Mark Isto
Analyst · CIBC. Your line is open. Please go ahead
Thanks, Bill. Turning to slide 5, I’ll cover portfolio performance over the quarter. Volume for the quarter was 76,000 gold equivalent ounces, or GEOs. This volume was in line with our expectations. And while there was a decrease year-on-year, keep in mind that the GEO volume in 2021 September quarter was a record for the Company, and our 2022 guidance reflected our expectation of reduced production from certain mines. Our royalty segment contributed $33 million in revenue, a decrease of 44% over the prior year quarter with lower contributions from Cortez, Peñasquito, Robinson, South Laverton and Dolores. Our stream segment revenue was $99 million, about 15% lower than the prior year quarter. Lower contributions from Mount Milligan, Pueblo Viejo and Rainy River were partially offset by new revenue from Khoemacau. I’ll now turn to slide 6 with a few specific comments on operations. We visited Khoemacau in late September and saw a well-managed and equipped operation. Production ramp-up is continuing, and the mining rate reached an average of 8,000 tons per day in September, up from the 7,300 tons per day in June. Production has reached the targeted mining rate of 10,000 tons per day for short periods during this ramp-up period, but the mining rate has yet to be consistently sustained at this level. KCM expects to reach the full run rate of 10,000 tons per day on a sustained basis towards the end of the fourth quarter or the first quarter of 2023. This is slightly later than what we said in our last conference call, mainly due to the availability of key mining equipment. The equipment issues are well understood, and the mitigation efforts are advancing well. At Mount Milligan, as Bill mentioned, Centerra issued the updated life of mine plan in early October. Compared to the 2020 plan, the life of mine has extended over four years to 2033, with increases of payable gold of 800,000 ounces and payable copper of 191 million pounds, all of which are positives for Royal Gold. The technical report is expected to be released in mid-November. Centerra also reported that resource expansion drilling is underway to the west and below the current pit boundary, while exploration drilling is underway east of the current ultimate pit boundary. According to Centerra, the results so far support the potential for future resource growth, all of which fall within the extreme area of interest. At Pueblo Viejo, silver deliveries were approximately 319,000 ounces in the quarter, and an additional 47,000 ounces of silver were deferred, resulting in a total of 530,000 deferred ounces. We expect that silver recoveries could remain highly variable until the plant expansion is completed and bottlenecks associated with the silver circuit and silver recovery can be fully addressed. Barrick expects plant expansion commissioning in the first quarter of 2023, and we don’t expect material deliveries of deferred silver this year. We continue to see this as a cash flow timing issue, and we don’t expect it to have any lasting impact on silver revenue. We also visited Wassa during the quarter and saw an operation focused on increasing gold production. Chifeng indicated that they expect 2022 production to come in at or above the high end of the previously provided guidance range of 155,000 to 170,000 ounces. At Andacollo, a significant rainfall event in July caused operations to shut down for five days. We expect the impact of the shutdown will affect stream deliveries in the first quarter of 2023. More generally, at Andacollo, gold production has trended lower since the beginning of 2021 due to lower ore grades in the mine plan. Teck has advised that expects that the period of lower grades to last through 2023, after which there will be a transition to higher grade ores as the next phase of mining is developed over the following years. Finally, we also saw a handful of positive developments at some of our smaller portfolio assets over the quarter, which were detailed in yesterday’s press release. For example, New Gold announced the start of underground production at Rainy River. Red 5 continues to ramp up production at King of the Hills. Bellevue Gold reached the first development ore. Hochschild reported construction is already 16% complete at Mara Rosa. And Sabina made formal decision to start construction at Back River in early 2023. We are pleased with the organic growth from the quality assets within our portfolio. I’ll now turn the call over to Paul for a review of our financial results.