Thanks Tony. Turning to Slide 6. I will highlight both the recent performance as well as near term growth prospects in some of our key properties. At Penasquito, Goldcorp reports that it is undergoing significant stripping that the Penasco pit while initiating stripping at Chile Colorado. Goldcorp is guiding to calendar 2017 production of 410,000 ounces of gold compared to production of 465,000 ounces of gold produced in calendar 2016. Goldcorp recently completed a review and optimization of their life of mine production plan resulting in lower production in 2017, due to high grade and Phase 5D being exhausted at the end of 2016 and exposure to high grade ore in Penasco Phase 6 not being reached until 2018. Goldcorp expects the new Pyrite Leach project to contribute gold production beginning in the first quarter of 2019. The project will recover gold now reporting tailings and expect an incremental 100,000 ounces to 140,000 ounces of gold production and 46 million ounces of incremental silver production. On Slide 6, we’ve included a picture of the prepared project site from Goldcorp's recent Investor Day presentation, Royal Gold has a 2% royalty on gold, silver, lead and zinc at Prestea. At Pueblo Viejo, Barrick chalked up its best ever year for gold production, reporting 700,000 ounces attributable and we are waiting their estimate for calendar 2017 production. Gold recovery performance is attributed to lower levels of total organic carbon in the ore, while improved availability of system components in the lime boil circuit contributed to higher silver recoveries and production. We remain impressed with the sizes of this deposit with about 20 years of current reserves and we understand that Barrick is evaluating an opportunity to expand its tailings facility which could potentially convert in additional 7.7 million ounces of gold and 44 million ounces of silver from resources to reserves. At Mount Milligan, Centerra is forecasting calendar 2017 gold production of 260,000 to 290,000 ounces, a substantial increase over the 204,500 ounces of gold production in calendar 2016. Centerra reports a commissioning of the secondary crusher is underway and they are optimizing the mine and mill to gradually increase gold and copper recoveries. An increase in calendar 2017 production versus 2016 is attributed to achieving higher mill throughput. Centerra expects to have the secondary crusher fully operational and supporting throughput of 62,500 tons per day. We remain focused on gold and copper recovery, Centerra has laid out a series of recovery improvement options which are being systematically reviewed and include additional rougher flotation capacity, additional regrind capacity and a development of the geometallurgical model. Finally, at Wassa and Prestea Golden Star is forecasting calendar 2017 production of 255,000 to 280,000 ounces of gold, well above their calendar 2016 actuals of 194,000 ounces. Commercial production at Wassa underground was declared a few weeks ago, Wassa underground will contribute to the 2017 production growth along with the Prestea underground deposit where commercial production is expected later this year. Beyond 2017's impressive growth forecasts we continue to believe that there is potential for additional additions to reserves from both Wassa and Prestea underground deposits. And are pleased that they plan to dedicate some of their recent offering proceeds to additional exploration. Turning to Slide 7, you'll see an aerial view of New Gold's Rainy River project. New Gold recent announced that first production will be delayed three months to September 2017. The schedule revision is attributed to an increase in construction materials due to redesign work coupled with the slower than planned ramp up of the mining rate. [Indiscernible] mining excides an average of 100,000 per day in January, while the revised schedule assumes an increase in the rate 220,000 ton per day over the next seven months. Long truck cycle times to deliver construction materials and difficult to handle clay overburden are identified is two key issues. Additional mining equivalent was procured in the September quarter and contractors with small equipment have been employed to move overburden. Approximately 24 million tons of overburden and waste have been moved to late January. New Gold reports that the primary crusher and conveyer are 80% complete and commissioning of the crusher is scheduled to commence in March followed by commissioning of the sag and ball mills during the June quarter. I'll now turn the call over to Stefan.