Rob Atkinson
Analyst · JP Morgan. Please go ahead
Before I start, I'd like to recognize the very significant efforts that continue to be applying at all of our operations in order to manage COVID and to keep our team safe and healthy. It is important to realize that this pandemic has some way to run and these efforts will need to continue from many months to come. Turning to Slide 11, I'll give an update on Africa's performance. Our assets in Africa delivered another strong performance in the first quarter and team maintained its momentum from quarter four delivering a strong first quarter from higher grade and improvements to the middle. We increased mill efficiency and overall planned performance during the first quarter, improving throughput by 3% whilst also reducing energy consumption by 4%. These improvements are driven by full potential projects and are an example of how we continue to find elevated solutions even at our matured operations. The site is well positioned to deliver solid production throughout the year, expecting to reach its highest production and lowest cost during the fourth quarter. Ahafo delivered higher stoppage tons due to mine sequencing improvements that resulted in an extra bench being mined at Awonsu, helping to offset lower grade during the first quarter. We continue to progress the development of our new mining method at Subika, sub-level shrinkage which will increase tonnage improved productivities and reduce mining cost. The team has commenced stopping ahead of schedule and we completed our first two ore blast this month a major milestone for the project. As the sub-level shrinkage project progresses during 2021, we expect to see improvements in grade throughout the year and a 50% increase in ore tones, mining by the fourth quarter. In addition, we expect to reach higher ore grades from the open pit operations in the second half of the year positioning Ahafo to deliver a very strong finish to 2021. Finally, at Ahafo North we continue to advance the permitting process with EPA. I'm pleased to announced that we've completed the environment's impact study and paid the invoice for the impairment this month. Putting us on track for full month's decision in July of this year after the receipt of the [indiscernible]. All other aspects of this project are proceeding well. Turning to South America on Slide 12, South America has been the region most impacted by the virus and we continue to see the more significant impacts in Argentina and Peru. We remain focused on the safety protocols to protect the health and well-being of our workforce and communities as we continue to mitigate the impacts of travel restrictions caused by the virus. We do expect to impact due to COVID to continue for some time until vaccinations are available and being administered in large quantities. Merian was the best performing asset in South America despite heavy rainfall during the first quarter which impacted productivity in the mine. The team continued to utilize ore blending strategy to optimize mill performance resulting in an increased tons process whilst maintaining stable grades. As the year progresses, Merian will transition from softer saprolite to harder ore, which will result in higher production through improved grades. But will be partially offset by lower mill throughput. And Cerro Negro will continue to work closely with government representatives and other key stakeholders as we manage our operations through the evolving pandemic. As we reviewed the number of COVID cases in the country and the increasing case numbers at our old site. We made a decision to temper hours, suspend operations for five days in January and seven days in March to reduce the spread of the virus. While these decisions impact first quarter production the health and safety of our workforce remains our first priority and despite stoppages during the quarter, we've been able to resume development at San Marcos and make good progress on the tailings storage to facilities expansion. Cerro Negro continues to focus on safely ramping up site activities, increasing camp capacity and appointing a new dedicated team to optimize the important and complex shift changes. Yanacocha has also experienced significant challenges due to COVID and due to the pandemic productivity will likely be impacted throughout the year. Despite the challenges from the virus, Yanacocha delivered higher grade material mine from Yanacocha maine [indiscernible] pits. These tons replaced on leach-plants during quarter which we expect to result in higher production in future quarters. In February, we decommissioned the old site mill and completed our transition to leach-only operations as planned ahead of the developments of Yanacocha Sulfides which will extend Yanacocha's operations well beyond 2040 [ph]. We continue to advance the sulfides project. I can't be walking through our internal peer review process in preparation for full funds approval later in the second half of 2021. Yanacocha is a world class asset in Newmont's portfolio with significant product prospectivity [ph] and we look forward to bringing you this next chapter in Yanacocha's long history of profitable production. Coming to North America, Slide 13. Peñasquito delivered another strong performance and achieved record core product sales of nearly 300,000 gold equivalent ounces in the first quarter due to higher grades and recoveries. The site also set a new monthly record for concentrate transport and shipping, rolling and selling over 125,000 tons in March. Full potential continues to deliver improvements to our mining and no performance at Peñasquito. And as an example, we've increased the average payroll for our whole trucks by 17 tons per load. This translates to an additional 12 million tons moved per year for next to zero cost, an increase of over 6%. The site is well positioned to remain a strong performer throughout 2021 and is also currently exploring our extensive line package of Q2 development opportunities. CC&V delivered lower grade and experienced geochemistry challenges during the first quarter and as a result, ore that was planned to be milled was redirected to the leach pads. Drilling improvements are expected during the second half of the year helping the offset the challenges experienced this quarter. At Musselwhite, we continue to closely monitor the impacts from COVID in Ontario and have made a decision to temporarily suspend operations for five days in April to reduce the spread of the virus. Despite the impacts from COVID which draw changes to the plan mining sequence, grade and ore tons mining continued to improve over the prior quarter. We're also continuing our full potential at Musselwhite with the largest focus on increasing development base and driving productivity as the year progresses. At Porcupine, ongoing ground control rehabilitation in the Hoyle and underground mining coupled with mill and equipment maintenance has resulted in more tons mined and processed during the quarter. We have begun the implementation of our full potential program at Porcupine which will deliver efficiency improvements in the second half of the year. Éléonore continues to make strong improvements to performance and productivity increasing underground development rates to an average of 40 meters per day by the end of the first quarter. This is an improvement of 25% from 2020. In addition the safest way, tele-remote mucking equipment for the first time, increasing tons mine, efficiencies and safety of our workforce. Éléonore will continue to be a stable contributor during 2021 as we expected to deliver steady production increases from higher tons mine and process through the year. It's also important to note, that the site is making good progress in the fight against COVID. I'm pleased to report that 70% of Éléonore workforce has been vaccinated so far. Turning to Australia on Slide 14. Tanami delivered a consistent performance despite heavy rainfall increasing ore tons mined during the quarter. For the rest of 2021, we will continue to monitor impacts of COVID on the Northern territory due to the potential closure state and territory borders. But we expect that production will steadily increase grades improves throughout the year. In addition, the team continues to advance Tanami Expansion 2 supporting the sites future as a long life, low cost and very efficient producer. We recently completed construction of the camp facilities and the excavation of the upper section of the production shaft putting us on track to deliver significant ounces, cost and efficiency improvement in the first half of 2024. At Boddington, we delivered a solid quarter in line with our expectations and full year guidance. Mine maintenance was completed during the first quarter ensuring the plant continues to perform at high levels. As we get into the second half of the year, as highlighted in our previous guidance. We expect to achieve higher grades, improved throughput and increased ore tons made due to efficiency from Autonomous Haulage and improved mill processing. As you can see in the picture, we are well in our way to operating the world's first open pit gold mine with an Autonomous truckload and I will provide more details in the project on Slide 15. I'm pleased to announce that the first Boddington AHS haul trucks went live in the March of this year and we've successfully started the first phase of our transition to fully autonomous haulage fleet which will improve safety and extend mine line as one of our core assets. Today, we're operating four trucks hauling ore from stockpiles to the crusher and four additional trucks completing the final testing. We expect to expand the use of autonomous units in the pit during the second quarter, deploying the entire fleet 36 trucks by the end of September. As a reminder, the AHS project was approved in February of 2020 meaning the project was planned, constructed and be able to achieve first production in just over a year. Being on track to deliver this project on time and on budget will be a huge accomplishment especially during the global pandemic and I'd like to thank our team at Boddington and our partners at Caterpillar including their dealership WesTrac. All the overgrowing dedication and drive during such an unprecedented time. We've received very strong support from Caterpillar through the project and we look forward to working together on future endeavors. In addition to the exceptional delivery at this project, we have already seen strong performance over the last month from these machines and the operating team. The fleet has been running non-stop since going live in March to eliminating stoppages from shift changes, meal and toilet brakes, tea breaks which increases its productivity and already the new vehicles have the first major milestone moving over 1 million tons in less than six weeks. It's also worth noting the significant productivity improvements that we'll achieve with this fleet will also translate to lower fuel cost and consumption. Reducing our carbon emissions at Boddington and supporting Newmont's climate initiatives. But most importantly, the use of these Autonomous trucks reduces the exposure that our workforce has to potential vehicle interaction, helping us to further reduce fatality risk and to ensure that our team members return home safely at the end of the shift at work. The implementation at the industry's first autonomous haulage fleet will be a major milestone from Newmont and the gold industry as a whole. We will look to replicate this technology, training and experience at other sites around the globe leveraging our team of experts and lessons around Boddington and we will also look to integrate further autonomous solutions both at future open pit and underground mine, as we plan and develop the assets in our project pipeline, ensuring that these important improvements to safety and productivity are applied across the global business. And with that, I'll hand it over to Nancy on Slide 16.