Rich Kruger
Analyst · Goldman Sachs. Your line is now open
Very good, Let's start with the Upstream, Upstream production averaged 407,000 oil equivalent barrels a day in the third quarter. This is 14,000 or 3.6% from the third quarter of a year ago. It's worth noting that the third quarter this year represented our highest third quarter production in some 30 years. And we achieved this result despite significant maintenance turnarounds in the quarter at both Kearl and Syncrude. The combined impact of this work from an Imperial share was an estimated 39,000 barrels a day 24,000 barrels a day at Kearl and about 15,000 barrels a day our share at Syncrude. As we look to the fourth quarter we would anticipate total production to be in the 380 to 390 kbd range Kearl and Syncrude both coming out of major maintenance work in October and November respectively and I'll comment a bit more on those turnarounds here in a moment. Moving to Kearl, on gross basis we produced 224,000 barrels a day in the third quarter. This was up from 207 kbd in the second quarter and this is our second highest quarterly production on record at Kearl with last year's third quarter being the highest. You may recall during our second quarter earnings call I gave some third quarter guidance suggesting we would produce somewhere between 215,000 and 220,000 barrels a day in the third quarter at Kearl. So our actual result's up about five to 10 kbd versus these earlier expectations. Year-to-date we're at 204,000 barrels a day through nine months and this puts us a couple thousand barrels a day above our nine months a year ago. We -- regarding the turnaround we began planned turnaround at one of our two plants at Kearl in the first half of September and it was successfully completed by mid-October about 33 days in total duration. The work scoped ores slurry prep equipment overhauls utility froth regulatory inspections and then hydro transport line installation and water tie-ins that are activities very key for our supplemental crusher startup and its operation thereafter. Cost of the turnaround work here at Kearl was about $70 million total $48 million to $50 million our share. I mentioned the duration 30-some days. And the work scope here was quite similar to the turnaround we had at this plant a year ago and the earlier in the year at our what we call our K2 plant in terms of duration impact cost a bit lower. We're getting better and better at planning and executing turnarounds. I mentioned supplemental crushing capacity of the project. That project continues on schedule for a year-end start-up. So we're coming down to the final weeks in a lot of commissioning work getting ready. And this again will support 240,000 barrels a day annual production in 2020 and beyond. Given the big increase year-on-year during our November 12 Investor Day we'll give a sense of what to expect on Kearl not only in terms of the annual average but we'll give you the kind of the seasonalized effect in the mining and how that occurs with first quarter being a bit lower than an annual average due to weather and other constraints. Second quarter often has some maintenance. Third quarter is when we get up and running in a big way. But we will take that 240,000 and give you kind of how we would suggest you consider that from a profiling standpoint. Moving onto Cold Lake, Cold Lake produced 142,000 barrels a day in the quarter up 7% from the second quarter. Relative to what I had conveyed earlier this is about 4,000 to 5,000 barrels a day lower than the guidance a quarter ago largely steam management production variations and we'll have much more on this in Cold Lake overall again on November 12. Fourth quarter we anticipate a quarter similar to the third quarter although somewhat as we get later in the year always the potential for somewhat weather dependent. But at this point we wouldn't anticipate that to be a big factor in the fourth quarter. Continuing on with Syncrude at 69,000 barrels a day our share in the third quarter, this was at the high end of our earlier communicated expectations where I had mentioned a quarter ago we anticipated 60 to 70 kbd. The turnaround work on one of Syncrude's 3 cokers the 8-1 began on August 23 as planned and it's expected to extend for about 75 days or into the first half of November. A lot of work scope here, double-digit processing units. The coker itself of course a hydrogen plant a lot of integrity and reliability upgrades improvements and our share of cost is a bit more than $90 million, so this is a big bit of work. We commented in the release it impacted production about 15,000 barrels a day our share in the third quarter. We would anticipate a fourth quarter impact to be comparable to that. So as we look to the fourth quarter we would expect production similar to the third quarter's 69,000 barrel a day. And if you roll that all together that would point to a full year outlook of plus or minus about 74,000 barrels a day our share. And a year ago at our Investor Day we pointed to the improvements we were striving to achieve at Syncrude and suggested a target over time of 75,000 to 80,000 barrels a day at Syncrude. We're kind of bumping up against that now in 2019. Crude-by-rail, with the -- when I thought through some of the comments I'd make here today we have even more information on what the government announced yesterday. But I think it's important to put it into context with the government of Alberta's curtailment order over this year crude-by-rail economics were certainly damaged and have largely throughout the third quarter continued to be weak. Shipments in the quarter for us declined each month from 76,000 barrels a day in July to 35,000 barrels a day in September 52 kbd average for the quarter. And in fact our last rail shipment was made in late September. And at this point based on kind of the -- an outlook fourth quarter rail shipments would have been expected to decrease from the third quarter level. Well with the TC Energy's key based -- Keystone leak government's announcement yesterday I would say the fourth quarter is -- I would have more confident saying it's kind of to be determined at this point than giving any specificity on what we expect rail movements to be, but I do think the quarter itself and over the course of the year the volatility has continued to highlight this negative unintended consequence of curtailment overall. Provincial inventories over the quarter have stayed and continued to drop a bit. You'll recall late last year at the end of the year and then largely through the first four, five months of this year provincial inventories were at or near tank tops roughly 35 million barrels or so. Inventories have declined over the past several months. The most recent data that I've seen per Genscape would report inventories somewhere 23 million 23.5 million barrels in kind of in the second half of October. And that we believe provides the industry cushion to continue to alleviate or reduce curtailed volumes and incent additional export capacity through rail or however, and there's a lot of flex-in the system that did not exist late last year nor largely for the first several months of this year. On August 20th, the government announced some revisions to the curtailment program increasing the operator threshold for those subject to curtailment from 10 kbd to 20. So as a result we are one of only 16 producers in Alberta that are subject to this order. Moving on on the Downstream in refining we averaged 363,000 barrels a day throughput in the quarte, This compared to 388,000 a year ago. July and August the first couple months of the quarter we're in the 390,000 range September closer to 310,000 to get to that average. September was impacted by start of a planned turnaround at our Nanticoke facility. Specifically that work started on September 9, part of regular periodic maintenance activities. four large units are out of service for catalyst replacement other general maintenance activities. The impact was an estimated 27,000 barrels a day or so in the third quarter and will be even more so in the fourth quarter plus or minus 50,000 to 60,000 barrels a day in the fourth quarter as we complete this roughly $90 million turnaround over a roughly -- a 70-day duration. That cost is a bit higher and the 70-day duration somewhat longer than I had suggested in the second quarter as we've had a bit more discovery work in just some challenges on workforce and productivity over it. But our current estimate would be about $90 billion -- or $90 million excuse me and about a 70-day duration. At Sarnia, we also had a turnaround start very late in the quarter September 29. This is about a 55-day activity with restart in the second half of November. The work scope is more limited here as one key unit the fluid cracker with inspection and repairs. On a throughput basis, the impact is quite minimal for the third quarter of course and also quite small for the fourth quarter just based on the nature of this work. Total cost of this turnaround is anticipated to be $45 million to $50 million, 55 duration, and these are precisely the estimates that we had shared when we outlined we'd be going into this work during our second quarter earnings call. A little bit of an update on the fractionation tower incident that occurred at Sarnia in early April. Work continues to replace the tower. The new tower has arrived at Sarnia in mid-October. It's been successfully lifted into place. Installation and commissioning is ongoing and we're on target for a restart expected sometime in the first half of December. And the throughput impact of it was -- I commented earlier it was about 35,000 barrels a day in the second quarter and it was about 20,000 barrels a day in the third quarter. It'll have about half that impact in the fourth quarter before we're up and running in a more regular manner. The cost and margin impacts of the Sarnia tower are generally consistent with our second quarter earnings call what I did feel at that point in time. If I look out over the remainder of the year and factoring the comments I've just outlined we would anticipate fourth quarter refining throughput with the major turnaround work continuing and ramping up and the commissioning of the new tower at Sarnia to be in the plus or minus about 320,000 barrels a day range and that would put a full year estimate of 350,000 to 355,000 somewhere. The last time we were at that level goes back to kind of 2016 when we had very similar high turnarounds in that year. And in fact 2019 is a much higher than a typical maintenance year with major work at two turnarounds at Sarnia and a major turnaround at Nanticoke. And I'd say the good news is that we can expect lower turnaround impacts in 2020 to 2021. This is a topic for another day but the timing and what you see this year is largely related to the periodic cycles three-year five year seven year whatever they happen to be on various units at our specific refineries. On petroleum product sales we were 488,000 barrels a day in the third quarter up 11 kbd from the second quarter. This again is consistent with the -- what we had earlier communicated in terms of somewhere between 480,000 and 500,000 barrel a day expectation. The Sarnia refinery addition or issues excuse me in addition to the higher than the planned maintenance across our sites is really largely behind where we were in the third quarter of this year versus where we were in the third quarter last year. And the third quarter last year was a record high a 30-year record high for us in terms of our product sales. Over the course of the third quarter volumes -- sales volumes increased coming out of planned and unplanned outages in the second quarter, but then here again they were impacted in September by the start of the turnaround in Nanticoke. Looking over the rest of the year fourth quarter I think something in the 480,000 barrel a day range would be a pretty reasonable assumption the end of the summer driving season. And if we look back over the last five years or so a 480,000 range would be consistent with kind of the mid-range of what we have seen recent years history in terms of fourth quarter sales. So with that, I would characterize the third quarter financial and operating performance as generally strong but more particularly in the Upstream and also in terms of kind of cash flow from operation Upstream performance record third quarter production even though we have significant maintenance activities and Downstream performance continued to recover from the Sarnia tower incident and was impacted by planned turnaround again most notably at Nanticoke. So I think, I'll stop there turn it back to Dave and he can kick off our Q&A.