Michael H. Dilger
Analyst · TD Securities. Your line is now open
Thanks Scott, good morning everyone. I’m going to provide a quick update on some of Pembina’s growth projects. Pembina continues to make great progress on a roughly $5 billion of secured growth projects. So far in 2016, we have placed approximately $740 million of asset into service. Noting none of which contributed to our first quarter results. Starting off with our conventional business, we are pleased to receive the AER approval for the Fox Creek to Namao portion of the Phase III expansion. This was the last major regulatory hurdle for the project and our teams will be out in the field shortly commencing clearing and construction activities. In aggregate, Phase III is now approximately 35% complete. In addition to beginning construction between Fox Creek Namao our focus this year will be on completing all expansion pump stations and the Wapiti to Kakwa Pipeline segments. Phase III continues to trend under budget and on-time for mid- 2017 in service date. Pembina is developing new gathered in laterals to extend the reach of our pipeline network. In aggregate, these investments are expected to require approximately $300 million of capital. The Karr lateral supporting Alberta and Montney was recently completed than is commissioning. The recently announced Altera’s lateral supporting the North East BC Montney is expected to be completed by mid-2017. Numerous other laterals are at various stages of development. Pembina has completed engineering and submitted regulatory environmental applications in support of the North East, BC crude expansion. Partially NGL expansion, Pembina will be constructing approximately 150 kilometers of 12-inch diameter pipeline. Initial capacity of the pipeline is estimated at 73,000 barrels a day and has expected cost of approximately $235 million. The project remains on track for late 2017 in service subject to receiving required regulatory and environmental approvals. The Vantage pipeline expansion is nearly complete, which will increase the system capacity to approximately 70,000 barrels per day from its initial capacity of approximately 40,000 barrels per day. Construction of the new lateral is now complete and the pump stations are almost half done. In aggregate, Pembina has approximately 777,000 per day of crude oil, condensate and NGL under contract through Phase I, II and III pipeline expansion projects. Our Vantage pipeline and re-contracting of base volumes on our systems. Now onto the gas services business unit. So far in 2016, Pembina has commissioned 200 million cubic feet per day of gross processing capacity through the expansion at the Resthaven and Musreau III facilities. Both of these projects were completed under budget and ahead of schedule. Engineering is almost half complete for the Duvernay I facility, which is the first large scale gas processing plant designed specifically for Duvernay. Construction teams are commencing site grading and piling activities, subject to receiving regulatory approval for supporting pipeline, Duvernay I is expected to be in the service in the second half of 2017. This project continues to trend on time and on budget. I'm proud to say we have completed the acquisition of Paramount’s Kakwa River facility which is well situated within one of our core operating areas and we believe to support some of the most economic geology in North America. By expanding our service offering includes sour gas processing, Pembina is well positioned to capitalized on future liquid-rich gas production growth. The acquisition is underpinning by a long-term take-or-pay commitment with Paramount. Furthermore the expansion option at the six of 18 site combined with Paramount's substantial resource base creates a strong growth platform. Pembina is well on its way to becoming one of the largest third-party gas processors, inclusive of Younger and the Empress facilities, Pembina will have approximately 4.2 billion cubic feet per day of gas processing capacity by the second half of 2017. Moving on to the NGL and crude oil midstream businesses. So far in 2016, Pembina commissioned a second 73,000 barrel per day fractionator at our Redwater site, plays 550,000 barrels a day of above ground storage at our Edmonton North Terminal into service and completed an expansion at our Corunna, Ontario site. RFS III continues to trend on-time and on budget for our Q3 2017 startup. Over 50% of long-lead items have arrived on site and the construction of foundations and pilings is now complete. Pembina has received regulatory approval for the development of the terminalling infrastructure for the plant North West Sturgeon Refinery. Detailed engineering and procurement activities are almost half complete and nearly all long-lead mechanical items have been ordered. The project is tracking on-time and on budget and will be placed into service throughout 2017 beginning earlier in the year. On April 11, Pembina announced a joint feasibility study for the evaluation of a world-scale integrated polypropylene facility in Alberta with Kuwait's Petrochemical Industries Company or PIC, which may create an opportunity to develop crucial new market demand for propane in the province. Building local value-added infrastructure will help maximize proceeds that our customers receive for their propane production as well as benefit the province by increasing regional economic activity. This facility could consume approximately 35,000 barrels per day of propane and produce 800,000 metric tons per year of polypropylene. The project leverages our position as WCSB's largest supplier to Alberta's petrochemical industry and extends our integrated NGL service offering. We have a lot of work ahead of us to determine if this project is feasible from a technical, commercial and financial perspective. We plan to make a final investment decision by mid-2017. Earlier this year, Pembina announced interconnection agreements for the Canadian Diluent Hub. In aggregate, these connections provide for initial takeaway capacity in excess of 400,000 barrels per day across multiple pipelines. Additionally, as a result of optimizing project scope and cost savings, the expected capital expenditure for CDH is now $250 million, roughly $100 million lower than initially expected. The in-service date of CDH is expected by mid-2017. Scott.