Larry Radford
Analyst · CIBC. Your line is now open
Thanks Lindsay. I've been in mining for 35 years and of those 35 years, half of it’s been in Nevada. So, taking personally to be back in the Nevada and I think it’s a great move for Hecla. I want to walk you through some of our thinking for the rest of 2018 on Slide 10. The first priority is to get Nevada operations working as an integrated operation, where we have three mines and one mill. As a coherent unit, we will move personnel and equipment around under the direction of one Vice President and General Manager, Kevin Shiell, and we'll prioritize the resources in these operations that make the most profit. As such, we’re working on a unified mine plan and expect to ramp-up production at Fire Creek and at the begin development of Hatter Graben. We are ramping down Midas and moving personnel and machines as appropriate to Hollister and Fire Creek. In the mill, we expect to complete installation of the carbon screens and all the leach tanks providing a robust CIL process capable of processing Hollister ore by the end of the year. We’re also installing sampling equipment in the front-end of the mill to better reconcile each mine to the mill. We continue at the tailings facility construction and we’re targeting year-end for its completion. At Fire Creek, we need to rehabilitate the existing mine access first, followed by a period of intense development targeting an increase in the development rate of 50%, as it has been underfunded with capital. We then expect to ramp up the tons per day of ore produced from 350 to the target of 550 tons per day, an increase of 57%. In some areas of the mine, the road conditions are muddy, and our Vice President of Technical Services introduced an engineered roadbase, which includes a new water-wick in geotextile that allows trucks to move through these areas. On Slide 11, you can see some photos I took last week from the 4 Haulage drift and Spiral 3 areas in Fire Creek. You can see the substantial improvement, this fabric in the aggregate that was imported and improvement that was made for trucks to go through these areas. The mud is only an issue in isolated areas, but conditions would get bad enough if machines will get stuck and would have to get towed-out. You can see the dramatic improvement from the before and after pictures, which is why the on-site team called it the magic carpet that is over for too earlier. Spent a couple of days of closing. We had moved our [indiscernible] plant from the now closed Troy mine to Fire Creek. We will move [indiscernible] equipment from Midas to Fire Creek, so we can include [indiscernible] Creek in the development cycle, reducing the need to go back and rehabilitate later, which was a problem for Klondex. Improving the development is key to create value at Fire Creek. Klondex was not able to keep up with the development at 350 tons per day and as we increased throughput to 550 tons per day, we will need to do 15,000 feet of development per year. For reference, this is about half of the annual development at Casa Berardi. Fire Creek development and definition drilling represents about half of the Nevada assets $20 million capital for the remainder of 2018. Also included is another 5 million or so in the tailings down construction as shown on Slide 12, and another 2 million for completion of the CIL circuit. We expect the dam to be completed in November and fully functioning by December. The previous tailings facility is expected to be full by then. Outside of Nevada, we also moved 10 million of R&D cost in the capital as the Remote Vein Miner is now under construction in Sweden. And we will invest another 4 million in both Greens Creek and San Sebastian. On Slide 13, you can see Greens Creek had another excellent quarter, producing 2 million ounces of silver at a cost of sales $48 million, and a cash cost after by-product credits of negative $3.47 per silver ounce. The all-in sustaining cost after by-product credits was $4.43 an ounce. We continue to advance our work to transition the fans to ventilation on demand to utilize the tele-remote LHDs and to implement computer assisted jumbo drilling. Slide 14, Casa Berardi had a great second quarter. Gold production was up 42,000 ounces, costs were down, capital spending declined as well. The mine is performing well and both grade and throughput were strong. The autonomous truck continues to impress in the 985 Drift as seen here on Slide 15, and if you came to our mine in July you would have seen how well it is operating. In fact, the performance is already considerably better than we thought it would be as you can see on Slide 16. We can load the truck faster, and it has a much shorter cycle time, a 90% availability, and fuel consumption is down 17%, and we think it will eventually be even higher than that. In the near-term we’ll complete slashing tight spots in the drift, which should enable the autonomous truck to drive faster. Additionally, we expect to have a second autonomous truck in operation in the fourth quarter. Savings from our running two trucks autonomously should be $3 million to $4 million a year. At Lucky Friday, we remain convinced that we need a safer way to mine at the mile and a half of depth. Our focus is on preparing for the Remote Vein Miner as seen on Slide 17. What could revolutionize how the Lucky Friday operates, we’re placing drilling glass with a much more efficient cutting technology. We’re working on an excavating a chamber to be used in 2019 to reassemble the machine at underground once the pieces are sent down the shaft. So, stay tuned on to this. We will have much more to say about it over the next year or so. At San Sebastian, we’re seeing improved underground mining performance as you can see on Slide 18. To improve the underground mining rate, we invest in development in the first half of the year, which led to a higher all-in sustaining cost, after by-product credits per gold ounce in prior quarters. A reduction in per ounce cost is expected in the second half of the year as underground production continues to ramp up. We plan on collecting a 12,000-ton bulk sample of the Hugh Zone on the Francine Vein the fourth quarter and then process this material through a third-party mill to test its suitability. If at all we [escorting the plan] we should be advancing the development into this area to ensure secondary access and then mining this area by late in 2019. It could mean another five or more the years of mine life at San Sebastian. I will now pass the call over to Dean.