Michael H. Dilger
Analyst · Macquarie
Thanks, Scott, and good morning, everyone. I too am pleased with the overall operational and financial performance of Pembina during the quarter and the dividend increase our board approved. As Scott mentioned, subsequent to the quarter end, Pembina announced that we placed our Phase II crude oil and condensate pipeline expansion into service on April 24. The incremental 55,000 barrels per day added on to our Peace Pipeline will help alleviate volume constraints for our customers. I'm also very pleased to report that this project was completed on budget and with no lost-time employee injuries given the over 350,000 man-hours worked and over 1.8 million kilometers driven. I'd like to thank our teams for working so diligently on achieving such impressive execution as these projects are in no way easy to carry out. We are continuing to focus on completing construction of the NGL portion of the Phase II Expansion and expect it will be in service in the third quarter of this year. All regulatory and environmental approvals have been received and 70% of the total costs are secured. This project is tracking on budget. As part of our Phase III Expansion, we brought into service a 35-kilometer, 16-inch pipeline segment from Lator to Simonette in January. And subsequent to the quarter end in April, we also brought into service another 35-kilometer, 16-inch pipeline segment from Kakwa to Lator. Today, we have completed over 15% of the overall Phase III Expansion program, and it's coming along according to plan. Also on the topic of Phase III Expansion, we are continuing with our plan to construct new 24-inch and new 16-inch pipeline in the Fox Creek to Namao corridor. We expect these pipelines to have an initial capacity of 420,000 barrels per day and an ultimate capacity of over 680,000 barrels per day, which could bring our total capacity between Fox Creek and Namao to over 1 million barrels per day. The energy regulator, or the AER, has announced it has scheduled a hearing in July relating to this portion of the pipeline. According to AER guidelines, we expect to receive a decision within 90 days after the hearing is concluded, although my personal hope is to settle matters with stakeholders without a hearing. Our service date remains in late 2016 to mid-2017 timeframe depending on regulatory timing. We continue to progress our pipeline lateral program to aggregate new volumes on to our system by expanding our presence in Alberta and British Columbia. Subject to regulatory and environmental approvals, we anticipate our lateral in the Edson, Alberta area to be in service in mid-2016. We have also completed the Willesden Green-Alberta lateral and expect it to be commissioned later this month. Work is advancing on our Northeast B.C. expansion in Northeast British Columbia, and is expected to be in service late 2017 subject to regulatory and environmental approval. Previously announced in February, Pembina continues to expand the Vantage Pipeline system for an estimated capital cost of $85 million to increase mainline capacity from 40,000 barrels per day to approximately 68,000 barrels per day through the addition of pump stations and the construction of a new gathering lateral. The Vantage Expansion is supported by a long-term fee-for-service agreement with a take-or-pay component, and the gathering lateral is underpinned by a fixed return on invested capital agreement. Subject to regulatory and environmental approvals, we expect the expansion to be in service early 2016. In aggregate, Pembina now has approximately 760,000 barrels per day of crude oil, condensate and NGL under contract through our Vantage Pipeline, the recontracting of base volumes on our systems and our Phase I, II and III Conventional Pipeline expansions. Now on to Gas Services. During the first quarter of 2015, we continue to progress construction of our 4 gas plants currently under development. Our SEEP gas plant has all regulatory and environmental approvals, and we have largely contracted all engineering, fabrication and construction services. The plant site construction is 50% complete and is currently on budget and on time with an expected in-service date of the third quarter of 2015. Construction is also progressing well at the Saturn II plant, which is currently tracking on time for an in-service date of the third quarter of this year. I'm also happy to report that we anticipate this -- completing this project under budget. Our Resthaven Expansion, all major equipment has been ordered, and construction is expected to commence in the third quarter of this year. The associated gathering line is 50% installed, and all major river crossings completed. Pembina expects the gathering pipeline to be in service in mid-2015 and the plant complete in mid-2016. We have now received regulatory and environmental approval for the Musreau III plant, which is leveraging the engineering, design and execution strategy of our Musreau and Musreau II facilities. With all major equipment ordered and 40% engineering currently complete, we expect to bring Musreau III online in mid-2016. As I mentioned last quarter, I'm pleased to have previously reported that our Musreau II facility was placed into service in December 2014 and came in on budget and ahead of schedule by 1 quarter. Once these facilities come on stream, we expect our total gas processing capacity to reach 1.5 billion cubic feet per day, including ethane plus extraction capacity of 870 million cubic feet per day. Depending on gas composition, these volumes could result in 70,000 barrels per day of NGL that can be transported for additional total revenue on our pipelines, thus further support our Conventional Pipelines expansion plans. Moving on to our Midstream Business. At our Redwater site, all major equipment has been set for RFS II, module fabrication is finished and overall construction is currently 70% complete. The project schedule has slipped slightly, and we now expect to bring RFS II on stream in the first quarter of 2016 versus late 2015 as originally planned. Our RFS III overall project is tracking on budget and on time, with detailed engineering work underway and over 60% of long-lead equipment ordered. We have received regulatory approval and expect environmental approval later this year. Pending environmental approval, we expect RFS III to be in service in the third quarter of 2017. Once complete, our Redwater site will be the largest fractionation facility in Canada with a total of 210,000 barrels per day of capacity. Site preparation is ongoing at our Canadian Diluent Hub, or CDH. We expect -- we plan to phase in pipeline connections and storage once we receive further regulatory and environmental approvals, and we expect CDH to reach full connectivity and service offerings by mid-2017. Work is progressing at our storage and terminaling facilities in Toronto, Ontario, for a number of initiatives. We also signed a long-term agreement, subsequent to the quarter end, for one of our caverns [ph] at Redwater expected to be in service in early 2016. For our proposed West Coast propane export terminal at the Portland -- at the Port of Portland, Pembina's dedicated project team has conducted consultation with community, regulatory and special-interest group engagement and has completed 2 public hearings as well as significantly advanced detailed engineering design work to support a number of permit applications to be submitted through 2015. Subsequent to the quarter end, Pembina received an affirmative vote of the Portland Planning and Sustainability Commission to move the approval process forward to the Portland City Council. Based on current information with respect to timing, we expect a decision from City Counsel in mid-2015. Subject to receiving the necessary permits and approval, Pembina anticipates bringing the project into service in late 2018. The delay from the original and service date of early 2018 is due to additional civil work that was required on-site resulting from geotechnical factors. Overall, I'm very pleased with the progress we are making on executing our growth plans, and that on a consolidated basis our portfolio is generally tracking on time and on budget. I look forward to bringing multiple projects into service throughout the year, which will continue to grow our fee-for-service cash flows. Scott, over to you.