Tom Palmer
Analyst · JPMorgan. Please go ahead
Thanks, Gary. Before reviewing our operational performance and integration work, I'd like to take a moment and welcome Rob Atkinson, our new Chief Operating Officer, who you will hear from next quarter. Over the past 25 years, Rob has delivered step-change improvements in safety, productivity and sustainability in the mining sector.We are excited to have Rob on board, as he brings a demonstrated commitment to building strong safety cultures and to leading and empowering teams to achieve meaningful business results. With his capability and experience, Rob's addition to our leadership team will help to drive the delivery of value we have identified through our combination with Goldcorp.Now beginning with a review of our regional performance on slide 8. Our North American operations were impacted by near-term challenges in the second quarter. The performance is expected to improve in the second half, as we work to fully integrate the Goldcorp assets and set them up for sustainable future success.At Peñasquito, operations safely ramped back up in June and concentrate inventories are almost back to normal levels. During the shutdown, the team brought forward maintenance on various plant and equipment. The remainder of 2019 and into 2020, grades are expected to steadily improve as we complete the stripping campaign in the main Peñasco pit. And we also launched our Full Potential Program at that operation and I'll touch a bit more on that later.On June 17, we began good-faith dialogue with a trucking company in the Cedros community. And just last week, the team hosted a session on-site. The stakeholders were able to see firsthand the focus we have on environmental compliance, order efficiency, social development and long-term community water plans and more.At Musselwhite, the rehab of the conveyor ramp is around 70% complete. Secondary egress has been successfully established, allowing us to recommence both development activities and work on the materials handling project earlier this month.The focus for the remainder of 2019 will be on replacing the conveyor system and using this period as an opportunity to get ahead on development work. At Éléonore, we have begun accessing higher grade in the Horizon five zone and preparations are underway to launch Full Potential in the fourth quarter. We also continued to advance materials handling project to improve productivity from lower levels of the mine.At Porcupine, the Borden Project remains on schedule to reach commercial production in the fourth quarter. And at Red Lake production at Cochenour was ramping up in the second quarter. However, in early July, we proactively paused the underground operations in order to strengthen our controls following an in-depth review of a historical underground area.Partial underground operations resumed a few days later, following the implementation of additional controls. And over the course of this quarter, we'll be installing some further control measures and expect to return to full underground operations during Q4.Turning to CC&V. We delivered steady production during the quarter and have signed a toll milling agreement with Nevada gold mines to continue processing concentrate in Nevada. In the second quarter, our Nevada operations performed as planned with Carlin safely completing its annual shut on Mill 6. And on July 1, we closed the Nevada joint venture and Barrick assumed operatorship of the Nevada gold mines. We look forward to working together and supporting the joint venture's efforts to unlock significant value over the years ahead.Turning to South America on slide 9. Yanacocha delivered another solid quarter, with continued higher grades in the Tapado Oeste pit and drawdown at La Quinua leach pad. And at Merian continued productivity improvements helped offset seasonal wet weather.At Cerro Negro, second quarter performance was in line with our expectations. And we anticipate a stronger second half as we reach higher grades from the Eureka and Marina Norte.We launched Full Potential earlier this month, with the focus on improving development and mining rates, maximizing recoveries and applying our asset management methodologies at that operation.Looking forward, Quecher Main continues on schedule, with commercial production expected in the fourth quarter. Turning to Australia on slide 10, Tanami, delivered another solid performance coming off higher grades in the first quarter. And we are starting to see the cost benefits from the transition to natural gas-fired power.Boddington continues to progress the stripping campaign in the South Pit and expects to reach higher grades in Q4. We recently advanced our autonomous haulage study, with the potential to reach a full funds decision later this year.If approved, the project is expected to improve cost and mining productivity, by converting the fleet of 39 haul trucks to autonomous operation, using the Cat command system.At KCGM, geotechnical remediation work on the east wall of the Fimiston pit is ongoing. We are starting to see production from the Morrison starter pit. And expect to reach higher grades in the second half.And Tanami Expansion 2 continued advancing towards a full funds decision in the second half. Engineering works are ongoing. And shaft sinking has progressed beyond the 150 meters.Turning to Africa, on slide 11, Akyem again delivered strong quarterly production on the back of higher grades. And new Full Potential initiatives associated with optimizing grounding and improving recoveries.At Ahafo, we continue to benefit from higher grades in both the Subika open pit and underground. We recently approved funding for further laybacks of the Awonsu pit. And while we anticipate first gold from these laybacks in the fourth quarter of this year, the majority of the benefits flow from 2024 to 2029.These laybacks extend the life of Ahafo surface mines by another four years. And the Ahafo Mill Expansion is nearing completion, with commissioning expected to start next month and commercial production in the fourth quarter, keeping us on course for a record year, in Africa.Following our review of geotechnical assumptions at the Subika Underground mine, we are assessing mining methods for the low levels of that mine. As we conduct this review, we are mining more laterally and as a consequence have reduced our 2019 outlook by approximately 40,000 ounces.Looking forward, at Ahafo North, we continue to work through the permitting process, engaging with the relevant government agencies and building upon our relationships with traditional leaders and local communities.By putting it all together, we delivered 1.6 million ounces and all-in sustaining cost of approximately $1,000 per ounce in the second quarter. With our global and balanced portfolio, allowing us to overcome headwinds at select sites with continued solid execution across the rest of our operations.Turning to a review of our operational outlook on slide 12, our 2019 guidance includes a full year for the Newmont operations, including a full year for our Nevada sites and a partial year for the former Goldcorp operations, from April 18 to December 31.Now outlook has been updated, to include the impacts from the blockade at Peñasquito, the conveyor fire at Musselwhite, the installation of additional safety controls at Red Lake and the impacts from the slip in the Gold Quarry pit at Carlin in late 2018.2019 is second-half weighted as we ramp-up the Ahafo Mill Expansion and Borden projects and reach higher grades at Cerro Negro, Peñasquito and Éléonore.Sustaining capital of $985 million, includes investments in tailings storage facilities, expansions at Ahafo and Peñasquito, VLF2 leach pad expansion at CC&V in addition to infrastructure equipment and ongoing underground mine development throughout the portfolio.Development capital of $575 million includes payment in Ahafo Mill Expansion, Quecher Main, Borden and conveyor remediation works at Musselwhite. In summary, we expect to deliver 6.5 million ounces of gold, an all-in sustaining cost of $975 per ounce in our first partial year as a combined company. This operational outlook does not include any of the benefits that will flow from our Full Potential work at Peñasquito and Cerro Negro or from supply chain improvements where we are actively progressing work.Turning to slide 13 for a look into our early successes. We have made excellent progress in the first 90 days of integration. On the G&A front, we recently completed our organizational design work, to resize the Vancouver office from a corporate headquarters to a regional office. This work has already captured $40 million per annum in labor savings to date. We have realized a further $10 million per annum in non-labor G&A synergies through the consolidation of insurance and benefit programs real estate and other quick wins. We have commenced the next phase of this work, which shifts the focus from Vancouver to target duplication across the operating businesses.Turning to our supply chain work. Newmont's experienced supply chain team is actively chasing value across several fronts. Quick wins are being achieved through the extension of best pricing and rebates and we are also leveraging our increased scale and volume to seek improvements on some of the input costs.Our Full Potential program is well underway at Peñasquito recently kicked off at Cerro Negro and we're preparing to launch at Éléonore in the fourth quarter. At Peñasquito, Full Potential began in early June, and we have our key subject matter experts on the ground working with the site team focused on opportunities in the areas of mining, processing, asset management, G&A and external spend.Another example of applying our technical expertise to turn these former Goldcorp assets around is our strategic resource development program. This program lays the groundwork for future business plans of testing an extensive set of mine plan options across a wide range of interrelated variables.The output from this work ensures that we are pursuing the optimal development and value path for operations. At Musselwhite, our strategic resource team is working with the site to understand the entire value chain and review critical trade-offs in physicals financials and risks to develop the best value for that operation.In summary, our structured approach to delivering value heads us well on our way to achieve the cash flow improvements of $365 million per annum. We expect 40% of the improvements to be realized this year ramping up to 80% next year, and 100% by 2021.Looking further ahead at our project pipeline on slide 14. Another key value proposition in our combination with Goldcorp is our industry-leading project pipeline. Leveraging our project delivery track record it provides the opportunity to establish a foundation for steady production and cash flow for decades to come. This pipeline gives us significant flexibility and we will continue to advance only those projects that meet our minimum hurdle rate of 15% at a $1,200 gold price.As previously mentioned, we recently approved the Awonsu layback and this project is now shown in execution along with Musselwhite materials handling, and the three projects we expect to complete in the fourth quarter this year:Ahafo Mill Expansion, Quecher Main and Borden, it's also worth noting that we shifted the Coffee project from definitive feasibility to pre-feasibility as we take a step back to perform further exploration confirm the resource advance permitting activities and improve our understanding of the asset.As part of our integration and annual planning work, we will continue to evaluate all projects through our rigorous and disciplined investment system. I look forward to providing updates on our project portfolio as well as our optimization work on the six former Goldcorp assets to deliver long-term value as we move ahead.With that, I'll hand it over to Nancy on slide 15.