Thanks, Lauren. Over the past quarter, we've made very good progress on our suite of brownfields projects. Starting with Tasiast phase one, which is nearing completion, we've made excellent progress. The project is on budget and on schedule to reach 12,000 tonnes per day by the end of June and Tasiast itself is on track to meet the 2018 gold production estimates, which were contemplated in the feasibility study. We now successfully commissioned several components of the project, including detailing storage facility, upgrades to the power supply system several ancillary facilities. We are in the advanced stages of commissioning the new primary crusher, which is sites to the phase 2 throughout capacity of 30,000 tonnes per day. The crusher itself has been running a number of tests and we've achieved design throughputs. Construction is complete for the new components of the CIL plant, which includes the ball mill cyclones, new leach tanks, elution circuit screen, intensive leach reactor and a number of other components. These new elements have been successfully tied into the existing mill and the shutdown that Lauren referenced and commissioning is going very well. At the SAG mill, it is 97% complete and while we commission the SAG, we plan to temporarily use a buyback. This in combination with a new primary crusher in the CIL plant modification is expected to achieve throughput of 12,000 tonnes per day. During initial test runs in the past couple of weeks, the plant has reached throughput rates in between 11,000 and 12,000 tonnes per day and we've also pre-crushed a total of about 50,000 tonnes, using the new primary and existing secondary crushers, all of which is awaiting for us to see through the CIL plant. Last night, we also posted a video on our website, featuring a recent footage of the expansion and I'd encourage you to have a look for yourself to see how it has progressed. Moving over to Nevada, around Phase W, detailed engineering is approximately 90% complete and we started grading the new heap leach pad area and began earthworks in the infrastructure area. We've also commission two new electric rope shovels, which are now in operation to support certain activities, of which have advanced on plan. At Bald Mountain, Vantage complex project engineering is also 90% complete and the majority of procurement packages and construction contracts have been awarded. All major permits are also now in place and earthworks at heap leach are well underway. We remain on track for expected commissioning of the heap leach pad and processing facility at Bald in the first quarter of 2019. Turning to Chile, we’re to continuing to look at additional future development opportunities and particularly at La Coipa and Lobo Marte. With permitting events well underway, we’re planning a feasibility study as Paul mentioned in the middle of this year. At the same time, we are considering our options for how Lobo Marte may fit into our pipeline. This deposit you'll recall is located 80 kilometers by road from Lo Coipa and has an estimated 7 million ounces of M&I resources at 1.2 grams per tonne. Those were early days, but one concept that we're thinking about is the potential to start production at Lobo, following the end of La Coipa’s mine life. This could add a new project in the 2025 to 2026 timeframe. In summary, we've made very good progress on our projects and we look forward to updating on a number of important milestones later in the year, including completion of Tasiast Phase 1 and the upcoming results that yield more feasibility study. With that, I'll turn the call back over to Paul.