John Suter
Analyst · FM Capital. Your line is open
Thanks Mike. If you’ll turn with me to slide six, you’ll see we have several operational highlights to touch on. I’ll cover them briefly, then go in more detail shortly. First in North Park, we’re making good progress on this year's objectives. Subsequent to the quarter, we have some exciting new well results from two different spacing tests on the east and west sides of our core area. Wells from both test targeted multiple benches and initial production results exceed our expectations. Current field production has ramped to over 6000 barrels of oil per day, which is over twice the average first half 2018 oil rate. We released our drilling rig in April as planned to evaluate results from the first of six western spacing test wells scheduled this year. We plan to deploy a rig in late Q3 to further advance tests that will optimize spacing patterns for future field expansion. In addition, we’ll further delineate the less developed southern area of this asset. Finally, we’ll initiate the midstream partner selection process. Our chosen partner will execute planned gas and oil takeaway projects. I’ll provide more color on these initiatives in coming slides. In Mid-Con, our NorthWest STACK asset continues to utilize one drilling rig under the drilling participation agreement. So far, we drilled eight wells this year under this arrangement. We continue to focus on delineating this asset while improving our drilling and completion practices for future expanded development. In the Miss [ph] we’re using one rig to drill the first of four higher return projects. Now on slide seven, let's zoom in on North Park specifically. Well density and delineation efforts make up more than half of our spend from drilling and completion activities during the year. Non VNC [ph] is made up primarily of Central facilities, pipeline and other infrastructure pre-spend for our 2019 drilling program. Moving to slide eight, you'll see the colored lines on the map, representing wells in the field that had at least 800 pounds per foot sand density in their completion, which defines our type curve set. These impressive results are widely distributed between B, C and D bench test and exists across a wide aerial portion of the core area. You'll note that our Gregory pad contains the six wells currently producing from our eastern spacing test. Also for reference, the Peters 16-12H13, the first well of our western test is located on the Grizzly Annex pad. Let's go to slide nine to look at the early results of the first spacing pilot. Our goal was to test 1320 foot spacing between wells in the same bench. We initially intended to test all four benches individually, but after further review of core and micro seismic work, we believe, we can recover Niobrara reserves from all four benches with three layers of drilling. This is highly cost effective plan that accomplishes reserve recovery in the most capital efficient manner. It's important to note that we only have proved reserves and up to eight wells per section in the core area primarily in the D&C intervals. We now have strong B bench test which could be a large upside to our pud [ph] category bookings to date. The table on the bottom right shows the first six IPs from various benches within this test, averaging 1305 barrels of oil per day growth, two of which are producing over 1500 barrels of oil per day. Three of the wells exhibited approximately 40% higher initial flowing pressures than historical wells. The graph on the top right shows the impact of the first 20 days, where 3 out of 6 wells have produced or nearly doubled the type [ph] curve rate. The last two wells of this initial eastern pilot will begin flow testing in the next few weeks. Now turning to slide 10. It's pretty clear how the uplift from these recent successful wells benefit our program. Our current total field oil rate is averaging above the 6000 barrel oil per day growth and in the first half of the year longer period of SIMOPS have been planned and delayed frac crude [ph] as Bill mentioned resulted in wells turning online a little behind schedule. With these results that are exceeding type curve performance, additional curtailments may be required until our midstream processing equipment is operational by year-end. In the interim, we will drill from different pads to utilize existing capacity and processing availability there. Despite these potential curtailments, we believe we will achieve our midpoint of guidance on oil. Let's move to slide 11, to review our objectives for the remaining 2018 North Park capital program. As I mentioned earlier, our rig returns in Q3 to drill the next five wells of the western spacing test to test 660 foot spacing in the same – well to well in the same bench. Similar to the Eastern pilot there'll be three layers of development, but we think there's 660 foot spacing well we'll test the next opportunity for eight wells per layer. The first well of this test produce an IP above type curve giving us confidence to move forward. In addition to the western spacing test the remaining capital will be spent drilling two new step-out wells at the far southern end of our core area. As Bill mentioned last quarter wells from our second half of 2018 drilling program should be online in early Q1, 2019. On slide 12, you'll see overall performance of our 22 wells drilled to-date that meet our completion requirements overlaid on the type curve. The economics table to the right outlines our criteria performance and SRL and XRL drilling inventory. Most of the plan development will utilize XRL designs which deliver over 100% rate of return and 6.9 million PV-10 at current strip pricing. Let's move to the midstream discussion on slide 13. Currently we are trucking oil with attractive differentials. We're combusting gas under flaring waivers as our pipeline plans move forward. Two projects underway will progress our oil and gas processing capability. First the installation of the permitted mechanical refrigeration unit will strip liquids out of a portion of our gas stream. Second our gas to liquids plant will convert a portion of our lean gas completely to diesel and gasoline further eliminating omissions from that stream. Both plants could be modularly installed at high-volume pad sites until pipelines are built. On the pipeline side we are awaiting a determination on plan submitted to the BLM in Q4 2017 to construct the first 36 miles of pipeline. The line will allow us to build an oil trucking facility north of Walden Colorado and a nearby plant to process gas away from the field. After testing multiple productive Niobrara layers establishing significant proven reserves and achieving production rates at meaningful levels, we're now prepared to initiate the process to find a midstream partner. The partner with carryout previously engineered plans to lay lines to Rawlins and IED corridor. Numerous oil and gas lines in that area currently transport product to up regional markets and refineries. Moving to the NorthWest STACK slides beginning on 14, we now continue to leverage the Drilling Participation Agreement to fund development. As you recall, our objective and participating in this agreement is to develop and to delineate our NorthWest STACK asset with minimal capital outlay. In Q2 we spent only $1 million in drilling and completion costs. Of the four wells we drilled two extended into Southeast Woodward County to delineate away from our Southwest Major County core area and to test additional outside leasehold. We plan to drill 16 wells in 2018 with a capital budget of $18 million to $20 million including $6 million to $8 million in total drilling and completion costs. Of the six wells that went to sales in the quarter, five produced at least 30 days for an average IP of 584 Boe per day consisting of 69% oil, total Q2 net production was 2.7 MBoe per day, 43% oil. Our net production is the result of our lower interest on wells producing under the drilling participation agreement. As evidenced by the chart on the lower right-hand corner of the slide, our gross production has increased by over 300% since Q1 of 2017. Drilling improvements over time are seen on slide 15 since initiating drilling in the NorthWest STACK cycle times have been reduced to 18 days in the second quarter, a 71% improvement. Over the same time period, we've cut the cost per foot by 51% and improve the footage per day 170%. Given our successful well results and production growth in the play, we plan to apply our learnings to higher interest areas in the future. The Sunkey well located in Major County Oklahoma is interesting case study highlighting the success of some key advancement we've made in the NorthWest STACK play. Look at slide 16 to examine the result. A major step change for us has been the progression of our geologic interpretation supported by a basin wide depositional model using over 3000 vertical logs and results from our core taken in 2017. These learnings have lead towards improved well selection as well as lateral placement within the Merrimack, targeting more brittle intervals that increases our efficiency of our stimulation. The Sunkey also tested enhanced completion design with higher profit density. The increase of total productivity is seen on the graph on the bottom right of the slide is a direct result of these developments. Slide 17 shows you SandRidge's Merrimack wells relative to other non-wells in the NorthWest STACK; industry drilling is currently fluctuating between 16 to 20 active rigs in the field. As indicated on the map, SandRidge and other industry wells across the play show encouraging results near our core acreage in Southwest Major County and near our plan delineation areas. Moving the slide 18 in the second half of the year we plan to continue our step out efforts in Central Major, NorthWest Dewey and Southeast Woodward Counties. All plan drilling locations exist within areas of established production on the previous slide. Moving forward the slide 19, the NorthWest STACK type curve is defined by economic parameters in the table on the top right. SRL wells generate a 35% rate of return with a 1.9 million NPV-10 at current strip pricing. SandRidge and offset operators well performance compared to our type curve consistently outperform on gas and meet expectations on oil, thereby causing a pretty solid beat on a BOE basis. As mentioned earlier, we've spud the first of four planned Mississippian wells subsequent to the quarter. On slide 20 you'll see the four-well composite program economics exhibit a 55% rate of return with an NPV-10 of $2 million for the program at current strip pricing. We expect the wells to start coming online in late Q3. I'll turn over to Bill now for some closing remarks.