Bruno Lemelin
Analyst · CIBC World Markets
Thank you, Maarten. Starting with Côté Gold. As Renaud noted in the opening remarks, this was an important quarter for Côté as the mine transitions from ramp-up to optimization and stability. We are very proud of our progress at the mine. 16 months ago, on March 31, Côté poured its first gold bar followed by commercial production 4 months later and ultimately achieving nameplate throughput of 36,000 tonnes per day on June 23, well before the 20-month estimate at project initiation. Looking at the quarter, Côté produced 96,000 ounces on a 100% basis. Mining activity totaled 11.8 million tonnes in the quarter with 3.2 million ore tonnes mined equating to a strip ratio of 2.7. The average grade mined increased from the prior quarter to 0.95 gram per tonne, in line with the updated mining plan as in-pit activities continue to broaden the mining area within the pit to support the transition to bulk mining. On a cost basis, we saw unit mining costs of $3.88 per tonne due to the higher-than-expected diesel consumption associated with additional rehandling as well as contractor costs, consumable parts related to an increase in drilling, loading and blasting activities. Mining costs are expected to reduce in the second half of the year closer to the $3.50 a tonne level. This will be achieved by targeting an objective of 1 million tonnes a week and the reduction of rehandling through an increased proportion of direct feed material, coupled with improved blasting and pit management. Turning to processing. Mill throughput totaled 2.9 million tonnes with successive increases in throughput each month during the quarter. Head grades of 1.1 per tonne were in line with plan, with feed material comprised of a combination of direct-feed ore and stockpiles. Mill recoveries averaged 93% in the quarter, beyond plan as well we believe we are seeing the benefits of the micro fracturing created by the HPGR. Reconciliation between the reserve models, grade control models, mill feed and production continues to be in line with expected tolerances with Q2 exit production seeing 7% positive reconciliation to both reserve tonnes and grade. Milling unit costs saw quarter-over-quarter improvement to $6.94 per tonne milled, though they remain elevated from our target of about $12 per tonne. Unit costs are impacted by the supplementary crushing and coarse ore refeed activities, which have performed well to provide additional capacity during maintenance windows, but come at an increased cost. The supplementary crushing is temporary, and we expect unit cost to decline following the installation of the additional cone crusher in the fourth quarter. Looking ahead, we remain confident in our Côté Gold production guidance of 360,000 to 400,000 gold ounces on a 100% basis, which is essentially a doubling of production from last year. The primary focus continues to be the stabilization of the processing plant to operate at or above the design capacity of 36,000 tonnes per day. On costs, as Renaud highlighted, cost guidance has been revised. Cash costs are now expected to be in the range of $1,100 to $1,200 per ounce sold and all-in sustaining cost is now expected to be $1,600 to $1,700 per ounce sold. The cash cost increase is primarily associated with higher royalties due to the higher gold price equating to an increase of about $50 to $60 per ounce, coupled with the higher than planned cost to operate the temporary coarse ore refeed crushing circuit and higher maintenance costs that contributed close to $150 per ounce over the course of the year. The all-in sustaining cost revision includes the additional $20 million or $40 per ounce for the additional nonrecurring capital to improve overall plant availability and operating conditions, including thus mitigation systems inside the facility. We are looking forward to seeing the impact of the installation of the second cone crusher in Q4, which will provide further capacity and flexibility in the dry side of the plant in support of the operation and potential future expansions, which leads us to what is the most exciting slide, the advancement of the Côté Gosselin super pit scenario. Our drills are busy at work with over 32,000 meters completed on the 45,000-meter program. This program is prioritizing the resource conversion at Gosselin to provide the foundation for an updated technical report that is expected to outline a significantly upsized reserve base combining Côté and Gosselin into a super pit. This report is expected to be released in the second half of next year. As currently designed, Côté has the mining capacity to average an annual ore mining rate of 50,000 tonnes per day versus our current nameplate processing rate of 36,000 tonnes per day. As part of the 2026 technical report, we will look to find the right balance between an increased processing rate with mining rates targeting the combined Côté Gosselin super pit. It is interesting to note that the Côté deposit itself has over 400 million tonnes of measured and indicated material. If mined at a rate of 20 million tonnes of ore per year or 50,000 tonnes per day, the Côté deposit itself would have a mine life of potentially 20 years prior to bringing Gosselin into plant. This would allow for considerable flexibility for phased permitting and capital outlays. Altogether, there is a significant amount of value to continue to uncover at Côté. Turning to Québec. The second quarter at Westwood saw improvement from the prior quarter with production of 29,000 ounces as the mine operates through some lower grade stopes and conducts, additionally underground activity to set up the mine for a stronger second half. Underground mining totaled 98,000 tonnes, averaging nearly 1,100 tonnes per day as volumes from the underground continued to increase compared to the prior year and previous quarters. Production drilling has continued to improve quarter-over-quarter, achieving 193 meters per day, a record since the mine restarted in 2021, building confidence that our underground mining methodologies and systems are proving to be effective. [ Falagountou ] satellite open pit reported 315,000 tonnes mined, higher than the previous quarters, in line with the mining schedule. Mill throughput in the second quarter totaled 323,000 tonnes at an average head grade of 3.07 grams per tonne. The strong throughput was due to plant availability in the quarter of 96%, which is -- which was higher than the same prior year period of 89%. The mill achieved recoveries of 92% in the second quarter 2025, in line with the same prior year period. Cash costs and all-in sustaining costs came in above our updated guidance ranges for the year as production is expected to be second half weighted with cash costs averaging $1,562 an ounce and all-in sustaining averaging $2,140 an ounce in the quarter. Looking ahead, we remain confident in Westwood's ability to meet our production guidance with production of 125,000 to 140,000 gold ounce. Underground mining rates are expected to be maintained at around 1,000 tonnes per day from multiple active mining zones, while grade is expected to increase in the second half of 2025 as the mining sequence transitions to higher grade zones during the period. As previously discussed, cost guidance has been revised and cash costs are now expected to be in the range of $1,275 to $1,375 per ounce sold and all-in sustaining costs to be between $1,800 to $1,900 per ounce sold. Unit costs were higher in the first half of the year due to higher mining and maintenance costs combined with lower production from lower average grade relative to plan in the first half of the year. Unit costs are expected to decline in the second half of the year on higher production expectations. Turning to Essakane. It was a challenging quarter as we work through the lower grade of the upper benches of Phase 7, while being impacted by higher costs from increased royalties, a stronger Euro, increased maintenance and consumables costs and a higher proportion of stripping activities being expensed. Production of a 90% basis -- on a 90% basis Q2 totaled 77,000 ounces. Mining activity totaled 10.7 million tonnes with ore tonnes mined of 2.2 million tonnes equating to a strip ratio of 4:1. Mill throughput was 3.1 million tonnes at an average head grade of 0.93 gram per tonne. The grade decreased as the mining activities progress through the upper benches of Phase 7. Grades tend to reconcile slightly below the reserve model during the earlier stages for the mining a new phase and conversely to the positive as mining moved deeper into the phase as we saw in the first half of 2024, when we were mining the later stages of Phase 5. The transition to the higher grade benches in Phase 7 occurred later than forecast with increases in grade materializing subsequent to quarter end. On a cost basis, Essakane reported cash cost of $1,855 per ounce and all-in sustaining cost of $2,224 per ounce in the quarter. Costs were higher in the quarter due to a lower proportion of capitalized waste in the period, higher maintenance activities and an increase in consumable costs, including diesel and grinding media. Labor, contractor and facility costs also increased due to the appreciation of the local currency, which is pegged to the Euro. Royalties accounted for $257 per ounce in the quarter, representing an increase of nearly $100 per ounce from the prior year period, primarily due to higher realized prices and a revision in royalty rates. Looking ahead, we estimate that Essakane will be on the lower end of the attributable production guidance target ranging from 360,000 to 400,000 gold ounce. The guidance -- this guidance accounts for the revision of the company's interest in the projects to 85% from 90% previously. Our Essakane cost guidance has been revised and cash costs are now expected to be in the range of $1,600 to $1,700 per ounce sold and all-in sustaining cost is now expected to be between $1,850 to $1,950 per ounce sold. Costs at Essakane are higher than planned, primarily due to the increased royalty rate previously mentioned and the impact higher gold prices have on royalties, resulting in an increase of approximately $77 per ounce and the continued impact of a stronger Euro on operating costs. While the cost of operation in country have risen over the recent years, Essakane continues to be a world-class mine and is positioned to generate significant free cash flows moving forward. Finally, it is worth highlighting that work is ongoing at the second largest gold mining camp, the Nelligan and Monster Lake project in Chibougamau, Quebec. Year-to-date, we have completed over 12,000 meters of drilling at Nelligan with an upsized drill program of 15,000 meters and 11,000 meters of drilling at Monster Lake. The Nelligan program prioritized the extension of the deposit at depth. Nelligan's mineral resources estimate was updated earlier this year, which saw indicated ounces increase to 3.1 million ounces with an average grade of 0.95 gram per tonne and an additional 5.2 million ounces in inferred at similar grades. We plan to have assay results from this program later in the year as we work to grow Nelligan, targeting over 10 million ounces, making it among the largest undelivered gold project in Canada. With that, I will pass it back to Renaud. Renaud?