Paul Chawrun
Analyst · SCP
Thank you, Richard, and hello to everybody. So turning to Slide 5. During my first 3 months with i-80, I've had the chance to evaluate our operations and development projects. We determine their technical status, additional work required and to identify opportunities to optimize execution, ramp up of personnel and potentially accelerate timelines. Some initial observations stand out. We have a solid geological understanding of our assets, underpinned by high-grade resources with meaningful growth upside. The supporting technical work required is relatively low risk positioning us well to advance our projects with confidence. We have a significant resource base with 6.5 million ounces of measured and indicated gold resources and 7.5 million ounces of inferred resources following prior years of extensive drilling and as well, approximately 100 million ounces of silver in each of the 2 categories. The 2025 drill program is progressing well, with a focus on infill drilling to advance technical studies. Next, we have access to a deep bench of experienced operating and technical mining talent. Our team brings decades of technical and operating experience from other major mining operations in Nevada. Recently, we have hired additional personnel in Reno and at the operations to execute on our growth plan. Next, we have industry-leading environmental, health and safety systems and controls. And lastly, i-80 has an established presence in the local community and trusting relationships with regulatory agencies, creating pride and commitment within our workforce. Moving to Slide 6 for a look at Granite Creek underground. Mining volumes during the second quarter were ahead of the prior year period. We mined approximately 24,000 tons of oxide mineralized material at a gold grade of 11.4 grams per tonne and approximately 11,200 tons of sulfide material at a gold grade of 7.4 grams per ton, plus an additional 16,000 tons of incremental low-grade oxide material at a gold grade of 3 grams per ton. For the quarter, just under 6,000 ounces of gold were sold, of which approximately 1/4 of the ounces were leached and sold from the Lone Tree heap leach facility. Approximately 28,000 tons or 7,000 ounces of sulfide mineralized material were stockpiled for processing at a third-party facility. We are encountering higher-than-expected levels of oxide mineralized material at Granite Creek underground compared to our March 2025 PEA. On the dewatering program, the team has shifted to a more proactive long-term approach and continues to upgrade the infrastructure. These upgrades include the planned installation of 2 additional surface dewatering wells, which is one more than initially planned at the beginning of the year based on the new predictive groundwater model. It includes expansion of the water treatment facility and upgrades to the existing underground water management infrastructure. We expect groundwater inflows to remain at or near the current ingress rates for the foreseeable future. However, by installing these mitigation measures, water inflows are not expected to impede our development planning for the long term. With the proper dewatering infrastructure in place, continued drilling, further technical work over the next 6 to 12 months, Granite Creek has the potential to be an excellent asset for us. At Lone Tree and Ruby Hill, we continue recovering gold from the existing leach pads with approximately 2,400 gold ounces recovered and sold in the second quarter. Company-wide, we expect to extract between 30,000 to 40,000 ounces of gold in 2025, in line with guidance. This includes 20,000 to 30,000 ounces of gold from Granite Creek and approximately 10,000 ounces from the heap leach pads. At Granite Creek underground, we completed the underground exploration drift, providing access for infill drilling in the prospective South Pacific zone. We currently have a total of 2 rigs underground and 3 at surface with more than 40 holes planned for a total of approximately 46,000 feet. The program is designed to upgrade the mineral resource and form the basis for the upcoming feasibility study planned to be completed for the first quarter of 2026. Next, let's turn to Slide 7 for an update on our second planned underground mine. At Archimedes, the upper level permitting is nearly complete, which covers mining activities above the 5,100 foot level, while we focus on geochemistry and technical studies to support permitting needed for the lower levels. With surface infrastructure to support the portal now complete, development of the underground exploration drift is scheduled to commence in the next several weeks. Infill drilling of the Upper Zone is expected to start in the fourth quarter followed by the lower zone in Ruby Deeps by the first quarter of 2026. In total, the program will comprise of over 175 holes and 197,000 feet with results feeding into a feasibility study targeted for the first quarter of 2027. With our committees progressing well, let's turn to Slide 8 for the status on Cove. At Cove, we are actively advancing major permit applications in anticipation of an EIS, which is planned for completion by the end of 2027. Following the completion of a 145,000 foot infill drilling campaign completed in the first quarter, we now plan to provide an updated mineral resource estimate this quarter followed by a feasibility study targeted for the first quarter of 2026. It is important to note that the current mineral resource estimate for Cove does not yet include drilling completed in recent years. Results to date have been encouraging and are consistent with traditional Nevada Carlin-style mineralized systems, meaning generally high conversion rates of resources to reserves. Turning to Slide 9 for a look at our Lone Tree processing facility. Lone Tree's plant and autoclave refurbishment study is expected in Q4. The refurbishment is highly achievable due to the low amount of construction hours minimal long-lead equipment and strong local contractors available in Northern Nevada. In addition, engineering is being completed by Hatch, an industry leader in autoclave plant technology. Recruitment of the owner's team is also underway to oversee the engineering and execution, and we are reviewing the schedule for early works opportunities to accelerate the time line. Commissioning the Lone Tree plant provides processing capacity of refractory material fed directly from our operations. It increases the payability on refractory material from a range of 55% to 60% up to approximately 92% recovery, which translates to a range of approximately an additional $1,000 per ounce versus toll milling depending on the grades processed and the price of gold. For this reason, Lone Tree is a cornerstone of our plan and is being prioritized. Now looking at Slide 10. Drilling at Mineral Point open pit began in June with 2 surface core rigs completing approximately 5,800 feet to collect baseline technical data, supporting initial permitting and the next phase of technical studies. Strategic reviews of the technical work completed to date are currently underway to determine the timing of a pre-feasibility or feasibility level study. Now over to Ryan for a financial review.