Paul Tomory
Analyst · CIBC. Please go ahead
Thanks, Lauren. We've got a lot on the go right now with our projects and exploration sites. We've got one of the most busiest and most productive quarters in recent memory. We've got the constructions of the Tasiast phase one expansion progressing well. We're in the final mile of the feasibility studies for Tasiast phase two and Round Mountain phase W. We're doing further work on expanding and upgrading resources at Bald. We're in the final stages of engineer for the Bald Mountain Vantage Complex project. And we're seeing encouraging results in Russia and at Tasiast on our priority brownfields targets. I’ll take you through some of the progress on each of these projects. Starting with the Tasiast expansion, it's progressing well and it's on schedule and on budget. We're now approximately, as Paul mentioned, 55% complete on construction and we have 85% of all required materials at site. Installation of the sag mill is progressing very well. The outer shell and the heads are on. Bolting is taking place, as we speak, and we started work on the trunnions and the upper portions of the gearless motor drives. Over at the crusher, and the picture is up on the slide here, the crush and the stockpile area, concrete work is in its final stages and the mechanical contractors for the crusher, apron feeders and conveyors have been mobilized. Over in the existing mill, construction results are progressing well on new leach thanks, cyclone towers, screens, intensive leach and other new elements. In addition, we've started some early commissioning. The oxygen plant has been commissioned and handed over to ops. And in the new tailing storage facility, we plan commissioning and handover to ops sometime in August/September – yeah, in the next several weeks. Phase two feasibility study is nearing completion and we expect to share those results with you in September, along with the results of the Round Mountain phase W feasibility study. We expect to make a decision on both of those projects at that time. Turning to Bald Mountain, we have two main areas of focus. First is development of the Vantage Complex in the South; and second, focusing on our exploration efforts to expand and upgrade the resources. Engineering work at Vantage is progressing well and the project team is now in place. We're in the midst of finalizing our execution plan and we expect to begin the initial works, procurement, and major capital spending in the first half of 2018. In terms of what are the main focus at Bald, expansion and upgrading resources, we continue to drill the Vantage deposit, including the South extension, Saddle and Luxe, and in the North area drilling is focused at the Top and Saga deposits and results continue to be encouraging. I’d like to conclude with a quick update on two of other priorities exploration targets. First, at Kupol, we have completed approximately 44,000 meters of core drilling in the first half of the year, but half of that was infill, but the north and the south strike extensions were the main vein. The results are encouraging, confirming our optimism from start of the year, and we expect to undertake geologic modeling and resource evaluation later this year to determine what potential mineral resource additions and reserve convergence we might have at year-end. Second, at Tasiast, drilling was focused on two deposits in the Tasiast Sud area, C613 and C615, which are located immediately south of the main West Branch deposit and just west of the Tamaya deposit, and as you can see there on the map on the slide. With approximately 13,000 meters drilled in the first six months of the year, C613 has been defined over approximately 2 kilometers a strike and is open south and north. While over at C615, it's been defined over 3 kilometers a strike. The majority of the mineralization at both these targets is within a banded iron formation, which is quite similar to what we encountered in the early years up at the Piment pits. Following these encouraging results, we have decided to accelerate the infill drill program with the goal of potential mineral resource additions at the year-end. Parallel to this, we've also initiated a PFS that contemplates a dump leach operation in the Tasiast Sud area, combining material from Tamaya, 613 and 615. In summary, we're making excellent progress on all our projects and exploration and we look forward to updating you on a number of these important milestones later in the year. With that, I'll turn it back to Paul.