William Zisch
Analyst · Shane Nagle with National Bank Finance
Thank you, Stefan, and good morning, everyone. I’ll start my review with our producing properties. At this time last year, we were anticipating increased production from 6 key growth assets Andacollo, Peñasquito, Holt, Canadian Malartic, Wolverine, and Las Cruces.
Today, I’m pleased to report on the contributions these properties make to our 12% growth in gold equivalent production, which is reflected in this year’s record financial results. At Teck’s Andacollo mine, the addition of temporary crushing capacity boosted their gold production by 25% over the prior year. Teck also constructed additional permanent crushing capacity during the year, and they now expect to achieve design capacity of 55,000 tons per day by the end of calendar 2012. They ended our fiscal year with average throughput of about 44,000 tons per day. So an increase in throughput the design levels has the potential to increase production by about 25%.
Peñasquito operated by Gold Corp, our fiscal 2012 gold equivalent production was 29% higher than fiscal 2011. Gold Corp successfully commissioned a new high pressure grinding roll line during the March and June quarters, but throughput was limited due to reduced water supply in June. Gold Corp’s revised guidance predicated in limitations associated with processed water, expect production to rebound to design capacity of 130,000 tons per day by the end of calendar 2013. Sustaining this design capacity would add an additional 20% to expected production.
At St. Andrew Goldfields Holt mine production is ramped up to design levels of 1000 tons per day and had sustained that level. Production in fiscal 2012 increased threefold over the prior partial year production ending the year at an annualized rate of about 80,000 ounces per year. With the gold price of over $1,600 per ounce, our royalty interest amounted to over 20% of this production.
Osisko focused on commissioning their Canadian Malartic during fiscal 2012, ramping up from the declaration of commercial production during the second calendar quarter of 2011 to a throughput of about 35,000 ounces per day during the June quarter. Osisko determined that it would be necessary to install additional crushing capacity at Canadian Malartic to achieve the design capacity of 55,000 tons per day, and completed the installation of 1 secondary cone crusher during the fiscal year, and the second crusher was just commissioned in July.
Osisko expects the installation of the secondary crushers to allow for more than a 50% increase in throughput to achieve the design mill capacity. The operation was also hampered during the June quarter with a fire that broke out in the mill in May. We compliment Osisko in the management of the situation and their quick response to reestablish normal operations less than 2 weeks after the fire. Even with these challenges production to our account increased more than 7 times over the prior fiscal year and for July our fiscal recently announced record monthly production and throughput.
At Yukon Zinc’s Wolverine mine, another precious metals growth asset, gold equivalent production to our account increased fourfold from fiscal 2011 to fiscal 2012. They continue to ramp up towards their designed capacity of 1,700 tons per day of no throughput and worked to improve precious metals recovery.
The final growth asset in this group is Las Cruces mine in Spain. Having overcome technical and operating process issues during the last year, Las Cruces production exceeded design capacity in the June quarter. As a result production in our recently completed fiscal year was 60% above fiscal 2011.
While not identified as a growth asset for fiscal 2012, we did realize significant increases at Voisey’s Bay as production returned to meet or exceed historical levels following the extended strike during calendar 2010.
While seasonal shipping constraints created quarterly variability that was seen throughout the year, annual nickel production was up 25% and copper production was up by more than 80% in fiscal 2011. Assets that did not report increased production for fiscal 2012 included Barrick’s Cortez and Goldstrike mines along with Newmont’s [indiscernible] mine. Mining sequence called for less production from our areas of interest and in previous year resulting in decreased production at these properties.
Also at our [indiscernible] security operations we did not see production growth as these 2 royalties both reached their caps in fiscal 2011 with [indiscernible] converting from a 25% royalty to a perpetual 2% tail royalty.
For the fiscal year, these reductions were more than offset by growth in the assets I reviewed earlier and the addition of production from Merry Gold as mining extended on the ground that included our area of interest. The acquisition of an interest in Barrick’s Ruby Hill Mine that immediately became a paying contributor, as well as production increases at Gwalia Deeps, King of the Hills, Mulatos and Dolores.
Revenue was about $9 million lower in the fourth fiscal quarter versus the third quarter, while consolidated gold production associated with our royalty interest was up slightly in the fourth quarter. The average price of gold was lower, accounting for about 20% of the revenue decline. At Voisey’s Bay, while mine production was slightly higher than the prior quarter, we saw a reduction in the concentrate shipments and payments, which was just the opposite of the March quarter when the nickel concentrate shipments were significantly greater than mine production.
This reduced concentrate shipping at Voisey’s Bay coupled with a 13% decrease in nickel prices, accounted for more than half of our revenue decrease over the preceding quarter. The final portion of the revenue decrease relates to lower silver production at Peñasquito associated with their drought conditions and a 10% decline in silver price which had an impact at both Peñasquito and Dolores.
With regard to our development properties, on July 26, Barrick announced that due to lower than expected productivity and persistent inflationary and other cost pressures, they initiate a detailed review of possible on schedule and cost estimate in the second quarter of calendar 2012. Barrick indicated that initial gold production is now expected in mid-2014, with an approximate 50% to 60% increase in capital costs from the top end of the previously announced estimate of $4.7 billion to $5 billion suggesting capital of $7.5 billion to $8 billion. I should remind you that as a royalty company we’re not required to contribute to Pascua-Lama capital.
We are disappointed that the construction schedule has been extended, but we continue to believe the Pascua-Lama is a world-class gold project and expect that upon completion of mine construction, Pascua-Lama will become 1 of our cornerstone producing assets in the next couple of decades.
Annual gold production in the first full 5 years of the 25 year mine life is expected to average 800,000 to 850,000 ounces. At our other cornerstone development project Mt. Milligan, we just announced an additional investment.
Tony will discuss the details of the transaction in just a moment, but I’ll give you an update on their construction progress. As of end of June, Thompson Creek reported that progress on Mt. Milligan reflected engineering that was 99% complete, procurement 94% complete, construction at 51% completion and that overall progress was 69% complete.
Thompson Creek also reiterated that Mt. Milligan remains on schedule with startup schedule for the third quarter of calendar 2013 and commencement of commercial production of copper and gold expected in the fourth quarter of 2013. At Mt. Milligan as part of our asset monitoring program we use the services of an independent project engineer who periodically visits the site and provides us with regular updates.
Our most recent report in early June, indicates that Thompson Creek's schedule in completion timeframe is still achievable.
With that I’ll turn the call back over to the Tony.