Steve Hatten
Analyst · Roth Capital Partners. Please go ahead
Thank you, Jeff. Rich if you could take us to slide five, Lost Creek development status. I'm going to first talk about, as we generally do out there, we talk about where the fluid comes from, where the fluid goes to and what it cost us. So we'll talk about, what we're doing out in the field to get production going. We'll talk about the drilling status. Right now, we've already installed all of the wells that we had originally planned in our first mine unit. This is one of those forward-looking statement, Jeff, had referred before when I say, originally planned that's exactly what we mean, Our geologists in June came out with the revised tech report where they increased our net resource in the first mine unit by 1.3 million pounds. The original planned well not incorporate those 1.3 million pounds and so in the future we will be planning for a drilling and an installation program that incorporates the production of those 1.3 million pounds of resource and thereby utilizing the existing infrastructure; fences, power, pipelines where possible and lowering the per pound cost based on that. So we have installed 100% of those original planned well, which is 13 header houses worth. We are also starting on our production well installation in our second mine unit. Those who work with me know that I routinely say that running a operation in ISR is driving a battleship you have to steer several months in ahead and this is the beginning of the steering process for mine unit too. We'll start installing those wells this year in preparation for production next year. Then finally with our drilling program, Jim Bonner will later about where we're going with the exploration end, but we are completing 150 hole program and we expect to do that sometime in mid-August. The second phase of what goes on outside the plant is the mine unit construction or the surface construction. The wells are installed, but we have to pipe all those in and that involve pipelines, powerlines, header houses, instrumentation management of that flow. So right now we have header houses 1 through 10 are complete on construction. We are nearing the end of construction on header house 11. The pipeline in the road to header house 11 are complete and the surface and downhole construction is underway and we should be again complete in another couple months. That doesn't preclude us from the other work that goes on out there. Our guys do a great job. They are constantly working on multiple fronts. So they have been working on the prefabrication of header house 12 and they will keep working towards 13 and then prepping for mine unit 2 construction. And also we will be doing some surface construction in the form of infrastructure in the mine unit 2 area starting in Q4. Rich, if you could please take us to slide six, Lost Creek production results. I am very happy to say that on the day of our two year anniversary, we are shipping our 33rd truckload of uranium out of our facility today, we're very proud of our staff. We're very proud of all the folks in the plant, in the wellfield, in the regulatory group, in the operations group that make all that happen. So with shipping that 33rd lot, it has given us the production numbers that we see below and I won't read those for you, but there is a few things I would like to point out, is that quarter-over-quarter we continue to expand the number of pounds, so you see continued growth quarter-over-quarter, for the last four quarters. And that comes in all forms that we are concerned with, the captured pounds, which is what comes in on the flow stream, the drums pounds and the ship pounds. As a matter of fact our folks at currently with the use of only one of our drying systems are drying at a million pound rate, routinely. Jeff referred to steady-state and this is what we're talking about with steady state. And with steady-state comes the reduction of unit costs. So again we talk about slow and steady and steady state. We have continued to bring on header house at a routine rate. We are on our 10th header house operating 10th of 13 in the first mine unit with many more to come. And again, there the other thing that you will see in steady-state that comes with steady state operations and ISR, is you will see a lowering of grade. But you will see that right now year-to-date we're 107 milligrams per liter apart from million used 308 and that is lower than it was the year ago. However, as you continue operations in any area, you hit peaks and then you start to come down from those areas and we are inclusive of that original below. We have header houses one, two, three, all those of grades are still running very reasonably, but we have an average grade of 107 there for the year. We are still making our production targets and we're doing quite well with that. A major milestone we hit that I'd like to point out before I move on is the 1 million pound. We were able to capture dry drum and ship that and that's an amazing feat and it's a big milestone for any operation. Also just touch briefly, as we talked about steady-state. We have all the systems in the plant are functional. We are not running our reverse osmosis system right now. It's not necessary for our operations to maintain also. Waste water is the tail that wags, the dog in this industry and three of our disposal wells are available and are utilized as necessary. Both of our storage ponds that are associated with the waste water system are at an all-time low and they are less than 30% of total capacity and are available in case we have any upset conditions within the waste water system. Rich, could you go ahead and take us to slide seven please, Lost Creek operational results. Finally, and we'll kind of segue into the cash end of things, which is what also wags this dog. But you will see that we have showed continued increases over time and are captured our ground and thus a nice reduction in the cost. You will see our cash cost in 2013 were $22 a pound, essentially $20 a pound in 2014 and we're running, less in Q1 we're $18.86 and in Q2 we're at $16.15 cash cost, that's an excellent number for us. And that turns into better revenues. As you can see, despite the lagging spot market and the price of uranium, we have continued to show increases in revenues in cost savings and therefore increases in what's coming in. So for last year we are showing $19.73 was the average cash cost and we're very proud of all those numbers. Again it speaks to the consistency of the operation, the uniformity in the staff and the excellent job that they're doing on a daily basis. And with that, Jeff, I'll turn it back over to you.