billion cubic feet of gas for a total of between 27.5 billion and 29.7 billion cubic feet equivalent. Although this is a decline from second quarter, we anticipate volumes to be higher in the fourth quarter. We still feel comfortable with our annual production guidance. As we stated in our last operational updates, the Company anticipates full year 2007 production to be between 7.7 million and 8 million barrels of oil and 74.7 billion and 78.7 billion cubic feet of gas for a total of between a 121 billion and a 127 billion cubic feet equivalent which is a 25% increase over the Company's 2006 annual production. There are several key projects that will drive the expected production build-up in the third quarter and fourth quarter of this year. During the third quarter, we anticipate shifting to a new zone in the Mississippi Canyon 718 while our Pluto 2 well with an expected rate increased to peak at approximately 20 million cubic feet equivalent per day. We anticipate production build up at a net rate of 18 million cubic feet equivalent per day from our Bay Junop discovery in mid-September. We expect to obtain our costal use permit for the pipeline and production facility this week. The refurbishment of an existing structure is complete and we are outfitting the deck with the processing equipment currently. Beginning in early September we expect to have first production from both our South Timbalier 299 installation and from our East Cameron 338 facility following the completion of our hurricane remediation efforts for a combined net rate of 7 million cubic feet equivalent per day. At South Tim 299 we are completing the final tie-in at the third party processing platform and our commissioning the control systems. At East Cameron 338 all major facilities kits have been set, all major piping is complete and we are currently commissioning the instrumentation and electrical systems. In the early fourth quarter, we anticipate initial buildup from the two High Island 24L discoveries at a net rate of 19 million cubic feet equivalent per day. Two pipelines have been laid and one structure has been set. The main processing structure is scheduled to be loaded out at the end of the month. We have an active workover facility surveillance program underway. We are installing low pressure facilities Acromilian [ph] 115 allowing us to reestablish production from an existing completion at an anticipated net rate of 4 million cubic feet equivalent per day. In addition to the Eugene Island C-4 Sidetrack and Pluto 2 recompletes I mentioned earlier we are evaluating several more recomplete and workover opportunities. Projects that have come online includes the West Cameron 181, C-2 Sidetrack and Galveston 303 number 7 tie-in are loose prospects in Mobile 867 and the South Timbalier 314 pipeline cleanup. During the second half of the year we also expect buildup from our active and planned exploration program. This buildup is currently not in our guidance. However we do anticipate a contribution this year from the exploration well that is currently being drilled at South Timbalier 41 as well as from our planned main-pass and ship shell projects. These wells are from existing platforms and should contribute production this year. Moving on to lease operating expense, in the last conference call I discussed our lease operating expense forecasting method. Taking a conservative approach we use the first quarter run rate on base LOE and held them flat for the year. I am pleased to note that the base LOE for the second quarter was $45.3 million, $4.7 million under the low end of guidance and hurricane remediation costs were $5.9 million slightly below the low end guidance of $6 million. This is a reduction in LOE and hurricane repairs of $9.3 million and $1.2 million respectively from the first quarter of 2007. Unlike the first quarter we had no significant well failures and workover expense was dramatically less. In fact 75% of the reduction in LOE is due to lower workover expenditures. Although LOE was lower in the second quarter, we are not revising full-year guidance at this time. Workover facility expenses are the greatest variables in total LOE because of the unpredictability of the well failures and unidentified facility problems. Now I would like to turn the call over to Jeff Durrant to update you on our drilling program.
Jeffrey M. Durrant - Senior Vice President of Exploration/Geoscience: Thanks Steve and good morning to everyone. Although we started on an exploration well in June, WNT [ph] did not complete the drilling of any new exploratory wells in the second quarter. However, we did successfully complete the 825 Sidetrack development well in Vermilion 331 field. Year-to-date we have successfully drilled two exploration wells plus we have deepened the Healy #3 project. And additionally both of our development wells drilled through the end of the quarter were also successful, so for an overall 100% successful 2007 drilling program. So, where are we now. Well as Steve just mentioned, we are currently drilling the 40% W&T working interest South Timbalier 41 B-3 Sidetrack, the Cap Rock prospect which is operated by EPO. In the original hole we found 70 feet of oil and gas and fire sand [ph]. Following information to evaluation we have mixed the Sidetrack well up-structure to a more optimal reservoir position. Current plans are the set casing and continue to explore for deeper objectives. The proposed final total measured depth for the well is expected to be about 19,000 feet or about 17,000 feet of true vertical depth. In our deep water program, our Healy #4 exploration well began drilling in July but our progress was cut-short by eddy currents and we decided to move the drilling rig off location. Before leaving however we were able to drill down to 3,920 feet and set 22 inch casing which is just above the first of the well's exploratory objectives. You might recall that this 14,500 foot well is designed to test for independent exploration targets. These wells are just the beginning of an expected increase or exploration drilling activity in the third and fourth quarters of this year. As we have discussed in various forms it takes about 1 to 2 years of evaluation of an acquisition before drilling activity significantly increases. Well it's now been about a year since we closed on the Kerr-McGee properties and I am happy to say that our exploration are capitalizing on our regional 3D seismic databases that cover both of these properties as well as the heritage W&T properties. Their efforts are showing promising results including two upcoming drilling programs in the Ship Shoal and the Main Pass areas. As Tracy mentioned in the opening... the Board has approved a $100 million increase in capital expenditures and here are some details of where we expect to be spending some of that digital capital in the remainder of 2007. We plan to begin drilling a fixed well infield [ph] exploration and development drilling program in the Ship Shoal 300 field in September. This was one of the properties that we got from Kerr-McGee. This low to moderate risk program will be drilled from existing platforms and infrastructure allowing us to quickly bring our successful wells online. The initial three wells will be drilled from Ship Shoal 300-A platform and will include two shallow gas wells... two shallow horizontal gas wells actually and an oil prospect. Additional drilling is anticipated in the Ship Shoal 300 field area later in the year and possibly on into early 2008. The Main Pass area, we expect to begin the drilling of a four to six well programs in September which will likely carry on in Q2 of early 2008. These wells are targeting objectives even with work [ph] between oil and natural gas. Also these wells will also be drilled from existing infrastructure. So that the combined, the Ship Shoal and Main Pass drilling programs could allow us to drill and complete up to six additional wells from existing structure by yearend 2007. Net unrisk production build up of 13 million cubic feet of gas per day and 2000 barrels of oil per day is possible. Also in the third quarter we are ramping up our open water exploration drilling program. This program includes a James volume [ph] test in the [indiscernible] and the old Main Pass area. Two deep water wells including the continuation of Healy #4 in Green Canyon #82 and the Blackbird prospect in Green Canyon #177. A final deep shelf well is planned in High Island area. The unrisk net exploration potential for all of the total remaining 2007 drilling programs is about 280 BCFE. The remainder of the year we anticipate drilling a total of 10 to 13 additional wells with two being in the deep water, two on the deep shelf and the remaining six to nine on the conventional shelf. Think as you can see that we expect the drilling activity to pick up significantly in the third and fourth quarters from what it had been in the first half of the year. While next year's drilling plan is still coming together in the planning and budget stage, I think it's fair to say that we see this ramp up in our drilling activity to continue into at least the first half of 2008. The paddle, I will turn it back to you Tracy.