Chris Stewart
Analyst · Roth Capital Partners. Your line is now open
Thank you, Rob. Good morning, everyone. Q3 2018 was a strong operating quarter with consolidated production of 43,700 gold equivalent ounces using a 75 to 1 gold to silver ratio. Consolidated production for the nine months ended September 30, 2018 was 135,000 gold equivalent ounces, which is 48% higher than the comparable period of 2017. At El Gallo mine in Mexico, residual leaching activities continued after the final ore was mined and stacked on the heap leach from El Gallo Gold. Work progressed on the Fenix project, including the start of our feasibility study in July and ongoing environmental permitting efforts. While the most recent Fenix project, PEA economics were completed at $1,250 gold and $16 silver, based on current metal prices, the project still demonstrates strong economics with an NPV of $41 million and a post-tax IRR of 22%. Based on residual heap leach activity, the operating team achieved a production of 10,400 gold equivalent ounces in Q3, which brought the year-to-date production to 33,400 gold equivalent ounces. Following cessation of mining and crushing activities at El Gallo, by the end of Q2, cost in Q3 were down to a total cash cost of $671, and all-in sustaining cost of $696 per gold equivalent ounce. Q3 was strong as a result of ore stacked on the heap leach pad at the end of Q2. Residual heap leaching is expected to taper significantly in Q4 to be more in line with our longer term recovery expectations. Closure and reclamation and residual heap leaching are ongoing and will continue for several years. Our Q3 work is focused on advancing the Fenix project towards the final feasibility study to be published during the first half of 2019. During the three and nine months ending September 30, 2018, we spent $1.5 million and $2.6 million, respectively, on feasibility study work, which includes reviewing mineral processing, mine sequencing, material transportation, tailing storage options and flow sheet optimization. We also progressed the permitting for Project Fenix and plan to make our formal submittal for Phase 1 in November with approval expected in Q2 2019. Phase 1 is for the reprocessing of El Gallo Gold, heap leach material through a typical carbon-in-leach mill circuit. Phase 2 permitting, which we look to obtain in 2020 would require further expansion to process sulfide ores from mainly El Gallo silver. Project Fenix is expected to add another 12 years of mine life to our Mexican operations. In Canada, at Black Fox during Q3 underground exploration efforts focused on potential resource growth near existing infrastructure. We also commenced an exploration drift on the 810 meter level, which will allow us to drill the deep potential for the main Black Fox deposit. We have initiated cost, logistics and environmental baseline studies at Lexam’s Fuller project and we now have completed the resource estimate for Froome deposit near the Black Box mine and a new resource for the Stock East Deposit near our mill. Together with results announced in Q3 from the ongoing exploration program of the complex we continue to develop expanded ore zones that can increase our mining output and gold production. We've produced 11,600 gold equivalent ounces for a total of 37,750 gold equivalent ounces produced year-to-date. Cash costs were $932 and all in sustaining costs $1,285 per gold equivalent ounces during the quarter bringing year-to-date cash costs to $839 and all-in-sustaining cost to $1,159. Black Fox production is in line with our full year production and cost guidance for 2018. For 2018, we forecasted a total of $14.5 million for sustaining and capital expenditure activities at Black Fox mine of which we spent $10.6 million during the nine month period ending September 30. We're excited about the potential of our Black Fox property and we will be closely evaluating our options with respect to bringing on additional production from one of our satellite deposits at Froome, Grey Fox and Tamarack in the next 12 to 18 months. At the San Jose mine in Argentina production is in line with our full year production and cost guidance for 2018. According to our 49% interest in the mine, our attributable production in Q3 was $21,600 gold equivalent ounces at a cash cost of $856 and all-in-sustaining cost of $1,028 per gold equivalent ounce. Our year-to-date attributable production is $64,000 gold equivalent ounces. The cash cost of $864 and all-in-sustaining cost of $1,078. At Gold Bar construction is advancing on budget and on schedule for completion by the end of 2018, targeting production in Q1 2019. Activities at Gold Bar in Q3 focused on completion of the heap leach pad, the crushing and conveying system, and advancing the gold processing facility. We expect to complete commissioning of the crushing and stacking circuit by mid -November and then we will start loading the leach pads with ore. Our ADR plant is expected to be completed in mid-December after, which the cyanide leaching process would commence. Mining activities are progressing well. We pre-stripped one million tons of waste material at Gold Pick, and Cabin Creek. We're also mining ore from Cabin Creek pit and currently have approximately 100,000 tons of ore sitting on the ground in front of our crushing plant waiting to be placed on heap leach pad. We also have another 97,000 tons of ore Cabin Creek, waiting to be hauled at the crushing facility, so we're in great shape with regard to having ore ready to go on to leach pads. All major equipment and bulk materials are either onsite or purchased, engineering for the project is complete and 97% of the contracts are awarded. Exploration on the Gold Bar property restarted in November 2017 after receiving the construction permit from the mine. From the $5 million exploration budget for Nevada, we spent $1 million in Q3 adding to $4.2 million for the nine months ended September 30, 2018. At Los Azules, we forecasted $8.9 million in expenditures for the 2017 - 2018 exploration season. We spent $5.5 million during the year. The activity is focused on technical site investigations, environmental baseline monitoring work in order to advance our permitting efforts. As you can see Q3 was another quarter during which we delivered significant production and focused on the future production growth of our company. I will now turn it over to Sylvain Guerard our Senior Vice President of Exploration to expand on the exploration programs for our properties.