Thanks, Brian, and good morning, everyone. As Tom mentioned, our team safely delivered an exceptional finish to the year, and we’re very proud of what our 30,000 strong Newmont team was able to achieve during 2022, despite the very-challenging and volatile operating environment that the whole mining industry was navigating. Today, I’ll cover the site level highlights for the fourth quarter, along with an overview of what to expect in 2023 from each of our operations and our two key development projects. So turning to the next slide, let’s get started with Peñasquito. When we acquired Goldcorp in 2019, we committed to delivering synergies of $365 million per year by applying the Newmont operating model to deliver value from G&A, supply chain, and most importantly, the implementation of our proven Full Potential continuous improvement program. Peñasquito alone has blown that target out of the water, delivering more than $700 million in annual synergies since we closed the acquisition nearly four years ago. Our core capability at Newmont is safely operating Tier 1 open pit and underground mines, and over 80% of this value is delivered from mining and processing improvements. And we have not stopped yet. Peñasquito delivered a strong fourth quarter, setting a new record in December for the tons we moved ex pit and exceeding our full year production guidance for the third consecutive year under the Newmont operating model. During the fourth quarter, mining was primarily from the Chile Colorado pit as planned, resulting in lower gold grades and higher levels of silver, lead and zinc contents. And as we progress this year, we expect this mining sequence and trend to continue at our two-pit polymetallic mine as previously communicated and in line with our long-term mine plans. In the first quarter, we expect gold grade to decline more than 20% compared to the fourth quarter due to this mine sequence. And for the year we expect gold production to be around 25% lower than 2022, whilst our gold equivalent ounces will be steady year-on-year. In South America, Yanacocha delivered slightly higher production during the fourth quarter compared to quarter three. With higher production expected in 2023 from higher leach recoveries due to the continued use of injection leaching, we continue to progress our review of the scope and the pace of the Sulfides project and expect to spend approximately $300 million to $350 million of development capital in 2023 and again in 2024. This spend is related to advanced engineering, procurement and completing camp construction. At Merian, the site delivered its highest quarterly production in two years due to record mill performance combined with higher grades mined from both the Maraba and Merian II pits. Merian is expected to deliver lower production and higher unit costs in 2023 as we begin stripping the next phase of the Merian pit, resulting in lower grades presenting to the mill as part of our planned mine sequence for the site. In particular, in the first quarter, we expect grades to decline more than 15% compared to quarter four as we enter the stripping campaign. And finally, at Cerro Negro, the site delivered another solid quarter due to higher grade and strong mill performance. Production from Cerro Negro is expected to steadily increase each quarter in 2023 due to sustained productivity improvements from our Newmont operating model. This will result in progressively higher tons mined and processed throughout the year. We continue to progress the first wave of district expansions at Cerro Negro, which will contribute to the higher production this year. And we just hit an important milestone with the first blast to commence development at the Silica Cap portal. In December, this project received approval for $200 million that will be spent over the next two years to develop Cerro Negro’s future through both the Marianas and Eastern Districts. And these funds will primarily be spent on underground development activities. This investment will extend mine life beyond 2030, and we expect to see annual production increase to above 350, 000 ounces beginning in 2024. Since we acquired Cerro Negro nearly four years ago, we’ve improved underground development rates by more than 50% and doubled the size of our land package to over 1,000 square kilometers, demonstrating both our operating capability and our confidence in the untapped growth potential from this highly prospective gold district in Argentina. In North America, our Canadian operations all delivered higher production in quarter four, a combined increase of 30,000 ounces compared to quarter three due to strong grades and improved productivity. At Éléonore, we finished 2022 with the strongest quarterly performance of the year. And importantly, key roles are all filled, and the team is ready to deliver higher ounces in 2023. This increase is largely driven by sustained productivity improvements as higher underground mining rates and strong mill performance will offset the lower grades coming through. At Musselwhite, we delivered our best quarterly performance in terms of gold production, development meters and total tons mined in more than five years. We anticipate production in 2023 to be weighted around 65% to the second half of the year, steadily increasing each quarter as mining continues in the PQ Deeps area. Porcupine delivered its strongest quarterly performance of the year and annual production is expected to slightly improve in 2023 due to higher tons mined and higher grade. We continue to progress the project to replace production from the Hollinger pit production with a layback of the Pamour pit. An investment decision is now expected in late ‘23 as we’ve been able to implement improvements to extend the life of the Hollinger pit. And at CC&V, we achieved our highest December production in over three years, resulting in a solid fourth quarter from higher tons mined and placed on our leach pads. Production in 2023 is expected to decrease slightly due to lower grades as we extend mine life through the stripping of a layback in the Globe Hill pit. In 2023, our four North American operations are expected to deliver nearly 1 million ounces of gold. This increase over 2022 will be safely delivered by a strong leadership team of experienced general managers who are in place, a stable workforce and without the challenges and constraints from COVID that we had to navigate through during the first half of last year. Boddington delivered an exceptionally strong quarter with 20% higher gold production and more than 50% higher copper production compared to quarter three. We set two important records in the fourth quarter, a new all-time monthly production record in December for both gold and copper on the back of higher grades and strong mill performance, and the best quarterly performance for our autonomous haul truck fleet for the tons moved per hour, a key metric for every open pit mine. Reaching these important milestones at a cornerstone operation like Boddington is a tremendous achievement, and we are proud of the hard work and dedication that our team has demonstrated in implementing leading technologies to promote both safety and productivity. The lessons we have learned will benefit not only Newmont but the gold industry as a whole, and we will look to leverage this technology and our experience at Boddington as we expand the use of autonomous solutions across our global business. In 2023, gold production is expected to remain steady compared to 2022, as continued strong mill performance and tons mined offset lower grade associated with further stripping in Boddington South pit. Tanami maintained strong production throughout the year and reliably delivered a solid fourth quarter from higher tons mined combined with higher grades despite an extreme weather event and record rainfall across Northwest Australia late in the quarter. Gold production is expected to be lower in 2023 and 2024 due to lower grades from the planned stope sequencing to allow for the underground construction of the crushing and conveying infrastructure associated with the Tanami Expansion project. Due to the extreme weather events and associated flooding, the main access route for supplies to Tanami and Tanami track has been closed from late December through mid-February. And although our fourth quarter was largely unaffected by this event, critical consumables such as cyanide, explosives and other reagents that can only come to site by road have not been able to be delivered over the last 6 to 8 weeks, and we have consumed the stocks that we maintained on site. As a consequence, we had to cease milling operations at Tanami over the last few weeks, and this will have an impact on gold production for the first quarter. However, the bottleneck at Tanami is the mining operation, not the milling plant, and mining has continued throughout this period with the ore being stockpiled in front of the mill. We restart the mill tomorrow and expect to recover the ounces that will be delayed from Q1, but that now means that we will have a production profile this year that will be strongly weighted to the second half. And with this impact, we expect only around 10% of Tanami’s 2023 gold production to be delivered during the first quarter. We also continue to progress the expansion at Tanami. Overall progress is now at 50% with engineering and procurement effectively complete, protecting the project from any new inflationary or supply chain challenges in the coming years. 373 meters of concrete lining has now been installed in the upper part of the 1,500 meter deep shaft, and this furnishing of the shaft continues to be the critical path work for the project. Underground development for the project has largely been completed with crusher and conveyor chambers, all fully excavated and ready for construction of infrastructure to commence. And as I signaled last July, following the completion of the four important project milestones of shaft reaming, head frame construction, underground development and the opening of state and international borders in Australia, we would assess project capital cost and schedule. We are expecting total capital costs of between $1.2 billion and $1.3 billion and the project completion in the second half of 2025. This is consistent with the direction we provided last July. Tanami Expansion 2 remains a key project in Newmont’s portfolio and underpins Tanami’s future as a long-life, low-cost producer well into the 2040. Turning to Africa. Our two operations in Ghana delivered this year’s strongest quarterly performance in Q4, increasing production by more than 45,000 ounces compared to Q3. In December, Akyem delivered its strongest monthly production in seven years on the back of higher tons mined, higher grades and strong mill performance. In 2023, Akyem is expected to deliver lower production as we progress stripping of the next layback in the pit. And as a consequence, 2023 gold production will be around 20% lower than last year as a result of lower grades. Ore grade is expected to decline by more than 40% in Q1 compared to Q4. Moving across Ahafo, the mill achieved record throughput during the fourth quarter, benefiting from higher grade and mining rates as Subika underground really starts to hit its stride. In 2023, gold production from Ahafo is expected to steadily increase each quarter as we open up more draw points in the Subika underground, lifting mining rates and resulting in the delivery of more higher grade ore to the mill over the course of the year. As a consequence, gold production will be strongly weighted to the second half of the year with around 15% of the year’s production to be delivered in the first quarter. And I’m pleased to announce that we are making great progress with our new mine in Ghana, Ahafo North, where we gained land access and have commenced construction and highway relocation activities. Ahafo North expands our existing footprint in the Ahafo complex, adding more than 3 million ounces of gold production over an initial 13-year mine life. And when combined with Ahafo South just 30 kilometers away, we expect to deliver an average of 850,000 -- I beg your pardon. 350,000 -- sorry. We expect to deliver an average of 850,000 gold ounces per year through until at least 2030 from our Ahafo complex. Leaning into one of Newmont’s core capabilities, we have conducted extensive regulatory and community engagements to ensure that from the very start of this project, we earn and maintain social acceptance. The process of engagement is critical work that cannot and must not be rushed. There’s an African proverb that we consistently apply at Newmont. “If you want to go fast, you go alone. If you want to go far, we go together.” And as I signaled last July, gaining land access and commencing construction activities was a key milestone for us to reach in order to assess project capital cost and schedule. We are expecting total capital costs of between $950 million and $1.05 billion in project completion in the second half of 2025. This is consistent with the direction we provided last July. We remain very excited about Ahafo North and look forward to bringing you updates as we develop this new mine over the next two years and create value from the best unmined gold deposit in West Africa. Finally, to our two non-managed joint ventures. Our 38.5% ownership of Nevada Gold Mines and 40% interest in Pueblo Viejo contributed 1.45 million ounces of attributable gold production in 2022. For Nevada Gold Mines, disappointingly, fourth quarter and full year production fell below the lower end of the guidance range and above the higher end for costs that were provided by Barrick in November 2022. However, most concerning was that these two non-managed joint ventures have experienced three tragic fatalities over the last 12 months. As for the 2023 guidance provided last week by Barrick, gold production is expected to increase by around 10% from both Nevada Gold Mines and Pueblo Viejo in 2023. Both of these joint ventures are core to the Newmont portfolio, and we look forward to our managing partners safely delivering on their 2023 commitment. And with that, I’ll hand it back to Tom.