Paul Tomory
Analyst · TD Securities. Please go ahead
Thanks very much Lauren. Very pleased to be joining the Kinross senior leadership team at a time when we have such a strong organic pipeline of developmental opportunities to extend life at many of our mines. So once we've got a strong technical team over the past few years and we're focused on advancing explorations completing our major studies and delivering on our approved projects. And I'll now update you on some of our key activities. As Paul mentioned, with the Tasiast Phase I expansion we are making good progress, we are on schedule, on budget, and we are on track to reach full production Q2 in 2018. We substantially completed engineering and the procurement of major capital packages and construction is on track approximately 20% complete this far with significant progress having made on earth works, concrete and the TSF. In fact the picture on the slide is a good view of the field of works right now looking from the primary crushers to the reclaim tunnel over to the segment on the background. Concrete, as I said, is well advanced with foundations of the SAG and the primary crusher now in place, and with work continuing on multiple fronts. Last week, we closed off the tailings, and that's the picture on the bottom right ahead of schedule and we're now proceeding with placement of the container and the liner. Major components of the SAG mill plant and primary crusher have arrived at site, and we expect installation of the SAG mill to begin later this month. With respect to the Tasiast Phase 2 feasibility study, it remains on track for completion in the third quarter of this year. Moving on to Bald Mountain, at year-end, we upgraded 1.2 million ounces of mineral reserves to proven and probable mineral reserves. Net depletion of 230,000 ounces, this resulted in a net increase of 1 million ounces, doubling Bald's gold reserve estimate to 2.1 million ounces. Of those, 670,000 ounces were converted in the North area as a result of drilling, resource, modeling, and mine plan optimization. And in the South area 560,000 ounces were converted as a result of our PFS work the Vantage Complex project. For the Vantage Complex project the scope of works in our pre-feasibility study includes the addition of a heap leach facility and the associated processing ad mining infrastructure. Just a note on a couple of numbers here, the Vantage project will require 28 million tons of capacity for the 560,000 ounces in the reserve, but we're designing a facility for 62 million tons to allow for an incremental 34 million tons from future deposits in the South area. On the exploration front in 2017, we plan to spend approximately 9 million with the goal of expanding and upgrading mineral resources in the North area, and at Yankee in the South. Turning to our Russia projects, in January we commenced stripping at September North East, the high-grade satellite deposit located 15 kilometers northwest of Dvoinoye. And on Moroshka the deposit located east of Kupol is on schedule to enter production in the first half of 2018. Construction of the portal is about 30% complete, and we started driving the twin declines. Moving over to Round Mountain Phase W, a drill program where the feasibility study continued during the fourth quarter. This resulted in an upgrade of 1.3 million ounces from inferred mineral resource to the indicated category, and an addition of 1.7 million ounces to inferred resources. A number of activities related to Phase W feasibility study are now fully underway, including mine planning, geologic modeling, mat test work, engineering, and permitting. The FS is on track for completion in Q3 of 2017. Moving now on to exploration, we put out a detailed update last night with the news release. And as mentioned, our priority for 2017 will be to intensify focus on extension of non-zones and mineralization at our mine sites. We believe that the best strategy continue finding economic ounces that add to mine life in the near-term. To give you an example of this and you can see it on the current slide with the long section at Kupol, mineralization remains open in certain zones. We are currently mining in the northern and southern zones, and also at depth. As we access some of those deeper zones it has become more efficient to drill from underground than from surface. Based on drilling that took place in the second half of the year we've identified potential targets for continued drilling and resource estimation work in 2017. On this long section again, on the left there's the 650 zone in the south, roughly in the middle the Big Bend deep zone, and over on the right the North Extension zone. Not shown on the long section is a separate mineralized zone located approximately 400 meters to the east of the main Kupol ore guardian. Some of our other priority targets for the year include Fort Knox, East and South Wall, and Kettle-River where we've identified some potentially promising opportunities in the Curlew District; still early days on a lot of these, but we're encouraged, and we'll keep you informed of our progress through the year. In short, to summarize, we've got a very strong pipeline of organic projects and promising exploration opportunities with the potential success in mine life and to add significant value to our existing portfolio. With that, I'll turn the call back over to Paul.