Isaac Angel
Analyst · JPMorgan. Please go ahead
Thank you, Doron. Starting with slide 16 for an update on operations. Ormat delivered double-digits top and bottom-line growth during the second quarter, clearly demonstrating that we're making solid progress against our multi-year strategic plan. Moving to slide 17, the key area of focus for Ormat's new management for past few years is to drive efficiency where we could to improve margins and overall profitability. We continue to make improvement in all aspects of our value chain. On the product side, we are focused on reducing manufacturing lead-time, improving procurement to lower our material cost, and improving management control. In the electricity segment, in addition to the improvements mentioned above, we're also focused on optimizing the operations of our power plant. We're evaluating each project, adjusting the output to match the resource, targeting expansions and upgrades where we can and centralizing operations to reduce costs. The process translates into a significant and sustainable improvement in gross margin and adjusted EBITDA margin. Turning to slide 18, another goal was to expand our electricity generation, both organically and inorganically, and we continue to make notable progress against these objectives. Electricity generation during the quarter was 1.3 million megawatt hours, an increase of 10% -- 10.8% compared to the last year. This increase was due to the commencement of the second phase of Don Campbell which come online in September 2015 as well as Plant 4 of the Olkaria III complex in Kenya, which come online in January this year. Generation was also positively affected by the high performance in the McGinness Hills complex. Note that while the revenues in the electricity segment increased approximately $13 million year-over-year. The cost of revenue in this segment actually decreased slightly. In addition as we indicated in our last quarterly call, we're working to monetize the Don Campbell 2 plant and further strengthen our balance sheet. As part of joint venture with Northleaf Capital Partners, we have completed the required power generation tests under the agreement to determine the final terms for closing which we expect to take -- which we expect to take place during the third quarter. Following the closing, Ormat will contribute -- Ormat Nevada will contribute Don Campbell 2 to ORPD and Northleaf will buy their interest share for a total amount of approximately $43 million. Turning to slide 19, as I mentioned, inorganic growth is another key part of our strategic plan. On July 5th, 2016, we completed the acquisition of Bouillante Geothermal Plant for approximately $18.6 million. This acquisition is immediately accretive to the earnings. GB owns and operates a 14.75 megawatt Bouillante Geothermal Plant located on the island of Guadeloupe, a French territory in the Caribbean. The Bouillante Plant currently generates approximately 10 megawatts with an expansion potential to up to 24 megawatts of capacity and Greenfield with the potential for additional 20 megawatts. We have plain modifications to the existing equipment as well as to further develop the asset, with a potential of reaching a total of 45 megawatts in phase development by 2021. Ormat together with CDC, a French state-owned financial organization, acquired approximately 8% interest in GB in the proportion of 75 to Ormat and 25 to CDC, which means that we acquired approximately 60% of the project. This acquisition marks another achievement in our strategic plan to expand our business to new geography. With CDC, an ideal partner, as CDC's profession with the French regulation and experience in investment that serve the economic development trends. Together with BRGM and CDC, we will continue to develop the Bouillante Geothermal Plant. Turning to slide 20, for an update on projects under construction. We added 10 megawatt to our portfolio from the Bouillante acquisition and plan to add another 150 and 280 megawatts by the end of 2018, by bringing new power plants online and expanding existing plants. The expansion plan includes the Platanares geothermal project in Honduras, in which construction and drilling activities are ongoing and equipment is on its way to the site. We expect to reach commercial operation before the end of 2017. We also initiated construction of Tungsten Project in Nevada. We expect Tungsten to generate 24 megawatts when it comes online at the end of 2017. Drilling is ongoing and major construction permits as well as interconnection agreements are in place. Dixie Meadows is at earlier stage and is expected to generate approximately 15 to 20 megawatt. We believe that both Dixie and Tungsten, may qualify for the production tax credit. We have taken us from the Menengai project in Kenya to the slow progress in the resource development and verification. In Sarulla, Indonesia, for the first phase, engineering and procurement has been substantially completed and construction is in progress with major activities relating to mechanical and electrical equipment installation. Major equipment including Ormat's OEC and Toshiba's steam turbine has arrived to the site and currently installed. The drilling of production and injection wells for the first phase is completed. For the second phase, engineering and procurement has been substantially completed, infrastructure work is in progress, and most of the equipment to be supplied by Ormat was delivered. For the third phase, engineering and procurement is still in progress, infrastructure work is in progress and manufacturing of equipment to be supplied by Ormat is underway as planned. Currently, for the second and third phases, drilling activity is still going and project achieved today based on preliminary estimates, approximately 70% of the required production capacity and approximately 15% of the required injecting capacity. The project is still facing delays, mainly in field development of the second and third phases and certain cost overruns resulting from delays and excess drilling costs. As a reminder, Ormat holds 12.75% equity interest in the project corresponding to approximately $60 million equity investment, covering Ormat share based on the current project plan. With respect to Ormat's role as a supplier, all contractual milestones under the supply agreement were achieved. The consortium expects that the first phase of operations to commence towards the end of 2016 and the remaining two phases of operations are scheduled to commence within 18 months thereafter. The project, I just described as well as additional projects under various stages of development are expected to support our expansion by the end of 2018. Besides the investments in new projects, we're continuing our exploration and business development activities to support future growth. If you could please turn to slide 21, you would see that our CapEx requirement for the balance of 2016 stands at approximately $135 million. We plan to invest a total of approximately $94 million in capital expenditures on new projects under construction and enhancement and additional $41 million are budgeted for exploration activity. Development of new projects, investment in new activities that reflects expenditure under the new strategic plan, and maintenance CapEx for operation -- for operating projects. In addition, $31 million will be required for debt repayments. Turning to slide 22, for an update on our product segment. We continued to win orders and strengthen our backlog, which as of August 2nd, 2016, stands at approximately $228 million. During the second quarter, we added 36 million EPC and supply contract that we secured in May with Eastland Group for a geothermal project located in New Zealand. Under the contract, Ormat will provide its air-cooled Ormat energy converter. The construction of the project is expected to be completed in 2018. We have been operating in Turkey for many years and expect to continue and operate in the coming years. The event in Turkey didn't have a material impact on electricity needs of Turkey or the ambition plan for renewable energy. We are now in the final negotiation stages of a new supply contracts in Turkey and we're very optimistic in the future as the turbulence has been behind us. We are -- turning to slide 23 for our 2016 guidance. We are reiterating our 2016 full year revenue guidance and increase our adjusted EBITDA guidance. For the year, we expect total revenue to be between $620 million and $640 million. We expect revenue in our electricity segment to be between $410 million and $420 million. For the product segment, we expect revenues to be between $210 million and $220 million. We expect 2016 adjusted EBITDA to be between $310 million and $320 million. We expect annual adjusted EBITDA attributable to minority's interest to be approximately $17 million. This amount assumes the inclusion of the second phase of Don Campbell power plant in joint venture with Northleaf. In summary, I'm very pleased with the strong results we delivered in the first half of the year. Ormat remains well-positioned for success with a healthy balance sheet, a strong pipeline, and a balanced portfolio of operational and third-party projects around the world. Thank you for your continued support and now I would like to open the call for questions. Operator?